Decision The Cabinet Member for Transport: 1. Approved the appointment of Mildren Construction Ltd to undertake the design and build pavement replacement at the bus apron; 2. Approved that the appointment should take place in advance of the conclusion of the ongoing legal process due to the risk that further delay in the pavement replacement could result in an unplanned substantial failure which would lead to vehicles not being able to access the bus apron. Electric Vehicle Charging Points Update The Chair provided an update on the current discussion with the 3 companies responsible for managing and providing the EV charging point situation. The Chair advised the initial bid for the points was to the ... view the full minutes text for item 51.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To agree to enter into a design and build contract to replace the pavement at the Hard interchange bus apron.
Recommendations
It is recommended that the Cabinet Member for Transport approves:
1.2The appointment of Mildren Construction Ltd to undertake the design and build pavement replacement at the bus apron.
1.3That this appointment is to take place in advance of the conclusion of the ongoing legal process. There is a risk that further delay in the pavement replacement could result in an unplanned substantial failure which will lead to vehicles not being able to access the bus apron.
Background
2.1The Hard bus interchange and accompanying apron was originally constructed in the 1970s.
1 www.portsmouth.gov.uk 2.2. This sits on a sub-structure that is piled into the seabed. The sub-structure comprises a network of piles, upon which rest a number of reinforced beams and slabs.
2.3The condition of the bus apron has deteriorated following opening of the new bus station. This has led to cracking of the surface, which, if left unattended will mean that the buses will no longer be able to continue using the interchange.
2.4To temporarily prolong the life of the pavement, regular "topping up" of the cracks and potholes takes place every few weeks. Whilst every few months, a deeper "intervention" is required, where the pavement is excavated to a greater depth, and new material put in place. These interventions are required on an increasingly more regular basis and are currently costing around £150,000 per year.
Procurement process 2.5. The Council went out to tender in early 2023 via Hampshire County Council's Gen 4.2 framework to replace the pavement of the bus apron and two service roads, Hertha Ayrton Way (HAW) and Millennium Way (MW). A preferred contractor, Mildren Construction Ltd. (Mildren) was identified in summer 2023.
2.6Following this, a period of scope review took place. Ramboll consultants, Mildren and the Council's project team took the opportunity to reevaluate the scope. While the bus apron pavement is failing, HAW and MW only have superficial defects and do not require full replacement at this stage. This resulted in de-scoping the works to focus on just the bus apron, rather than HAW and MW.
2.7By focusing on just the bus apron, this minimises passenger and interchange user disruption by having a construction program of total bus apron closure of around four months.
2.8Prior to entering into contract, procurement Gateway C will need approval, as per the Council's Contract Procedure Rules.
Contract outputs 2.9. An outline design has been prepared by Ramboll. The design proposes removing approximately 490mm of pavement on top of the structure down to the waterproof layer.
2 www.portsmouth.gov.uk Figure 1 - Existing bus apron pavement to be removed (image produced based on Trial Holes investigation)
2.10The proposed reinstatement pavement is composed of concrete, Cement Bound Granular Mixture (CBGM) and foam concrete as illustrate in figure 2 below.
Figure 2 - Proposed Layer Composition (image from Tender Submission)
2.11Once appointed, Mildren will develop this into a detailed design, and if acceptable, will be instructed to enter into the build stage of the contract.
3 www.portsmouth.gov.uk Impact on transport network 2.12. During construction works, the bus apron and taxi rank will be closed. The bus terminal itself will remain operational, along with the associated concessions and toilet facilities.
2.13HAW and MW will remain open to allow pedestrian and service access to the bus terminal, in addition to the usual access for Network Rail, Gosport Ferry and IoW catamaran.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Residents Parking Zones Future ProgrammeDECISION The Cabinet Member for Transport: 1. Approved progressing the RPZs Future Programme for proposed new zones a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.