Highway Asset Management - Intervention Criteria and Repair Frequency Regime
ApprovedPlanning1 paper
Strategic Environment, Planning and Transport Committee approved this item on Monday 15 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved – (1) That the 6-month trial to reduce the carriageway safety defect intervention level criteria be approved; (2) That the change to the highway safety defect repair times in respect of Category R1 with effect from April 2021 be approved.
Word for word from the decision Reading published for this meeting.Source: democracy.reading.gov.uk
Report to Strategic Environment, Planning and Transport Committee
READING BOROUGH COUNCIL
REPORT BY DIRECTOR OF ECONOMIC AND NEIGHBOURHOOD SERVICES
TO: STRATEGIC ENVIRONMENT PLANNING & TRANSPORT COMMITTEE
DATE: 15th MARCH 2021 TITLE: HIGHWAY ASSET MANAGEMENT - INTERVENTION CRITERIA AND REPAIR FREQUENCY REGIME.
LEAD COUNCILLOR PORTFOLIO: STRATEGIC ENVIRONMENT, COUNCILLOR: PAGE PLANNING AND TRANSPORT SERVICE: ENVIRONMENTAL & WARDS: BOROUGH WIDE COMMERCIAL SERVICES LEAD SAM SHEAN TEL: 0118 937 2138 OFFICER: JOB TITLE: STREETCARE SERVICES E-MAIL: [email protected] MANAGER 1.0 PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The purpose of this report is to seek approval to amend the intervention level criteria in relation to highway defects for a trial 6-month period and to seek a change to highway safety defect repair times.
1.2The Council is making a £9M Capital Investment into residential roads and pavements over 3 years which is addressing the repair of residential roads in most need. This programme has reduced the demand on pothole repairs considerably and has enabled the transition to addressing defects of a lesser depth manageable.
1.3The Council’s current highway safety defect repair frequency regime currently requires ‘Category R1’ repairs to be completed within 24 hrs. It is proposed to amend this to ‘the next working day’.
1.4The report sets out the current position and the options available in relation to the proposed changes.
2.0RECOMMENDED ACTION
2.1That the Committee notes and approves the 6-month trial to reduce the carriageway safety defect intervention level criteria.
2.2That the Committee notes and approves the changes to the highway safety defect repair times. 3.0 POLICY CONTEXT
3.1To secure the most effective use of resources in the delivery of high quality, best value public service.
3.2To make travel more secure, safe and comfortable for all users of the public highway.
3.3To provide a public highway network as safe as reasonably practical having due regard to financial constraints and statutory duties.
4.1Reading Borough Council currently class an actionable carriageway defect as having a minimum of 50mm depth over an approx. area of 300mm x 300mm. The Highway Inspector can also action defects of a smaller size if they are concerned that leaving that defect would pose too great a risk when taking into account various criteria including the location within the highway, traffic and pedestrian volumes and the classification of the road.
4.2The Highways Team reviewed their inspection and repair regime 3 years ago. Service improvements include the introduction of an electronic system allowing inspections to be carried out by handheld tablet with the defects being sent electronically to the Highways & Drainage Manager who then assigns them to the repair gangs directly on their tablets. This has shown an increase in efficiency of the whole process and repairs response times have improved significantly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Environment, Planning and Transport Committee at Reading and we tell you when its next papers are published, before the meeting rather than after it.
Strategic Transport Schemes UpdateResolved – (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
Strategic Transport Schemes UpdateResolved - (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.