Strategic Environment, Planning and Transport Committee noted this item on Monday 14 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved – (1) That the outcome of the six month trial to reduce the highway investigatory level safety defect criteria in the carriageway be noted; (2) That the proposed change to the highway investigatory level safety defect criteria in the carriageway, as set out in section 4 of the report, be approved.
Word for word from the decision Reading published for this meeting.Source: democracy.reading.gov.uk
LEAD COUNCILLOR PORTFOLIO: STRATEGIC ENVIRONMENT, COUNCILLOR: A PAGE PLANNING AND TRANSPORT
SERVICE: ENVIRONMENTAL & WARDS: BOROUGH WIDE COMMERCIAL SERVICES LEAD SAM SHEAN TEL: 0118 937 2138 OFFICER: JOB TITLE: HIGHWAY & TRAFFIC E-MAIL: [email protected] SERVICES MANAGER 1.0 PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report seeks to inform the Committee on the outcome of the 6-month trail to lower the investigatory level safety defect criteria in relation to highway carriageway defects.
1.2This report seeks Committee approval to formally adopt the lower Investigatory level safety defect criteria in carriageways following the successful 6-month trial.
2.0RECOMMENDED ACTION
2.1That the outcome of the 6-month trial to reduce the highway investigatory level safety defect criteria in the carriageway be noted;
2.2That proposed change to the highway investigatory level safety defect criteria in the carriageway, as set out in section 4 of this report, be approved.
3.0POLICY CONTEXT
3.1To secure the most effective use of resources in the delivery of high quality, best value public service.
3.2To make travel more secure, safe and comfortable for all users of the public highway.
3.3To provide a public highway network as safe as reasonably practical having due regard to financial constraints and statutory duties.
4.0PROPOSED CARRIAGEWAY SAFETY DEFECT INVESTIGATORY LEVEL CRITERIA 4.1 Reading Borough Council prior to the 6-month trial classed an actionable carriageway defect as having a minimum of 50mm depth over an approx. area of 300mm x 300mm. The Highway Inspector can also action defects of a smaller size if they are concerned that leaving that defect would pose too great a risk when taking into account various criteria including the location within the highway, traffic and pedestrian volumes and the classification of the road.
4.2The Highways Team reviewed their inspection and repair regime 3 years ago. Service improvements include the introduction of an electronic system allowing inspections to be carried out by handheld tablet with the defects being sent electronically to the Highways & Drainage Works Manager who then assigns them to the repair gangs directly on their tablets. This has shown an increase in efficiency of the process and repair response times have improved significantly.
4.3In should be noted that the Council’s £9M Capital Investment into residential roads and pavements over 3 years (2020/21 to 2022/23) is addressing the residential roads in most need. Associated with this programme is an extensive pre-patching regime in advance of surfacing, which is addressing defects of a lesser depth and increasing the structural integrity of the carriageway prior to surfacing. This programme has reduced the demand on pothole repairs, which, along with the service improvements mentioned above, enabled the transition to addressing defects of a lesser depth manageable. This improved efficiency provides an opportunity to review our current safety defect investigatory level criteria. By amending the investigatory level criteria to anything over 40mm depth over an approx. area of 300mm x 300mm, then in theory the Council should be able to improve customer satisfaction, road safety and improve on an existing good record of successfully defending public liability claims, as we would be treating some ‘defects’ earlier than we currently do. Analysis of our performance compared with our standard defect repair times has shown that the Highway Works Team are exceeding the performance standard for repair times, (defects are being repaired quicker than required), which shows that there is currently capacity to continue with this lower investigatory level criteria.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Environment, Planning and Transport Committee at Reading and we tell you when its next papers are published, before the meeting rather than after it.
Strategic Transport Schemes UpdateResolved – (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
Strategic Transport Schemes UpdateResolved - (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.