Resolved
That we (i) agree the outline schemes and estimates for the projects in the “Building Maintenance – D3 Priority” and “Building Maintenance – C2 Priority” provision in the Libraries Service Capital Programme for financial year 2004-5, as listed in Appendix A to the report, noting that the costs given are approximate; (ii) agree that the Chief Engineering & Building Services Officer be authorised to manage any variations in costs across the component schemes within the overall resources available of £126,000 and within the constraints imposed by Standing Order 111.6; (iii) approve the total expenditure of £126,000 from the Libraries Service Capital Programme for the schemes identified in the appendix to the report;