Item11
Resolved
That we (i) note the officers comments on the reference from Area 5 Committee that any profit generated from the parking bays after deductions of operational and management costs be returned to their Committee budget; and (ii) agree that because of the strategic nature of Green Lane and the need for strategic solutions to the parking problems in this road Area 5 Committee be advised that officers in Engineering and Building Services will review both need and current provision as soon as resources are available and prepare proposals for the entire route. Until this is complete the works proposed by Area 5 should be deferred. ([name removed] and Councillor Staight spoke on this item). (These decisions were subsequently requisitioned to Council).