Item28
Resolved
That we (i) a ccept the second stage tender from Elliott Group Limited in the sum of £2,443,465.00 for the design and construction of a new Classroom and Sixth Form Block at Valentines High School in accordance with the first stage tender and the variations arising from the second stage tendering process as outlined in the report; (ii) agree the changes to the Children’s Services Capital Programme as detailed in appendix B; and (iii) agree that the capital allocation remaining after the phase 1 tender has been taken into account will need to be retained until the tenders for phase 2 are received and the total cost for the whole scheme is known.
Word for word from the decision Redbridge published for this meeting.
Source: moderngov.redbridge.gov.uk