Item16
Resolved
That we (i) agree the outline scheme for creating a new Children’s Resource Centre and Children’s Centre at the site of the current Albert Road Family Day Centre as further described in Appendix A and shown in Appendix B to the report ; (ii) agree the outline estimate in the sum of £1,159,000 for creating a new Children’s Resource Centre and Children’s Centre at the site of the current Albert Road Family Day Centre as further described in Appendix A and shown in Appendix B to the report; (iii) authorise the Director of Children’s Services to proceed with obtaining further detailed design and to seek tenders for the creation of a new Children’s Resource Centre and Children’s Centre at the site of the current Albert Road Family Day Centre; (iv) approve the total expenditure of £709,628 from the Children’s Services Children’s Service Capital Programmes for 2006 / 2007 and 2007 / 2008 in respect of the new Children’s Resource Centre and Children’s Centre at the site of the current Albert Road Family Day Centre ; and (v) agree to waive the application of Standing Order 93 requiring competitive tendering and to agree that the project for creating a new Children’s Resource Centre and Children’s Centre at the site of the current Albert Road Family Day Centre be awarded to Geoffrey Osborne Limited under the Collaborative Framework Contract. Actions: Brian Stoneham Ext. 83624 Frank O'Neill Ext. 83117
Word for word from the decision Redbridge published for this meeting.
Source: moderngov.redbridge.gov.uk