Item22
Resolved
- That, subject to the agreement of resources by Budget Council, we (i) agree to progress the works on the pavilion; (ii) agree the scheme and estimate for the proposed pavilion refurbishment and remodelling works in the sum of £1,695,000 as set out in Appendix B to the report; and (iii) accept the most economically advantageous tender in respect of the main refurbishment and remodelling package, that of Lengard Ltd. in the sum of £1,226,522.49 as set out in Appendix C to the report.
Word for word from the decision Redbridge published for this meeting.
Source: moderngov.redbridge.gov.uk