Loxford School of Science & Technology - Building Schools for the Future - One School Pathfinder - Appointment of ICT Contractor (CAB/25/170209)

Agreed Executive

Cabinet agreed this item on Tuesday 17 February 2009. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

That we (i) appoint XMA Limited to provide ICT services for the Loxford BSF One School Pathfinder project; (ii) appoint Ramesys as reserved bidder for the ICT services for the Loxford One School Pathfinder project; (iii) agree that the requirements of contract standing orders 93 and 92 are waived to allow for the appointment of XMA Limited under the BECTA Framework; (iv) note that the fees for the services will be met by the Department for Children Schools and Families funding for the Loxford One School Pathfinder project as referred to in paragraph 1.1 of the report; (v) delegate to the Director of Children’s Services, in consultation with the Cabinet Member for Children’s Services, authority to engage and instruct XMA Limited in respect of the project. Also, to finalise any contractual documentation, with advice from the Borough Solicitor and Secretary, as may be necessary; (vi) in the event that XMA Limited is unable or unwilling to take up the appointment, to delegate to the Director of Children’s Services, in consultation with the Cabinet Member for Children’s Services, authority to appoint Ramesys Limited as ICT Contractor to the Loxford BSF One School Pathfinder project; (vii) agree to the establishment of an ICT contingency of £140,000 to support the development of the CIT solution at the school; (viii) agree to the transfer of £150,000 from the nominal ICT budget to the main building works contingency; and (ix) agree that the school contribution of £300,000 be allocated to the fixed furniture & equipment budget. Chairman
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting
4Minutes of the previous meeting held on 12th January 2008 (CAB/04/170209)Agreed 5Environment and Highways Scrutiny Committee - Parking Management Scrutiny Working Group - Final Outcome Report (CAB/05/170209)Decided 6Forward Plan and Work Programme (CAB/06/170209)Agreed 7Calender of Meetings for the Municipal Year 2009/10 (CAB/07/170209)Approved 8Outcomes of Consultation with Scrutiny and Area Committees and Council Partners on the 2009-10 Budget Proposals (CAB/08/170209)Noted 10Budgetary Control Report for December 2008 (CAB/10/170209)Decided 11Risk Management - Quarterly Monitoring Report (CAB/11/170209)Noted 12Capital and Revenue Budget and Council Tax 2009/10 (CAB/12/170209)Agreed 13Proposed Children's Centre in Redbridge - Phase 3 (2008-2011) (CAB/13/170209)Agreed 142009/10 Transport for London Highways Funding Allocations and 2008/09 Amendments (CAB/14/170209)Approved 15Variation to London Council's Transport and Environment Committee Governing Agreement (CAB/15/170209)Approved 16Review of Housing Revenue Account Finances and Charges 2009/10 (CAB/16/170209)Agreed 17Quality of Life Committee Revisions (CAB/17/170209)Approved 18Rent Increase for Northview Caravan Site (CAB/18/170209)Agreed 19Redbridge Local Development Framework - Joint Waste Preferred Options Report (CAB/19/170209)Decided 20Growth Fund 2009-11 - Project Funding Allocations (CAB/20/170209)Approved 21Corporate Capital Building Maintenance Programme 2009/10: Scheme and Estimate Report (CAB/21/170209)Agreed 23Motion to exclude the public (CAB/23/170209)Decided 24Report on Expenditure on the Project to build the new Cranbrook Primary School (CAB/24/170209)Agreed
25Loxford School of Science & Technology - Building Schools for the Future - One School Pathfinder - Appointment of ICT Contractor (CAB/25/170209)This decision

Who was there

10 of 10 attended
AE
Councillor Alan Edward Weinberg MBEMember, present
LA
Councillor Linda A. HuggettMember, present
MA
Councillor Mark AaronMember, present
RI
Councillor Ronald I. BardenMember, present
TC
Councillor Thomas ChanMember, present
VC
Councillor Vanessa ColeMember, present
JW
Councillor John William Fairley-ChurchillMember, present
PR
Councillor Peter R. GoodyMember, present
KP
Councillor Keith PrinceMember, present
CM
Councillorr Michael StarkMember, present

On this subject at Redbridge

Search all
  1. Loxford School of Science & Technology - Building Schools for the Future - One School Pathfinder - Appointment of ICT Contractor (CAB/25/170209)This decision
  2. Delivering temporary accommodation at Loxford Hall and the former Newbridge School (CAB/12/040417)Noted
  3. Delivering Temporary Accommodation at Loxford Hall and the Former Newbridge SchoolAgreed
  4. Expansion of the Age Range of Loxford School of Science & Technology - Outturn Report and ICT Tender (CAB/16/110313)Noted
  5. Outcome of Statutory Consultation to Change the Age Range of Loxford School of Science and Technology (CAB/14/100111)Agreed
  6. Loxford School of Science & Technology Building Schools for the Future - One School Pathfinder Project (OSP). Appointment of Design and Build Contractor (for stage 2 works) (CAB/22/150408)Agreed

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies