Item15
Resolved
That we (i) agree the outline scheme and estimate for roof replacement project at Wanstead High School, totalling £775,000, noting that the costs given are approximate; (ii) grant, in accordance with Standing Order 125.1, approval to apply the budget identified in the Children’s Services Capital Programme 2010/11 for the purpose of the roof replacement project at Wanstead High School; (iii) approve the total expenditure from the Children’s Services Capital Programme of £775,000 in 2010/11; (iv) note that the Council, having made the decision to avail itself of the Sinclair Directory, the procurement of certain aspects of the work will be carried out in accordance with Standing Order 94.8; (v) delegate to the Chief Property Services Officer, in consultation with the Cabinet Member for Children’s Services, authority to accept the most economically advantageous tender and award a contract for the undertaking of the building improvement works without further reference to Cabinet and, accordingly, authorise a waiver of Contract Standing Order 107.5 provided that the tender is within the overall budget of £1m; (vi) note that the outcome of the tendering process will be reported to Members and should any contingency not be required then this will be returned to the Corporate Capital resources; and (vii) authorise the issue of a letter of intent in order to advance commencement of the contractors mobilization period, to enable materials to be ordered and work to commence (up to a maximum value of £350.000).
Word for word from the decision Redbridge published for this meeting.
Source: moderngov.redbridge.gov.uk