That we ( i ) agree the Cabinet’s initial proposals as set out in Appendix B ( i ); (ii) receive an option sheet to Cabinet in February proposing the inclusion of the revised option for the refurbishment of Wanstead High School Science Laboratories to the Capital programme; and (iii) refer the proposals to the appropriate Scrutiny and Area Committees and other bodies for their comments. (Councillors R. Cole, Wilson and Chan spoke in relation to this item)
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1The next few years present the most difficult financial challenge Redbridge has had to face. This report sets out the detail of the Cabinet’s initial revenue and capital budget proposals to seek to address that challenge. They are for consultation prior to proposing a final budget and Council Tax for 2011/12 to Budget Council.
1.2Council at its meeting on 21st October 2010 agreed in-year spending reductions for 2010/11 and their ongoing impact for 2011/12 onwards. These reductions were to help address the reduction in grant for 2010/11 and also start the process of planning for more significant cuts in grant from 2011/12 onwards.
1.3On the 13th December 2010, the Government announced its Local Government Finance Settlement for 2011/12 and 2012/13. Redbridge has been notified that its Formula Grant for 2011/12 will be cut by £10.086 million when compared to the adjusted Formula Grant for 2010/11. The adjusted allocation for 2011/12 will be cut by a further £6.634 million in 2012/13.
1.4The Council has been consulting on making cuts of £25 million over the next three years. The grant reductions for the next two years amount to nearly £20 million. The figures for 2013/14 have not been announced. There will also be a new grant distribution formula in place for that year making predictions very difficult. However given the scale of grant cuts to date and the serious demographic pressures also faced by the Council, the £25 million savings figure does not seem unreasonable.
1.5The budget proposals put forward for consideration do reflect the need for the Council to make some very difficult decisions. In preparing these proposals the Cabinet have endeavoured to protect front line services as far as possible and drive out back office savings whilst maintaining a balanced and prudent budget.
1.6The officer report is attached as Appendix A to this report and Cabinet’s initial revenue and capital budget proposals are set out at Appendix B (i) [White] – Revenue; and Appendix B (ii) [White] – Capital (Internal).
Reasons for recommendations
2.1It is necessary for Cabinet to agree an Initial Revenue Budget and Capital Programme for consultation with Committees and other relevant key stakeholders. 3. Recommendations
3.1The Cabinet is recommended to:
Agree the Cabinet’s initial proposals as set out in Appendix B (i) and (ii) [White] and refer them to the appropriate Scrutiny and Area Committees and other bodies for their comments.
THE ABOVE CABINET RECOMMENDATION WILL FORM PART OF THE COUNCIL’S BUDGET SETTING PROCESS AND THEREFORE MAY NOT BE REQUISITIONED, IN ACCORDANCE WITH STANDING ORDER 64.1 (m)
Contact Point Name : Councillor K. Prince Position : Leader Telephone : 0208 708 2800 e-mail : [email protected] APPENDIX A
OFFICER REPORT To : Cabinet Member for Finance From : Chief Executive and Director of Finance and Resources Date : 10th January 2011
Background
1.1The Government has announced a series of grant reductions which have reduced its in-year funding to Redbridge by £5.826 million in 2010/11. This included £2.320 million used to meet ongoing general fund expenditure and £3.506 million used to fund one-off initiatives. Whilst Cabinet has agreed that the latter one-off initiatives will not now be progressed, Council had to agree savings to offset the £2.320 million which was in the base revenue budget. Council at its meeting of 21st October 2010 therefore approved in-year spending reductions of £3.984 million for 2010/11 with a full year effect of £6.092 million. These reductions were to help address the reduction in grant for 2010/11 and also start the process of planning for more significant cuts in grant from 2011/12 onwards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.