Resolved
That ( i ) determine the New Rush Hall School statutory notice, thereby formally enlarging the capacity of the school from 64 to 80 places, effective from 1 September 2020, the approved.
Cabinet approved this item on Tuesday 7 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That ( i ) determine the New Rush Hall School statutory notice, thereby formally enlarging the capacity of the school from 64 to 80 places, effective from 1 September 2020, the approved.
1.1The High Needs Review and subsequent forecasting has identified a need to create more places for children with Special Educational Needs and Disabilities. A key element of the programme of work to meet this need is the expansion of the Borough’s special schools.
1.2This paper relates to the proposal to expand The New Rush Hall School by 16 places, to meet the current and forecast growth in the cohort of pupils with Social, Emotional and Mental Health needs, which was the subject of a recent public consultation process.
Cabinet is recommended to:-
2.1Determine the New Rush Hall School statutory notice, thereby formally enlarging the capacity of the school from 64 to 80 places, effective from 1 September 2020.
THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr. Elaine Norman Position: Cabinet Member for Children and Young People Telephone: Email: [email protected]
Contact Point Report Author: Oliver Gill Position: High Needs Planning Consultant Telephone: 0208 708 6225 E.Mail: [email protected] 3. Background and Proposals
3.1Since the introduction of the Children and Families Act 2014, the number of Redbridge resident pupils with a Statement or EHCP has risen by approximately 35%, broadly in line with the national average. Furthermore, it is anticipated that the SEND pupil population will continue to grow, with a 16.5% (or 153-place) increase in primary and a 33.7% (248-place) increase in secondary demand forecast for the period of 2019- 2025. A sizeable amount of the forecast increase (46 places) is anticipated to be associated specifically with Social, Emotional and Mental Health (SEMH) needs. Such pupil growth has resulted in the need for additional provision to accommodate the increasing and changing of need, which has only been partially achievable within the current school capacity.
3.2As a consequence of the rising demand, the Council undertook a High Needs Review, which recommended the creation of 140 new school places for pupils with SEND, over the period 2018-2023. The proposal to expand New Rush Hall School forms part of a borough-wide expansion programme, aimed at providing sufficient SEND school places to meet the current and projected future levels of demand.
3.3It is proposed to increase the formal capacity of The New Rush Hall School from 64 places to 80 places. In line with the present remit of the school, these places would be for pupils with SEMH needs. The additional places would be evenly split across Key Stage 1 (8 places) and Key Stage 2 (8 places). The impact on the capacity of the school would be to increase the number of 8-place classes in the primary phase to five, thereby balancing with the five 8-place classes currently on offer in the secondary phase. If approved, this proposal would provide 16 additional primary places within Redbridge, which would help to bridge the gap between the supply and demand for school places, in combination with a number of other such proposals.
3.4Separate from the current proposal, the Piccolo provision at New Rush Hall is scheduled to close on 1 April 2020. This provision consists of 12 part-time places for Key Stage 1 pupils with SEMH, who remain on the roll of their mainstream school, and also attend mainstream classes. Should the proposal to enlarge the capacity of New Rush Hall be approved, then one of the 8-place classes generated could be used to provide for any children displaced by the closure of The Piccolo, if it would be most appropriate to their needs for them to attend dedicated specialist provision full-time.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
14.1 Appendix A1: NRH Statutory NoticeAppendix | 293 KB | Download |
PDF |
14.2 Appendix A2: Ilford Recorder NoticeAppendix | 1.7 MB | Download |
PDF |
14.3 Appendix B: Equality Impact Screening NRH 06112019Appendix | 86 KB | Download |
PDF |
Proposal to Enlarge New Rush Hall School(CAB/14/070120)Report | 90 KB | DownloadRead as text |
Follow Cabinet at Redbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. | Agreed | Open |
| 17 Jun 2026 | Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. | Agreed | Open |
| 17 Jun 2026 | Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... | Noted | Open |
| 17 Jun 2026 | Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... | Approved | Open |
| 17 Jun 2026 | Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.