Resolved

That ( i ) the forecast overspend position of £52.168m in relation to the 2020/21 General Fund Service Directorate Revenue Budget, be noted (ii) the forecast overspend position of £1.129m in relation to the overall 2020/21 General Fund budget, be noted (iii) the forecast over spend position of £1.831m in relation to the Dedicated Schools Grant, be noted (iv) the forecast overspend position of £0.114m in relation to the Housing Revenue Account, be noted; (v) the mitigation plans relating to the forecast outturn position as a Quarter 2 2020/21 as reported to November Cabinet and the requirement for further mitigation plans to be presented to February 2021 Cabinet in relation to the current forecast overspends as per section 6 and Appendix E( i ) - (xi), be noted; (vi) the progress and delivery of the approved savings programme (RAG - Red £14.000m, Amber £3.136m, Green £4.759m and Blue £5.188m). To ensure savings delivery for all red saving items, substitutions are expected to be identified and implemented; (vii) the forecast outturn position reported on the capital programme in section 12 of the report, be noted; (viii) the addition of £2.061m capital grant funding to the Housing General Fund (£0.962m) and Civic Pride (£1.099m) Capital programme as identified below and in paragraph 12.3, be approved: · £0.962m – Rough Sleeping Accommodation Programme · £0.288m – Disabled Facilities Grants · £0.761m – Local Implementation Plan Corridors and · £0.050m – Local Transport Fund. (ix) capital slippage of £50.583m into 2021/22 and acceleration of £0.871m in the General Fund Capital Programme as detailed in paragraphs 12.6-12.10, be approved. (x) HRA capital slippage of £9.356m into 2021/22 in the HRA Capital Programme as identified in paragraph 12.11, be approved. (xi) the capital virements approved as set out in paragraph 12.12 of this report, be noted. (xii) the forecast COVID-19 impact and associated grant funded as set out in section 14, be noted. (xiii) the performance update as set out in section 15 and Appendix D, be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report sets out the Authority’s financial performance to 31 December 2021 and the forecast outturn for 2020/21.

Recommendations

The Cabinet is recommended to:

2.1Note the forecast overspend position of £52.168m in relation to the 2020/21 General Fund Service Directorate Revenue Budget;

2.2Note the forecast overspend position of £1.129m in relation to the overall 2020/21 General Fund budget;

2.3Note the forecast over spend position of £1.831m in relation to the Dedicated Schools Grant;

2.4Note the forecast overspend position of £0.114m in relation to the Housing Revenue Account;

2.5Note the mitigation plans relating to the forecast outturn position as a Quarter 2 2020/21 as reported to November Cabinet and the requirement for further mitigation plans to be presented to February 2021 Cabinet in relation to the current forecast overspends as per section 6 and Appendix E(i) - (xi);

2.6Note the progress and delivery of the approved savings programme (RAG - Red £14.000m, Amber £3.136m, Green £4.759m and Blue £5.188m). To ensure savings delivery for all red saving items, substitutions are expected to be identified and implemented;

2.7Note the forecast outturn position reported on the capital programme in section 12 of the report;

2.8Approve the addition of £2.061m capital grant funding to the Housing General Fund (£0.962m) and Civic Pride (£1.099m) Capital programme as identified below and in paragraph 12.3:  £0.962m – Rough Sleeping Accommodation Programme  £0.288m – Disabled Facilities Grants  £0.761m – Local Implementation Plan Corridors and  £0.050m – Local Transport Fund. 2.9. Approve capital slippage of £50.583m into 2021/22 and acceleration of £0.871m in the General Fund Capital Programme as detailed in paragraphs 12.6-12.10.

2.10Approve HRA capital slippage of £9.356m into 2021/22 in the HRA Capital Programme as identified in paragraph 12.11.

2.11Note the capital virements approved as set out in paragraph 12.12 of this report.

2.12Note the forecast COVID-19 impact and associated grant funded as set out in section 14.

2.13Note the performance update as set out in section 15 and Appendix D.

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT

MAY BE CALLED IN

Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance, Leisure and Culture Telephone: 020 8708 2020 Email: [email protected]

Contact Point Report Author: Ian Ambrose Position: Operational Director of Finance (Deputy s151 Officer) Telephone: 0208 708 6410 Email: [email protected] 3. Background and Proposals

3.1Budgetary control reports are presented to Cabinet so that the Council’s revenue and capital programme can be monitored. It is essential that frequent monitoring takes place in order to ensure that the Council’s financial resources are properly controlled.

3.2In accordance with Financial Standing Orders 129, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action. Section 6 sets this out in more detail.

3.3This report highlights the main risks and issues that are being addressed by Corporate Directors to maintain expenditure within the approved Revenue Budget and Capital Programme. It also provides a summary of progress in delivering savings brought forward from 2019/20 and those due to be delivered in 2020/21. Where these actions require the virement of budgets, they are reported for noting in accordance with financial regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
8.1 Appendix A: RevenueAppendix 118 KB Download
PDF
8.2 Appendix B(i): Savings Tracker 2020-21 Q3Appendix 169 KB Download
PDF
8.3 Appendix B(ii): Savings Tracker 2020-21 Q3Appendix 92 KB Download
PDF
8.4 Appendix B(iii): Savings Tracker 2020-21 Q3Appendix 31 KB Download
PDF
8.5 Appendix C: CapitalAppendix 177 KB Download
PDF
Quarter 3 Budgetary Control ReportReport 1.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
IA
Ian AmbroseCouncil Staff, expected
JA
Councillor Jas AthwalChair, present
KR
Councillor Kam RaiVice-Chair, present
EN
Councillor Elaine NormanMember, present
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, present
HM
Councillor Helen Mary CoombMember, present
GM
Greg MortimerOfficer, expected
JB
Councillor Jo BlackmanMember, present
VS
Councillor Vanisha S. B. SolankiMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present

On this subject at Redbridge

Search all
  1. Quarter 3 Budgetary Control ReportThis decision
  2. Budgetary Control Report for Quarter 3 2025-26Noted
  3. Budgetary Control report for Quarter 3 2024/25Noted
  4. Budgetary Control Report for Quarter 1Noted
  5. Budgetary Control Report for Quarter 3Noted
  6. Scrutiny Performance Monitoring - Budgetary Control Report for Quarter 2Noted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies