Resolved
That ( i ) the outcome of the financial review of the Redbridge Living Limited financial model, be noted; (ii) that the proposed three schemes revert to direct delivery by ... view the full minutes text for item 11.
Cabinet noted this item on Tuesday 14 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That ( i ) the outcome of the financial review of the Redbridge Living Limited financial model, be noted; (ii) that the proposed three schemes revert to direct delivery by ... view the full minutes text for item 11.
1.1At its meeting in July 2017, Cabinet approved the establishment of a wholly owned development company with the aims and objectives to deliver residential led developments to provide a mix of private sale, private rented and affordable homes. It was intended for the company to act in a commercial manner and, alongside other objectives, to generate financial returns to the Council through interest on development loans and in the longer term through rental returns on the retained private rented homes. Redbridge Living Limited was duly set up and incorporated at Companies House in October 2018.
1.2Subsequently, professional teams have been appointed and they have worked with local communities to develop proposals for high quality, policy compliant schemes on Council owned sites on Clements Road, Loxford Lane and Seven Kings incorporating 489 new homes, including 162 affordable homes of a mix of London Affordable Rent and Community Land Trust (discounted for sale homes) along with a Community/Health Hub and Business Enterprise Hub at Seven Kings. Work on Redbridge Living was put on hold over the past 18 months with the Council’s focus understandably drawn to the Covid-19 pandemic.
1.3The pandemic, together with Brexit, have presented a unique mix of challenges in the housing market with labour and materials shortages driving rapid construction cost inflation. As the Council emerges from the pandemic, it has taken the opportunity to review the financial modelling underpinning Redbridge Living before committing to physical delivery of the schemes to consider the extent to which the Council’s original objectives are being met. The review has concluded that, whilst it remains possible to meet the ambition to deliver high quality, policy compliant housing that meets the needs of local families, the likely financial returns from the three schemes are significantly lower than originally anticipated and no longer support the objectives around the development of a build to rent portfolio to generate long term revenue returns.
1.4This report, therefore, recommends a change in approach to focus on the delivery of schemes focussed on build for sale housing which will cross subsidise the delivery of affordable housing and community infrastructure. This change in objectives gives the Council the opportunity to deliver the schemes directly without the need for a company structure providing greater efficiency, control and transparency around decision making. The report updates on the work completed to date and the outcomes of the additional financial modelling and recommends that the existing contracts be transferred to the Council and that the Council seek to progress direct delivery of the existing schemes at Clements Road and Loxford Lane. The report outlines further work required on the proposals for Seven Kings and resolves to bring a further report back to Cabinet once this work is complete.
The Cabinet is recommended to:-
In relation to Redbridge Living
2.1Note the outcome of the financial review of the Redbridge Living Limited financial model;
2.2Agree that the proposed three schemes revert to direct delivery by the Council;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
11.2 Appendix 2a: Site Plan: 17-23 Clements Road IlfordAppendix | 56 KB | Download |
PDF |
11.3 Appendix 2b: Site Plan: 22-26 Clements Road IlfordAppendix | 56 KB | Download |
PDF |
11.4 Appendix 2c: Site Plan: Loxford LaneAppendix | 104 KB | Download |
PDF |
Development of sites at Loxford Lane and Clements RoadReport | 259 KB | DownloadRead as text |
Follow Cabinet at Redbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. | Agreed | Open |
| 17 Jun 2026 | Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. | Agreed | Open |
| 17 Jun 2026 | Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... | Noted | Open |
| 17 Jun 2026 | Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... | Approved | Open |
| 17 Jun 2026 | Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.