Project to Expand Newbridge School

Approved Executive 2 papers

Cabinet approved this item on Tuesday 6 September 2022. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That (i) the allocation of an additional £0.600m from the High Needs Provision Capital Allocation to the Newbridge Capital Project, taking the total project budget to £1.400m, with authorisation to procure up to this total value, be approved.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The High Needs Review and subsequent needs forecasting has identified a need to create more places for children with Special Educational Needs and Disabilities. A key element of the programme of work designed to meet this need is the expansion of Newbridge School. At the meeting of 16 November 2021, Redbridge Cabinet approved this scheme, inclusive of the allocation of a £800,000 budget to facilitate the associated capital project.

1.2Unfortunately, due to a combination of severe market volatility; inflation pressures; and adverse survey outcomes, it has not been possible to maintain the project within its budget envelope. Ultimately, the project has now shifted too far from the original brief and has been brought back to Cabinet to set a new budget envelope that reflects current market conditions.

1.3The Cabinet is asked to review the education rationale for the project, together with the summary of the progress to date, summarised within this report. On that basis, the Cabinet is asked to decide whether to approve the funding required to enable to project to proceed in the current market conditions.

Recommendations

The Cabinet is recommended to: -

2.1Approve the allocation of an additional £0.600m from the High Needs Provision Capital Allocation to the Newbridge Capital Project, taking the total project budget to £1.400m, with authorisation to procure up to this total value

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN Cabinet Member Contact Point Name: Cllr. Mark Santos Position: Cabinet Member for Children and Young People Telephone: 020 8708 9722. Email: [email protected] Contact Point

Report Author: Liz Hunt Position: Head of Access & Inclusion Telephone: 020 8708 3976 Email: [email protected] 3. Background and Proposals

3.1Newbridge School is a 148-place Special Academy, which accommodates children with an Education, Health and Care Plan (EHCP), from ages 2 to 19. The school provides places for pupils who have a complex learning difficulty, such as Profound and Multiple Learning Difficulties (PMLD), Severe Learning Difficulties (SLD). This is often accompanied by additional special educational needs (e.g. Autistic Spectrum Disorder, physical disabilities etc.). Newbridge presently operates slightly over capacity, with 73 places in the primary phase and 80 places in the secondary phase. The school is part of the Astrum Multi Academy Trust (MAT).

3.2In partnership with the London Borough of Redbridge, the Astrum MAT is proposing to expand the formal capacity of Newbridge School from 148 places to 169 places. It is intended that the additional capacity would be delivered for the secondary-age cohort (11-19).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10.1 Appendix A: Equality Impact Screening (Newbridge)Appendix 648 KB Download
PDF
Project to Expand Newbridge SchoolReport 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
KR
Councillor Kam RaiVice-Chair, present
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, present
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present
JA
Councillor Jas AthwalMember, present
VS
Councillor Vanisha SolankiMember, present

On this subject at Redbridge

Search all
  1. Project to Expand Newbridge SchoolThis decision
  2. Project to Expand Newbridge SchoolNoted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies