That ( i ) the Outturn overspend against budget of £15.317m in relation to the 2024/25 General Fund Revenue Budget in Table 1, be noted; (ii) the Flexible Use of Capital Receipts of £1.593m and abortive capital costs of £0.548m, be noted; (iii) that there were approved revenue virements since Quarter 3 of £0.733m, be noted. (iv) the delivery of the approved savings programme as set out in Table 2 and Appendix D, be noted; (v) the Outturn General Fund outturn of £55.702m and HRA outturn of £77.479m, for the Capital Programme in Appendix B of the report and note the overall Capital Programme outturn is set to breakeven, subject to, be noted; · Agree capital slippage from 2024/25 to 2025/26 of £29.990m General Fund and £9.970m HRA since Quarter 3 as detailed in Appendix B ; · Agree the capital accelerations from 2025/26 to 2024/25 of £0.505m all within General Fund as detailed in Appendix B; · Note the capital virements as detailed in Appendix B; · Note the capital additions of £4.347m all in relation to the General Fund as detailed in Appendix B; · Note the capital reduction of £0.500m in relation to the General Fund as detailed in ... view the full minutes text for item 9.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report sets out the financial performance of the Authority for its Revenue, Capital Programme, Housing Revenue Account, Dedicated Schools Grant and savings for the year 2024/25.
1.2The General Fund Outturn for 2024/25 is an overspend of £15.317m. This includes overspends of £14.979m in Communities, £22.865m in the People Directorate, £1.445m in Regeneration and Culture, £2.063m in Strategy and an underspend of £0.134m in Resources. Corporate outturn is £24.856m under budget including the application of the Risk and Contingency provision of £14.400m. In addition there are abortive capital costs of £0.548m written back to revenue and the flexible use of capital receipts to fund £1.593m of eligible transformation work.
1.3As a result of this overspend there has been a significant reduction in Earmarked Reserves, reducing by £15.721m including other movements for the year. This has a notable impact on the Council’s financial resilience and there will need to be significant focus on cost reduction in 2025/26 to avoid further reductions in reserves, along with the development of a plan to replenish reserves used in recent years. Unbudgeted pressures rolling forward into 2025/26 include £17.151m in housing and £16.333m in adult social care, with more minor sums across other areas of the council.
1.4The Capital Programme outturn and revised budget are £133.181m for the year.
1.5For 2024/25 the amount of Council Tax collected at the end of March 2025 was 95.82%. The amount of Business Rates collected was 92.67%
1.6Full details are set out in the report and additional information is provided in the following appendices:
Appendix A – Detailed General Fund Revenue Appendix B - Capital Appendix C – HRA and DSG Appendix D – Savings Tracker Appendix E – Debt Management Report Appendix F – Debt write-offs Appendix G – Reserves 2. Recommendations
The Cabinet is recommended to:
2.1Note the Outturn overspend against budget of £15.317m in relation to the 2024/25 General Fund Revenue Budget in Table 1;
2.2Note the Flexible Use of Capital Receipts of £1.593m and abortive capital costs of £0.548m;
2.3Note that there were approved revenue virements since Quarter 3 of £0.733m.
2.4Note the delivery of the approved savings programme as set out in Table 2 and Appendix D;
2.5Note the Outturn General Fund outturn of £55.702m and HRA outturn of £77.479m, for the Capital Programme in Appendix B of the report and note the overall Capital Programme outturn is set to breakeven, subject to;
2.5.1 Agree capital slippage from 2024/25 to 2025/26 of £29.990m General Fund and £9.970m HRA since Quarter 3 as detailed in Appendix B;
2.5.2 Agree the capital accelerations from 2025/26 to 2024/25 of £0.505m all within General Fund as detailed in Appendix B;
2.5.3 Note the capital virements as detailed in Appendix B;
2.5.4 Note the capital additions of £4.347m all in relation to the General Fund as detailed in Appendix B;
2.5.5 Note the capital reduction of £0.500m in relation to the General Fund as detailed in Appendix B;
2.5.6 Note the capital funding changes of £0.025m in relation to the General Fund and £0.067m in relation to the HRA as detailed in Appendix B;
2.6Note the collection rates for Council Tax and Business Rates as set out in Section 9;
2.7Note the outturn position of a £0.749m surplus on the Housing Revenue Account (HRA) as set out in Appendix C;
2.8Note the outturn position of a £0.051m surplus on the Dedicated Schools Grant (DSG) as set out in Appendix C;
2.9Note the Debt Management Report set out in Section 12 and in Appendix E;
2.10Note that there was an approved debt write off since Quarter 3 of £0.018m for Adults Social Care; and
2.11Note the Reserves position as set out in Appendix E and Section 13.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.