London Borough of Redbridge
Cabinet, Thursday 26 February 2026

Waiver and Contract Monitoring 202526 Quarter 3 October December 2025

Noted Executive 1 paper

AI summaryRedbridge Cabinet notes seven contract waivers worth £1.542m granted between October and December 2025, covering works and surveys across Place, Communities and Enterprise services.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarterly report for October to December 2025
Money£1.542m total waiver valueAcross seven contracts in the quarter
What happens nextNo further action requiredReport is for noting only
Who it affectsPlace, Communities and Enterprise directorateSix of seven waivers; one for Customer, Performance & Insights

What was decided

Cabinet noted the seven contract waivers approved in the reporting period, totalling £1.542m. Report 2.1, 5.1

Cabinet noted the contracts awarded in the reporting period, listed in Appendix 2. Report 4.4

Why

Contract Standing Order 90.10 requires a quarterly report to Cabinet on all waiver applications received in the preceding quarter, providing assurance over procurement controls. Report 1.1, 3.1, 4.3

Waivers were granted where following standard standing orders was not practical, including limited supplier markets, non-use of the e-procurement system, and time-critical service needs. Report 5.3, 5.4, 5.5, 5.6

What happens next

Details of awarded contracts will be published on the Council's website under Contract Standing Order 101.14 and are visible via the Council's contracts register. Report 4.4, 14.2

Any increases on these contracts must be met from within the relevant service directorate's existing budget. Report 13.2

The money

  • £75,000 Van mounted jet wash Report 5.2, P15
  • £127,527 Demolition of Elmhurst Bowling Club Pavillion Report 5.2, P15
  • £970,000 Parks WC Refurbishments Report 5.2, P15
  • £16,347 Self-Assessment Tool, Analysis & 1:1 Briefings Report 5.2, P15
  • £78,781 MDS Electrical Services Ltd Report 5.2, P15
  • £139,696 Stock Condition Survey program Report 5.2, P15
  • £134,564 M&E Condition Surveys Report 5.2, P15
  • £1.542m Total value of seven waivers in the quarter Report 5.1

Options considered

  • Chosen: Note the contract waivers in the reporting period. Required by Contract Standing Order 90.10 to provide assurance over procurement controls Report 2.1, 3.1, 4.3
  • Chosen: Note the awarded contracts in the reporting period. Required by Contract Standing Order 101.14; details published on the Council's website Report 4.4, 14.2

Implications

  • Legal: Each waiver must not be in breach of the Procurement Act 2023; the report complies with Contract Standing Orders 90.10 and 101.14. Report 14.1, 14.2, 14.3
  • Financial: Each contract must be delivered within the service directorate's existing budget, and any increases must be met from within that directorate's budgetary envelope. Report 13.1, 13.2
  • Risk: No significant risks are identified directly from the report; individual waiver risks are assessed by the project owner and Procurement Team. Report 7.1
  • Equalities: The proposals have no direct impact on groups with protected characteristics under the Equalities Act 2010. Report 8.8
  • Staffing: Not applicable. Report 9.1
  • Other: Crime and community safety implications are not applicable; child friendly implications are not applicable. Report 11.1

Who and where

  • Place, Communities and Enterprise directorate (six of seven waivers including Parks WC Refurbishments and Demolition of Elmhurst Bowling Club Pavillion) Report 5.2, P15
  • Customer, Performance & Insights directorate (Self-Assessment Tool, Analysis & 1:1 Briefings waiver) Report 5.2, P15
  • Suppliers awarded work without a competitive tender, including MDS Electrical Services Ltd Report 5.2, P15

Timeline

  • 1 October 2025 to 31 December 2025: Reporting period covered by the waiver and contracts data Report 1.2, 5.2
  • 2026-02-26: Cabinet meeting at which the report was noted

Plain English for the jargon

  • Waiver: Approval to award a contract without following the Council's usual Contract Standing Orders, granted where it is not practical to comply.
  • Contract Standing Orders (CSOs): The Council's internal rules governing how contracts must be procured, made under section 135 of the Local Government Act 1972.
  • Most Advantageous Tender: A competitive quote process used by the Council where multiple suppliers are invited to price work.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That ( i ) the contract waivers in the reporting period, be noted. (ii) the awarded contracts in the reporting period, be noted
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Council’s Contract Standing Orders requires the Procurement Department to report all contract waivers to Cabinet for information on a quarterly basis to provide assurance over the controls in place around procurement activity.

1.2This report provides an overview of the approved waivers for the period 1 October 2025 to 31 December 2025.

Recommendations

Cabinet is recommended to:-

2.1note and consider the contract waivers in the reporting period. 2.2 note and consider the awarded contracts in the reporting period

Reasons for recommendations

3.1This report is a requirement of the Council’s Contract Standing Order 90.10.

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN Cabinet Member Contact Point Name: Cllr Helen Coomb Position: Cabinet Member for Resources and Transformation Email: [email protected]

Contact Point Report Author: Adam Sargent Position: Head of Procurement Email: [email protected] 4. Background

4.1The Council may only contract with external parties within the legal framework for local authority procurement, i.e. in accordance with the UK Public Contract Regulations 2015 (as amended), the Council’s Contract Standing Orders (s135 of the Local Government Act 1972) and the general duty to obtain Best Value (Local Government Act 1999). 4.2. There are occasions where it is not practical or possible to procure contracts in accordance with the Contract Standing Orders. In such instances officers may request a waiver to the rules. The approval of such waivers ensures compliance with the Contract Standing Orders.

4.3As per the Council’s Contract Standing Orders 90.10, the rules require a quarterly report for submission to Cabinet, which will contain details of all waiver applications received during the preceding quarter.

4.4Contracts let through the waiver process are subject to the Local Government transparency 2015 requirements and is information that is visible to the public via the Council’s contracts register. Pursuant to Contract Standing Order 101.14, details of contracts awarded by the Council are published on the Council’s website1. These awarded contracts are provided as Appendix 2.

5. Options and Proposals

5.1The total number of waivers actioned during this period is seven (7) and the total value of these contracts is £1.542m.

5.2Waivers between 1 October 2025 and 31 December 2025:

Contract Title Value Directorate

1. Van mounted jet wash £75,000 Place, Communities and Enterprise 2. Demolition of Elmhurst Bowling £127,527 Place, Communities Club Pavillion and Enterprise 3. Parks WC Refurbishments £970,000 Place, Communities and Enterprise 4. Self-Assessment Tool, £16,347 Customer, Analysis & 1:1 Briefings Performance & Insights 5. MDS Electrical Services Ltd £78,781 Place, Communities and Enterprise 6. Stock Condition Survey £139,696 Place, Communities program and Enterprise 7. M&E Condition Surveys £134,564 Place, Communities and Enterprise

5.3Waiver 1 was granted the market for this type of equipment is limited. It was demonstrated that this purchase route is appropriate on this occasion.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waiver and Contract Monitoring 202526 Quarter 3 October December 2025Report 333 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
KR
Councillor Kam RaiChair, present
MA
Councillor Mark A. SantosMember, present
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present
VS
Councillor Vanisha SolankiVice-Chair, present
LJ
Councillor Lloyd Jacob DuddridgeMember, apologies
NB
Councillor Namreen B. ChaudhryMember, present
SE
Councillor Sahdia E WarraichMember, apologies
S(
Councillor Saima (Syeda) AhmedMember, present
CH
Claire HamiltonOfficer, expected

On this subject at Redbridge

Search all
  1. Waiver and Contract Monitoring 202526 Quarter 3 October December 2025This decision
  2. Part Exempt: Contract Waiver Monitoring October 2024 - December 2024Noted
  3. Exempt: Contract Waiver Monitoring November 2020 - January 2021Noted
  4. Waiver of Contract Standing Order 94 for the Provision of Integrated Sexual Health Service (CAB/18/070715)Decided
  5. Waiver of Contract Standing Order 93 for the Provision of Chlamydia Screening Programme (CAB/19/070715)Decided
  6. Waiver of Contract Standing Orders 91 to 94 and Lease of 16 York Road in relation to the delivery of the former Supporting People Programme Contracts (CAB/28/090615)Agreed

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies