London Borough of Redbridge
Cabinet, Thursday 23 April 2026

Redbridge Corporate Performance Report Quarter 3 2025/26

Noted Executive 2 papers

AI summaryRedbridge Council noted its Q3 2025/26 corporate performance report, recording 199 new council homes delivered in the quarter, 100% of major planning applications decided in time, and council tax collection on track at 79.57%.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ3 2025/26 key priority measures across all portfolios noted
Money£5,596,759 social value committedCouncil contracts over £177k, validated next quarter
What happens nextQ4 2025/26 report dueNext quarterly performance report and annual data
Who it affectsRedbridge residents and servicesHousing, planning, leisure, environment, children, adult care

What was decided

The council noted Q3 2025/26 performance against key priority measures covering housing, planning, leisure, environment, enforcement, children, adult social care, finance and resources. Report P1, P2, P3, P4, P5, P6, P7, P8, P9, P10, P11, P12, P13, P14, P15, P16, P17, P18, P19, P20, P21, P22, P23, P24, P25, P26, P27, P28, P29, P30, P31, P32, P33, P34, P35, P36, P37, P38, P39, P40, P41, P42, P43, P44, P45, P46, P47, P48, P49, P50, P51, P52, P53, P54, P55, P56, P57, P58, P59, P60, P61, P62, P63, P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P74, P75, P76, P77

Why

The report is the council's quarterly oversight of progress against key priority measures across all directorates.

Several indicators are off-target, including EHCP timeliness at 26.9% against a 45% target and FOI response rates at 68%, prompting recovery plans. Report P61, P76, P77

What happens next

Various directorates are implementing recovery plans, including mobile device procurement for licensing inspections and EHCP process reviews, with progress to be reported next quarter. Report P18, P19, P61

Quarter 4 data is expected for affordable homes delivery, waste and recycling, and NHS Health Check uptake, which are reported on a lag. Report P1, P41, P42, P62

The money

  • 79.57% Q3 council tax collection, on track for 97.25% year-end target Report P72
  • 80.63% Q3 business rates collection, on track for 98% year-end target Report P73
  • £5,596,759 Social value committed across council contracts over £177k Report P77
  • £587,388 Social value delivered across council contracts over £177k Report P77

Implications

  • Risk: EHCP timeliness is at 26.9% against a 45% target, with the Department for Education requesting monthly monitoring data after last year's 7.1% outturn. Report P61
  • Staffing: Sickness absence short-term rate rose to 2.2% in Q3, with 3,035 days lost between October and December 2025. Report P77
  • Equalities: The attainment gap between SEN and non-SEN pupils at Key Stage 2 narrowed from 57.1 to 48.2 percentage points, though pupils with EHCPs continue to underperform. Report P54
  • Other: The council has delivered 199 new council homes in Q3, exceeding the 500-per-year target for 2022-2026. Report P1

Who and where

  • Redbridge residents across all service areas Report P1, P20, P31, P35, P44, P45, P62
  • Households in temporary accommodation (2,861 at end of December 2025) Report P2
  • Children with EHCPs and SEN support Report P54, P60, P61
  • Council tenants in non-decent homes (230 in Q3, with 297 more at risk by March 2026) Report P7
  • Businesses receiving growth support and licensing inspections Report P18, P23, P26

Timeline

  • Q3 2025/26 (October to December 2025): Reporting period for all performance measures Report P1, P2, P7
  • End of March 2026: Targets expected to be met for temporary accommodation (under 2,700) and non-decent homes Report P2, P7
  • April 2026: Q4 2025/26 reporting period ends; annual data for affordable homes and waste to be published Report P1, P41, P42
  • June 2026: Next tranche of legionella re-assessments due Report P12

Plain English for the jargon

  • TA: Temporary accommodation provided to households pending a settled housing solution.
  • EHCP: Education, Health and Care Plan, a legal document for children and young people with special educational needs.
  • HHSRS: Housing Health and Safety Rating System, used to assess hazards in rented properties.
  • RAAC: Reinforced Autoclaved Aerated Concrete, a building material linked to safety concerns at Fullwell Cross leisure centre.
  • FOI: Freedom of Information request, answered within 20 working days.
  • MEQ: Member Enquiry, answered within 10 working days.
  • CLA: Children Looked After by the local authority.
  • CPP: Child Protection Plan, for children at risk of harm.
  • ELWA: East London Waste Authority, which provides recycling and waste data for Redbridge.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That ( i ) performance against the key priority measures for Redbridge, be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Housing & Homelessness Cllr Saima Ahmed Outturn Outturn Q3 Q4 Q1 Q2 Q3 Target Ref Indicator Commentary 23/24 24/25 24/25 24/25 25/26 25/26 25/26 25/26 Deliver 500 council homes 199 new Council homes were delivered in quarter 3 from our HRA new build A1 between 2022 and 2026 (100 77 316 316 43 62 40 199 151 programme. The Council has now exceeded its target of 500 Council homes per year) to be delivered between 2022 and 2026. Deliver 1,000 affordable homes between 2022 and 24 381 - - - This data is compiled annually and will be available in Quarter 4. A2 381 Annual 200 2026 (200 per year) In Q3 there were 52 homeless preventions made, 33 secured alternative accommodations, 19 secured existing. In Q3, a greater volume of successful Number of prevention 99 105 52 30 B1 New New - - preventions occurred for households under a Relief Duty, rather than outcomes Prevention Duty

At the end of December 2025, a total of 2,861 households were recorded as living in temporary accommodation. This figure reflects continued pressure on local housing services and highlights the ongoing demand for suitable, sustainable housing options. The target of 2,700 is projected to be achieved by April 2026 as new supply becomes available. Number of households living 3011 2830 B3 2829 2830 2836 2868 2861 <2700 Whilst the Q3 figure (2,861) shows a 1.3% increase in the number of in temporary accommodation households in TA on last year (2,822). The latest published data for London shows an 8.4% increase in households in the same period, suggesting that Redbridge are working well in addressing the pressure being seen nationally. Amendments to the Allocations Policy are intended to further drive down the number of households in TA. The outreach team now provides far greater coverage across the whole Number of Rough Sleepers borough. While this means the service is more likely to identify rough (Verified bedded down rough 24 19 sleepers, it also means the service is better placed to provide them with B2 30 40 20 34 27 <19 sleepers - latest bi-monthly assistance and support. The rough sleeping accommodation pathway is being count) reconfigured to create more capacity and better move on, and new provision is also being sourced. In October the number of families was successfully reduced to zero, leaving no families in bed and breakfast accommodation over 6 weeks. As at the end No of Families with children 165 35 of December 2025 the number increased to 6 which as performance was B4 133 35 26 3 6 0 in Bed and Breakfast 6wks impacted by the closure of several of the TA agents over the Christmas period. All 6 households have been earmarked for properties and will be moved into those shortly.

1 Eviction rate in Redbridge Data B5 (per 10,000), in social or 4.2 3.8 3.8 3.8 4.2 2.2 Eviction rate for Private and Social Landlord in Q3 reduced to 2.2 per 10,000 Only private rented rented properties. Outturn Outturn Q3 Q4 Q1 Q2 Q3 Target Ref Indicator Commentary 23/24 24/25 24/25 24/25 25/26 25/26 25/26 25/26 Emergency repairs performance remained high, and above the 99% target across the quarter. Only 5 (0.33%) of the 1,516 emergency repair requests Proportion of Council Housing were recorded as missed. This was due to internal administration. C5 repair emergency requests 100% 100% 100% 100% 99.3% 99.7% 100% Action: Review repair logging process with contractor to avoid future lags in completed in time reporting.

Total of 232 surveys have been completed to date. Satisfaction remains higher than target. Temporary Accommodation satisfaction is one area with the lowest level of satisfaction at 58.3%. Learning from the surveys will be C6 Satisfaction with repairs 68.3% 71.3% 70.3% 69.7% 75% 72.8% 70% used to address highlighted issues and improve satisfaction for residents living in Council temporary accommodation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
7.1 Q3 Corporate Performance Report 2025: 26 Apdx1Report 1.5 MB DownloadRead as text
PDF
Redbridge Corporate Performance Report Quarter 3 2025/26Report 566 KB Download

At this meeting

Whole meeting

Who was there

9 of 11 attended
KR
Councillor Kam RaiChair, present
MA
Councillor Mark A. SantosMember, present
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, apologies
VS
Councillor Vanisha SolankiVice-Chair, present
LJ
Councillor Lloyd Jacob DuddridgeMember, present
NB
Councillor Namreen B. ChaudhryMember, present
SE
Councillor Sahdia E WarraichMember, present
S(
Councillor Saima (Syeda) AhmedMember, present
CH
Claire HamiltonOfficer, expected

On this subject at Redbridge

Search all
  1. Redbridge Corporate Performance Report Quarter 3 2025/26This decision
  2. Redbridge Corporate Performance Report Quarter 2 2025/26Noted
  3. Redbridge Corporate Performance Report Quarter 4 2024/25Noted
  4. Redbridge Corporate Performance Report Quarter 3 2024/25Noted
  5. Redbridge Corporate Performance Report Quarter 2 2024/25Noted
  6. Redbridge Corporate Plan Performance Report Quarter 3 2023/24Noted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open