Resolved
RESOLVED THAT COMMITTEE: 1. Submit a new capital bid of £490k to Policy & Finance committee to be included in the capital programme, and 2. Agree that the programme should be delivered over 3/4 years.
Community Services agreed this item on Tuesday 19 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: 1. Submit a new capital bid of £490k to Policy & Finance committee to be included in the capital programme, and 2. Agree that the programme should be delivered over 3/4 years.
2.1This report builds upon previous ones considered by Committee. It provides an outline of proposed expenditure, which could if members wish form the basis for a capital bid to be submitted as part of the budget process currently underway.
2.2At your last meeting, committee asked that officer prepare some illustrative costing as a basis from which to take the matter forward.
3 ISSUES
3.1Four of the 18 play areas will have some form of improvement during the current financial year. Of the rest the following is proposed;
Play Area Work proposed Approximate Total Cost Cost Castle Field 1. Repaint all equipment. £8k 2. Repair/replace safety surface £25k £33k
Salthill, 1. Complete refurbishment with £100k Clitheroe steel equipment. 2. Replace safety surface £30k £130k
Colthirst (off 1. Replace multi -play unit £20k Chatburn 2. Repaint all equipment £4k £32k Rd), 3. Repair/replace safety surface £8k Clitheroe Edisford 1. Repaint all equipment. £2k £2k River Bank, Clitheroe Edisford Play 1. Repaint all equipment. £3k Area, 2. Repair/replace safety surface £8k £11k Clitheroe Hawthorne 1. Repaint all equipment £2k Place, 2. Repair/replace safety surface £6k £8k Clitheroe Highfield 1. Repaint all equipment £3k Road, 2. Repair/replace safety surface £8k £11k Clitheroe Highmoor 1. Repaint all equipment £5k Park, 2. Repair/replace safety surface £12k £17k Clitheroe Low Moor, 1. Repaint all equipment £4k Clitheroe 2. Repair/replace safety surface £10k £14k
Henthorn 1. Repaint all equipment. £5k Park, 2. Repair/replace safety surface £15k £45k Clitheroe 3. New multiplay £25k
Procters 1. Repaint all equipment. £4k Field 2. New equipment £25k £37k Whalley 3. Safety surface for new £8k equipment
Whalley 1. Extend current site and install £30k £30k Woodland a zip wire. Calderstones Woodland 1. Repaint all equipment. £1.5k Park, 2. Repair/replace safety surface. £6.5k Whalley £5k Kestor Lane, 1. Repaint all equipment £7k Longridge 2. Repair/replace safety surface £15k £22k
Mardale, 1. Repaint all equipment £5k Longridge 2. Repair/replace safety surface £8k £13k
John Smiths 1. Repaint all equipment £3k Longridge 2. Repair/replace safety surface £5k £8k
Redwood, 1. Repaint all equipment £2k Longridge 2. Repair/replace safety surface £7k £9k
Fielding 1. Replace wooden equipment £40k Arms, Mellor add multiplay, junior and cradle swings 2. New safety surface for above. £20k £60k
£490k
3.2It must be stressed that the above costs are estimates only, officers have used the most recent work undertaken as the basis for estimating the cost of the work.
3.3Much of the equipment appears worse than it is, simply because of the state of the paint work. As evidenced by the repainting work undertaken at Procters Field, Whalley, which transformed the multiplay piece, because the steel work itself was sound. Hence the reason for the extensive repainting programme work outlined.
3.4A note of caution must be expressed in relation to these estimates, because of the rising costs of raw materials. Recent evidence has seen extraordinary price rises in materials costs, which are impossible to predict.
3.5Whilst new equipment is always welcome, there is a finite amount of space in each play area, in addition 4 play areas will be improved over the coming months with s106 funding.
4 RISK ASSESSMENT
4.1The approval of this report may have the following implications.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Play AreasReport | 154 KB | DownloadRead as text |
Follow Community Services at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Aug 2026 | Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... | Agreed | Open |
| 25 Aug 2026 | Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... | Decided | Open |
| 25 Aug 2026 | Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... | Approved | Open |
| 25 Aug 2026 | Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... | Decided | Open |
| 26 May 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.