Resolved
RESOLVED THAT COMMITTEE: 1. Approve the proposed amendment to the capital programme as outlined, and 2. Ask Policy and Finance committee to amend the capital programme to enable the filter and tiling work to be completed as proposed.
Community Services approved this item on Tuesday 23 August 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: 1. Approve the proposed amendment to the capital programme as outlined, and 2. Ask Policy and Finance committee to amend the capital programme to enable the filter and tiling work to be completed as proposed.
2.1The Council has £44k allocated within the capital programme for the replacement of the three pool filters at Ribblesdale Pool, two provide water filtration for the main pool and one for the teaching pool. However, since that was submitted several years ago, the cost of replacement has risen to over £80k from the verbal estimates officers have received from suppliers recently.
2.2The rationale for either seeking such an increase over the budget or carrying out this major piece of work on building that is 50 years old no longer makes economic sense.
2.3The Council have had the filters inspected, with the idea of refurbishing them, which involves shot blasting them and relining them, but this is not viable, because the inspection assessed the thickness of the metal in the filters and although suitable for the purpose of filtering water, it is not recommended that they could withstand shot blasting and relining without risking damaging the metal shells of the filters and consequently filter failure.
2.4An alternative proposal would be to replace the filter media. This comprises the layers of sand and stone in the filters which together with the chemicals used help to ensure the water quality meets the levels for safe bathing.
3 ISSUES
3.1The pool facility is 50 years old and if the necessary funding were available to replace the filters, they would need to be cut up and removed from the plant room, because they are too big to remove in one piece. However new filters would not be a straight replacement it would require substantial amendment to the pipe work to accommodate a new design. All of which would take in the region of 2 months or more to complete, which even with available funding would make this year’s window of opportunity impossible to achieve allowing for tenders to be drawn up and the time to go to the market. (The work would be programmed for Nov/Dec) which historically is the quietest period for the pool.
3.2Spending so much to replace an important aspect of the pool plant would not guarantee that a failure with another aspect of the building would not require an enforced closure of the building. Given the age of the facility, much of the work done in the past few years has been to replace failing equipment and plant needed to keep the building running.
3.3The tiling in the pool was repaired some years ago, however some have had to be repaired in the intervening period and although these have been carried out using special waterproof compounds that can be applied underwater. The best and most cost-effective way to carry out this maintenance is with the pool closed and empty of water. Thereby allowing a thorough inspection of the pool tiling and a replacement programme to be carried out as needed. It also ensures work on the filters is not reliant on the valves alone to hold the water back from the pool reaching the plant room.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ribblesdale Pool FiltersReport | 90 KB | DownloadRead as text |
Follow Community Services at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Aug 2026 | Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... | Agreed | Open |
| 25 Aug 2026 | Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... | Decided | Open |
| 25 Aug 2026 | Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... | Approved | Open |
| 25 Aug 2026 | Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... | Decided | Open |
| 26 May 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.