Ribble Valley Borough Council
Community Services, Tuesday 18 October 2022 at 6.30pm

Mardale Playing Fields

Agreed Committee 1 paper

Community Services agreed this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.

Item375

Resolved

RESOLVED THAT COMMITTEE 1. Ask officers to prepare a drainage improvement scheme based on vertidraining and sand slitting/filling over a one or two year period; 2. Request a report to a future meeting of this committee with an update on the scheme, and 3. Agree to prepare for the implementation of the scheme as soon as the 2022/23 football season is complete.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Community Services

Background

2.1At Mardale Plying Fields there are four football pitches used primarily by Longridge Town FC and Longridge Juniors.

2.2For many years the pitches have suffered from poor drainage rendering them unplayable at times through the winter period. Although the pitches themselves are very level and in dry weather provide an excellent playing surface.

2.3Earlier in the year, the ditch which runs around the southern boundary of the field was cleared out, it had become over the years, silted up and overgrown. This contributed to make the limited drainage in the field work better. Though this did not prevent matches being cancelled over the winter.

2.4A section 106 contribution of £80,400 was allocated from the Dilworth development for the improvement of the pitches.

2.4The Council sought tenders for a drainage scheme on the pitches designed to be undertaken during the summer period.

2.5A topographical survey was undertaken on the pitches as part of the preparation for the drainage design.

2.6Council officers are collaborating with the Lancashire FA on a national project aimed at improving grass pitch quality. This has involved an inspection by an agronomist to all our pitches and a report and recommendations will follow.

3 ISSUES

3.1The tenders came back considerably higher than the sum available, the lowest was over £100k above the budget sum. 3.2 The window for doing work on the pitches this year has now passed and plans need to be put in place to carry out work during Spring/Summer 2023, ready for the 2023/24 football season.

3.3The teams which play on the site were disappointed that no improvement work could be carried out this year, because it means a winter of interrupted play. Therefore, it is important that a plan is made to ensure whatever decision the Council makes can be carried out next year and the budget invested.

Options

4.1Committee could ask Policy and Resources to consider allocating an additional sum for the work to be completed next year, however given that the lowest tender was over £100k higher this year, it can be expected that figure will rise by at least another £10k. given the other priorities for service delivery the Council has over the next year, such a significant sum is unlikely to be achievable.

4.2The pitches could be heavily spiked with our “Verti drain” machine followed by spreading of fine/medium sand mix, up to 80 tonnes of sand per pitch would be required. The sand would cost c£6,500 per pitch, plus the time to verti-drain and a contractor to spread the sand which would add up to a further £4,000 per pitch. This would potentially allow sand to be applied over two consecutive seasons, thereby improving pitch quality significantly within the budget we have available.

4.3The Council could wait for the FA report and then price up the proposals in that report, which are based on hierarchy with improving soil quality at the top descending to physical drainage works at the bottom.

4 RISK ASSESSMENT

4.1The approval of this report may have the following implications:

• Resources –Any additional capital investment above the s106 money will need to be resourced via capital bids. The cost of any scheme arising from the FA requirements at this stage are still unknown.

• Technical, Environmental and Legal – None arising as a direct result of this report.

• Political – Work carried out on the pitches to enable them to be used throughout the winter period will be welcomed.

• Reputation – None arising as a direct result of this report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mardale Playing FieldsReport 67 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 23 attended
RN
Councillor Richard NewmarkChair, present
JA
Councillor Jan Alcock JPCommittee Member, present
SA
Councillor Stephen AtkinsonCommittee Member, present
DB
Councillor David BirtwhistleCommittee Member, present
SB
Councillor Stella Brunskill JPCommittee Member, expected
SC
Councillor Stuart CarefootCommittee Member, present
R(
Councillor Rosemary (Rosie) ElmsVice-Chair, present
SF
Councillor Stewart FletcherCommittee Member, present
AH
Councillor Angeline HumphreysCommittee Member, present
GM
Councillor Ged MirfinCommittee Member, apologies
SO
Councillor Simon O'RourkeCommittee Member, present
SR
Councillor Sarah RainfordCommittee Member, apologies

All 23 on the meeting page

On this subject at Ribble Valley

Search all
  1. Mardale Playing FieldsThis decision
  2. 3/2026/0295 - Brian Holden Memorial Playing Field Mardale Road Longridge PR3 3EUDeferred
  3. Naming of Mardale Playing FieldsApproved

More from Ribble Valley Community Services

All decisions
MeetingDecisionOutcome
25 Aug 2026 Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... Agreed Open
25 Aug 2026 Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... Decided Open
25 Aug 2026 Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... Approved Open
25 Aug 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... Decided Open
26 May 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies