Resolved
RESOLVED THAT COMMITTEE: 1. Grant planning permission (contrary to the recommendation) subject to conditions. 2. The application is to be brought back to a future committee meeting for decision with conditions drafted.
Planning and Development decided this item on Thursday 1 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: 1. Grant planning permission (contrary to the recommendation) subject to conditions. 2. The application is to be brought back to a future committee meeting for decision with conditions drafted.
RECOMMENDATION FOR PLANNING AND DEVELOPMENT COMMITTEE
REFUSAL
DATE: 1 June 2023 REF: SK CHECKED BY: LH
APPLICATION REF: 3/2022/1039
GRID REF: SD 373384 440661
DEVELOPMENT DESCRIPTION:
PROPOSED CONSTRUCTION OF TWO NEW DETACHED DWELLINGS WITH ASSOCIATED ACCESS AND GARDEN AREAS. RESUBMISSION OF 3/2021/1263. LAND ADJACENT TO 115 KEMPLE VIEW, CLITHEROE BB7 2QJ. CONSULTEE RESPONSES/ REPRESENTATIONS MADE:
PARISH COUNCIL:
No representations received in respect of the application.
LANCASHIRE COUNTY COUNCIL (LOCAL HIGHWAYS AUTHORITY):
The level of car parking and turning areas are considered acceptable. There are no garages proposed. Each dwelling requires a secure, covered cycle store and electric vehicle charging point. The proposed highway drain diversion shown on drawing 'Site drainage diversion and proposed building outline' PHA/366-100 is acceptable.
Should consent be granted, the following conditions are requested:
• No development shall take place, including any works of demolition, until a construction method statement has been submitted to and approved in writing by the Local Planning Authority • Prior to commencement of any building works, the drainage diversion works shown on drawing 'Site drainage diversion and proposed building outline' PHA/366-100 shall be completed in accordance with Lancashire County Council Specification under an appropriate agreement with access right s agreed thereafter. • The new estate road shall be constructed in accordance with the Lancashire County Council Specification for Construction of Estate Roads to at least base course level before any development takes place within the site. • Prior to the first occupation of any dwelling, the car parking and turning areas shall be provided and maintained thereafter for the purposes of vehicle parking. • Prior to the first occupation each dwelling shall have an electric vehicle charging point. Charge points must have a minimum power rating output of 7kW, be fitted with a universal socket that can charge all types of electric vehicle currently.
UNITED UTILITIES (UU):
United Utilities have identified that a number of assets (public sewers) cross the site. Following review of the proposed site layout, along with the CCTV investigations of the sewer and the topographical survey, it appears that our required access to the public sewers are provided. Request that the submitted drainage easement, drainage diversion and building outline plans are listed as approved documents on any subsequent Decision Notice.
Further site-specific investigations would be needed to determine the precise location of United Utilities assets. Should consent be granted, UU have requested the following condition(s):
1. No construction shall commence until details of the means of ensuring the sewers that are laid within the site boundary are protected from damage as a result of the development have been submitted to and approved by the Local Planning Authority in writing. The details shall outline the potential impacts from construction activities and the impacts post completion of the development on the sewers that cross the site and identify mitigation measures to protect and prevent any damage to the pipelines both during construction and post completion of the development. Any mitigation measures shall be implemented in full in accordance with the approved details. 2. Prior to the commencement of development, details of a sustainable surface water drainage scheme and a foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The drainage schemes must include:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
3/2022/1039: Land adj Kemple View, Clitheroe BB7 2QJReport | 345 KB | DownloadRead as text |
Follow Planning and Development at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Aug 2026 | 3/2025/0801 - Land to east of Salesbury View WilpshireRESOLVED THAT COMMITTEE: REFUSE PLANNING PERMISSION for the following reasons: 1. The proposed development would be o... | Refused | Open |
| 27 Aug 2026 | 3/2022/0317 - Land at Higher Standen Farm and Part Littlemoor Farm ClitheroeRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): 1. Unless explicitly requir... | Approved | Open |
| 27 Aug 2026 | 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): The development hereby perm... | Approved | Open |
| 27 Aug 2026 | 3/2025/0997 - Land off Henthorn Road Clitheroe BB7 3BYRESOLVED THAT COMMITTEE: Application deferred to enable an alternative access directly off Henthorn Road to serve the... | Deferred | Open |
| 27 Aug 2026 | 3/2026/0230 - Land to the south of Ribblesdale Primary School west and north of Higher Standen DriveRESOLVED THAT COMMITTEE: DEFER AND DELEGATE to the Director of Economic Development and Planning for approval subject... | Deferred | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.