RESOLVED THAT COMMITTEE: 1. Approve the new capital programme scheme for the 2023/24 financial year for the Financials System Server Upgrade and associated software upgrades at a cost of £13,500. 2. Approve the use of transparency code new burdens monies that are within earmarked reserves to fund the new capital scheme.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 12 SEPTEMBER 2023 title: FINANCIALS SERVER OPERATING SYSTEM submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: LAWSON ODDIE
1 PURPOSE 1.1 To request approval for an additional capital programme scheme to enable the replacement of the financial server operating system. The scheme would also see an upgrade to the reporting software at the same time and a system version upgrade. 1.2 Relevance to the Council’s ambitions and priorities: Community Objectives – none identified. Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer need. Other considerations – none identified. 2 BACKGROUND 2.1 Already included within the capital programme are a number ICT related schemes. These largely relate to the main ICT infrastructure across the council and are not system related. 2.2 The Council have a number of servers running Windows Server 2012 R2 which will be de-supported by Microsoft in October, and therefore require an upgrade. 2.3 Other server operating system upgrades have been able to be undertaken in-house through the provision of information from the various system providers and Microsoft. However, it has been identified that the system providers for the Financials system and the Planning system require the upgrades to be undertaken by themselves. 2.4 The Planning NEC system server operating system can be upgraded within an existing capital programme scheme, falling under the Planning and Development Committee. However, no such scheme is available for the Financials server operating system and associated work. 3 PROPOSED SCHEME DETAILS 3.1 The servers that support the Civica Financials system are currently running Windows Server 2012 R2 which will be de-supported by Microsoft in October. There are some options for extended support, but the most cost-effective way forward would be to upgrade now. The upgrade would be to the 2019 version to ensure there are no compatibility issues. 3.2 In addition, the Business Objects query tool that is used together with the financials system requires an upgrade. Furthermore, a new release of the Civica Financials software is also now available, which we are looking to move to within our existing contract. 3.3 This scheme would look to have all three elements of upgrade work undertaken by Civica UK Limited, together with assistance from our in-house ICT team. 3.4 If approved, the majority of the work would be undertaken towards the end of September 2023, with some further work between January and March 2024 to upgrade the live version of the financials system with the latest version of the software, after all necessary testing has been done in a test environment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.