AI summaryRibble Valley Policy and Finance Committee approved capital slippage of £1,756,430 on main schemes, £235,287 on UK Shared Prosperity Fund schemes, and £52,675 on Rural England Prosperity Fund schemes into 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedMain, UKSPF and REPF capital schemes
MoneyThree separate slippage amountsMain, UKSPF and REPF schemes approved
What happens nextBudgets carried into 2026/27Work continues into next financial year
Who it affectsPolicy and Finance Committee schemesMain, UKSPF and REPF capital programmes
What was decided
The Committee approved slippage of £1,756,430 on the main Policy and Finance Committee capital schemes listed at paragraph 3.5 of the report.
The Committee approved slippage of £235,287 on the UK Shared Prosperity Fund capital schemes.
The Committee approved slippage of £52,675 on the Rural England Prosperity Fund capital schemes.
Why
Of the 9 main capital schemes in the revised programme, 3 were completed in year and 6 remain ongoing, resulting in requested slippage of £1,756,430 into 2026/27.
Of the 14 UK Shared Prosperity Fund schemes in the revised programme, 6 were completed in year and 8 were not, resulting in requested slippage of £235,287 into 2026/27.
Of the 8 Rural England Prosperity Fund schemes in the revised programme, 2 were completed in year and 6 were not, resulting in requested slippage of £52,675 into 2026/27.
What happens next
Slipped schemes will continue into 2026/27, with completion dates ranging from July 2026 to throughout 2026/27. Report P180, P189
The Director of Economic Planning and Development will submit a separate report on the Ribble Valley Shared Prosperity Fund. Report P189
Further details on UKSPF and REPF schemes will be given in a separate report presented at this meeting.
The money
£1,756,430 Slippage approved on main Policy and Finance Committee capital schemes
£235,287 Slippage approved on UK Shared Prosperity Fund capital schemes
£52,675 Slippage approved on Rural England Prosperity Fund capital schemes
£364,353 Actual expenditure on this Committee's main capital programme in 2025/26
£403,207 Actual expenditure on UK Shared Prosperity Fund schemes in 2025/26 Report 4.2
£77,405 Actual expenditure on Rural England Prosperity Fund schemes in 2025/26
£2,072,035 Capital resources already in place to fund the requested slippage to 2026/27 Report P42
Options considered
Chosen: Approve slippage of £1,756,430 on main capital schemes. 6 of 9 main schemes remain ongoing and require budget to be carried forward into 2026/27.
Chosen: Approve slippage of £235,287 on UK Shared Prosperity Fund schemes. 8 of 14 UKSPF schemes were not completed in year and require budget to be carried forward.
Chosen: Approve slippage of £52,675 on Rural England Prosperity Fund schemes. 6 of 8 REPF schemes were not completed in year and require budget to be carried forward.
Implications
Financial: Capital resources of £2,072,035 are already in place to fund the requested slippage to 2026/27 for this Committee's capital programme. Report P42
Financial: Overall expenditure on the Committee's capital programme and UK Shared Prosperity Fund capital schemes in 2025/26 was contained within approved revised estimate budgets, requiring less capital financing than budgeted. Report P42
Risk: Sound financial planning for known capital commitments safeguards the reputation of the Council. Report P42
Equalities: Equality and diversity issues are examined as part of the capital bid appraisal process. Report P42
Who and where
Ribble Valley Borough Council's Policy and Finance Committee Report 1.2, P8
Council offices (mains and LED lighting upgrade, fire alarm system, solar panels) Report P23, P171, P49
Community organisations receiving UK Shared Prosperity Fund grants Report P58, P59
Rural communities receiving Rural England Prosperity Fund grants Report P70, P71
Timeline
16 JUNE 2026: Policy and Finance Committee meeting date Report P2
2025/26 financial year: Original capital programme year for the schemes Report 1.1, 2.1
2026/27 financial year: Slippage to be carried forward into this year Report 1.1
July 2026: Expected completion of Council Office Fire Alarm Replacement Report P180
February 2027: Expected completion of Network Infrastructure slippage work Report P114
March 2027: Expected completion of Council Offices Mains and LED Lighting Upgrade and Software Upgrade for Regulatory Services Report P94, P147
Throughout 2026-27: Work on Ribble Valley Shared Prosperity Fund to continue Report P189
Plain English for the jargon
Slippage: Budget that is carried forward from one financial year to the next for capital schemes that are not yet complete.
Outturn: The actual final income or expenditure for a financial year, compared to the budget.
UK Shared Prosperity Fund (UKSPF): A central government fund providing capital and revenue for local investment projects.
Rural England Prosperity Fund (REPF): A government fund that supports rural businesses and communities, reported alongside UKSPF.
Revised Estimate: An updated budget for a capital scheme after changes during the financial year.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item128
Resolved
RESOLVED THAT COMMITTEE: 1. Approved slippage of £1,756,430 on the main Policy and Finance Committee capital schemes listed at paragraph 3.5 of the report. 2. Approved slippage of £235,287 on the UK Shared Prosperity Fund capital schemes. 3. Approved slippage of £52,675 on the Rural England Prosperity Fund capital schemes.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 16 JUNE 2026 title: CAPITAL OUTTURN 2025/26 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: JEAN WADDINGTON
1 PURPOSE
1.1The purpose of this report is to review the final outturn of the 2025/26 capital programme for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2025/26 financial year to the 2026/27 financial year.
1.2This report covers the Policy and Finance Committee capital schemes, including the Ribble Valley Shared Prosperity Fund and also the additional schemes in the capital programme that relate to the UK Shared Prosperity and Rural England Prosperity Funds.
1.3Relevance to the Council’s ambitions and priorities: • Community Objectives – none identified. • Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need. • Other Considerations – none identified.
2 2025/26 CAPITAL PROGRAMME BACKGROUND
Main Committee Schemes (for the purpose of reporting Ribble Valley Shared Prosperity Fund is counted as one scheme).
2.1There were 7 capital schemes for this Committee’s original estimate budget, totalling £2,108,540. These were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2025 and March 2025 respectively. This included 2 new schemes for 2025/26 and budget for 5 schemes that had been moved from the 2024/25 capital programme.
2.2In addition, slippage of £202,140 from financial year 2024/25 was approved by this Committee in June 2025. This was in respect of 4 schemes.
2.3Additional approval of budget of £69,760 in respect of one scheme brought forward from the 2027/28 capital programme was agreed by this Committee at their meeting in November 2025.
2.4The above resulted in an overall approved capital budget 2025/26 for this Committee of £2,421,250 in respect of 11 schemes.
2.5Later in the year the 2025/26 main capital programme budget was revised in respect of these 11 schemes to 9 schemes with a budget of £2,168,750 and was then approved by the Policy and Finance Committee in January 2026. This followed a review of progress on all schemes in the capital programme. The revised estimate budget for this Committee is shown at Annex 1.
44-26pf 1 of 19 UK Shared Prosperity Fund and Rural England Prosperity Fund Schemes
2.6Additional schemes in the capital programme in respect of the UK Shared Prosperity Fund and Rural England Prosperity Fund, and reportable to this Committee, are shown in Annex 2 and 3. There were 14 UKSPF and 8 REPF schemes that were approved for this committee totalling £638,494 and £130,081 respectively in 2025/26.
2.7During the financial year this Committee has received reports monitoring the progress of schemes within this Committee’s capital programme and the UK Shared Prosperity Fund/Rural England Prosperity Fund capital programmes.
3 CAPITAL OUTTURN 2025/26 – POLICY AND FINANCE COMMITTEE SCHEMES
Budget Total Budget Original Slippag Additional Revised Actual Requested Moved Approved Moved Estimate e from Approvals Estimate Expenditure Slippage From Budget to 2025/26 2024/25 2025/26 2025/26 2025/26 into 26/27 2024/25 2025/26 2026/27
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.