RESOLVED THAT COMMITTEE: 1. Recommend to Full Council that a resolution is made to adopt the new Local Development Order (2024) for the Lancashire Advanced Engineering and Manufacturing Enterprise Zone at Samlesbury for the next ten years and for this to be submitted to the Secretary of State for their consideration. 2. Recommend to Full Council adoption of the new Masterplan (2024) for the Lancashire Advanced Engineering and Manufacturing Enterprise Zone at Samlesbury for Development Management purposes. This is subject to minor changes as necessary which are delegated to the Director of Economic Development and Planning.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
1.0BACKGROUND AND PURPOSE 1.1.1 In 2011 land at BAE Samlesbury and Warton sites was designated as Lancashire’s first Enterprise Zone (EZ). In order to support the development of the sites a simplified planning regime in the form of a Local Development Order (LDO) and accompanying Masterplan was adopted for each.
1.1.2 The Samlesbury EZ site LDO and Masterplan were adopted in 2014 with a lifetime of 10 years. The provisions of the LDO allowed for its replacement at any time or renewal with new terms and conditions if development was not completed by the time of its expiry. An updated replacement LDO was adopted on XXXX together with this replacement Masterplan which will support it. Significant progress has been made in bringing forward the site and the updated LDO and Masterplan should enable build out to be completed. It should be noted that the level of development will not increase but will remain the same as set out in 2014.
Fig. 1 - Lancashire County Council advertisement board.
2.0VISION FOR THE SITE 2.1.1 Since gaining Enterprise Zone status and adopting a Masterplan and LDO for the site, significant site infrastructure and utilities have been put in place enabling a number of key developments to be delivered. These include BAE’s Academy for Skills and Knowledge, AEM Defence Logistics and Asset Management Facilities and the University of Sheffield’s Advanced Manufacturing Research Centre North-West. The Enterprise Zone is therefore supporting genuine additional growth, creating new businesses and is building a strong base from which transformational growth in the Advanced Engineering and Manufacturing (AEM), Sci-tech and Cyber sectors is anticipated to come forward at pace. The site is currently on track to deliver around 2,528 high value new jobs on site. The potential for further associated technology spin-out businesses, new business starts and SME’s is significant with the potential to deliver a further 5,000-6,000 high value jobs in the wider Lancashire sub region in the long term.
2.1.2 Strategically the site plays a key role in anchoring and developing an AEM, Sci-tech and Cyber enterprise corridor linking to Lancashire’s key universities and extensive AEM capabilities. This will capitalise on new and emerging market opportunities and will strengthen and grow local supply chains through inward investment and modernisation of the sectors. Lancashire forms a key part of the North West cyber corridor linking to Manchester and Lancaster and is positioned as a national core of expertise across AEM, Sci-tech and Cyber sectors. Samlesbury EZ now forms part of a cluster of 4 Enterprise Zone sites in Lancashire. These form the Lancashire Advanced Manufacturing and Energy Cluster (LAMEC). Together these sites provide a strategic resource and opportunity for Lancashire to build on national and international strengths in aerospace, advanced engineering, manufacturing, sci-tech, cyber chemicals and energy. Fig.2 - Aerial view showing SEZ Site.
3.0DEVELOPMENT PRINCIPLES 3.1.1 The vision outlined for the site was established in the 2014 Masterplan and is carried forward into this Masterplan. Delivery of this vision is being progressed via a set of overarching development principles which in turn inform more detailed principles relating to the delivery of built form, infrastructure, ecology and landscaping. The overarching development principles are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.