RESOLVED THAT COMMITTEE: 1. Approved that the R&C grants window for application was re-opened and closed on 14 February 2025 for the current financial year only. 2. Requested that details of the grant schemes be sent out to all Councillors to promote within their ward.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: TUESDAY, 7 JANUARY 2025 title: RECREATION AND CULTURE GRANTS submitted by: ADAM ALLEN DIRECTOR OF COMMUNITY SERVICES principal author: MARK BEVERIDGE HEAD OF CULTURAL AND LEISURE SERVICES
1 PURPOSE
1.1To seek Committee approval for an extension of the deadline for applicants to apply for a Recreation and Culture (R&C) Grant.
1.2Relevance to the Council’s ambitions and priorities
• Community Objectives – To sustain a strong and prosperous Ribble Valley, encompassing our objective to encourage economic development throughout the borough, with a specific emphasis on tourism. 2 BACKGROUND
2.1In the last financial year, 2023/24 there was some confusion for organisations applying for grants which the Council offers. It is thought that this may have been because both the Voluntary Organisation (VO) grants and the R&C Grants had closing dates at the same time. Consequently, some organisations made VO applications and others went for a R&C grant. This led to some VO applications being passed to the R&C grant panel to consider.
2.2As a result of this there was a change to the submission date for R&C grants to an earlier date (30th November 2024), to avoid a clash of closing dates.
2.3This amendment was advertised on the Council’s website and social media channels plus a media release was issued to help get the message out to organisations in the Borough.
2.3All the grants which the Council provides are agreed in advance of the financial year they are granted for. The current grants which will be considered are for projects to be completed in 2025/26.
3 ISSUES
3.1The significant difference between VO and R&C grants is the former has a different set of criteria for applicants compared to the latter. Specifically, the R&C grants are focused on capital items in the main, rather than providing ongoing revenue support, and are recreation and culture focused.
3.2Consequently, the organisations which applied for VO grants in 2023/24, did so because they were volunteer run organisations, however in doing so they were asked to supply differing sets of information regarding their application. When these were passed to the R&C grants for consideration, the organisations were then surprised to be asked for additional information to meet the different criteria. It was hoped to address this by changing the closing dates to provide that separation between the two different grant pots.
3.3The number of applications received within the revised closing date of 30th November for R&C grants, was 5, which is around 25% of the number received last year. Some of this reduction maybe due to the allocation of UKSPF for rural areas, which several rural based organisations have benefitted from. It is not known whether the change in closing date has directly impacted the number of applications. However, it is considered that by re-opening the application process for further bids it will ensure that any organisation that was not aware of the change to the earlier deadline date will have a chance if they wish to apply.
4. RISK ASSESSMENT
4.1The approval of this report may have the following implications.
• Resources – The R&C Grant budget is agreed for the 2025/6 year and all applicants will be considered by the Grants panel which forms the basis of a report which is then submitted to the Community Committee for agreement. The subsequent payment is administered by officers, following compliance with the grant conditions agreed by the organisation in receipt of the grant offer.
• Technical, Environmental and Legal – The Grants Panel Membership is agreed by Community Committee at the first meeting of the Civic year and is composed of a politically balanced group of councillors who determine which applicants are recommended for a grant and the sum to be awarded, that is then considered by the Community Committee.
• Political – No implications identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.