RESOLVED THAT COMMITTEE: 1. Approved the overall revised capital programme for 2024/25. 2. Approved to reverse the decision of the Policy and Finance Committee of 18 June 2024 Minute 111 – UK Shared Prosperity Fund resolution number 3 and agree that the stone sets should not be re-laid at Clitheroe Market but re-purposed within the Castle Grounds.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
2.1The Council operate a capital programme, with a review undertaken every year to examine whether the programme still marries with our current and future plans.
2.2As part of that review, we also undertake a detailed examination of the current year’s capital schemes to make any adjustments to the budgets, based on progress, and to ensure that they are included in the correct financial year, should any scheme delays have been identified.
3 CURRENT APPROVED CAPITAL PROGRAMME 2024/25
3.1The original capital programme for 2024/25 was approved by Full Council in March 2024. Since then, regular reports have been presented to all committees with regard to the progress of the capital programme. There have also been a number of further approvals and adjustments made during the year. As a result, the total approved budget for the Council’s overall capital programme of 74 schemes is £8,991,430.
3.2The table below provides a summary of the in-year movements, leading to the total approved budget:
Scheme Budget Capital Programme 2024/25 movements Count 2024/25 2024/25 £
Original Estimate 2024/25 19 2,671,190 Schemes and Budget Moved from 2023/24 16 3,680,810 Total Original Estimate as per Budget Book 35 6,352,000 Slippage from 2023/24 13 1,074,300 Additional Approvals in year 2024/25 (largely UKSPF/REPF schemes) 25 1,430,130 Schemes Brought Forward 1 135,000 Total Approved Budget 2024/25 74 8,991,430
14-25pf 1 of 16 4 REVISING THE 2024/25 CAPITAL PROGRAMME 4.1 We have now discussed each of the schemes in the capital programme with budget holders and reviewed the programme to reflect progress on schemes and estimated full year expenditure. 4.2 Following this review, the proposed revised estimate is £5,414,150 for 65 schemes, which is a reduction of £3,577,280 from the previously approved capital programme budget and a net reduction of 9 schemes. The detail around these movements is provided at Annex 1, but a summary is provided below: Impact on Impact on Capital number Capital programme 2024/25 Programme of Capital Proposed Revised Estimate changes Budget schemes 2024/25 in 2024/25 £ Total Approved Budget 2024/25 74 8,991,430
Schemes where full budget is proposed to be moved to 2025/26 -9 -1,869,500
Schemes where part of the budget is proposed to be moved to 2025/26 0 -1,780,980
Schemes where budget is proposed to be reduced in 2024/25 0 -57,380
Schemes where budget is proposed to be increased in 2024/25 0 36,830 Changes to UKSPF/REP schemes agreed at Policy and Finance 0 93,750 Committee 21 Jan 2025 Proposed Revised Estimate Capital Programme 2024/25 65 5,414,150
5 FINANCING OF THE 2024/25 CAPITAL PROGRAMME 5.1 The capital resources to finance the capital programme for 2024/25 have also been revised, as shown in the table below. Total Revised Approved Estimate Budget Budget Financing Proposed Financing 2024/25 Changes 2024/25 £ £ £ Capital Programme Budget 8,991,430 -3,577,280 5,414,150 RESOURCES Grants and Contributions DLUHC - Disabled Facilities Grants -1,104,690 604,950 -499,740 Onward Homes Contribution -50,260 0 -50,260 DLUHC - UK Shared Prosperity Fund -1,956,540 353,490 -1,603,050 Changing Places Grant Funding -176,120 18,480 -157,640 DEFRA Food Waste Grant Funding -715,550 715,550 0 Sport England Grant Funding -25,000 3,650 -21,350 S106 Funding -2,080,080 1,000,640 -1,079,440 Usable Capital Receipts Usable Capital Receipts Reserve -166,690 4,270 -162,420
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies