Ribble Valley Borough Council
Planning and Development, Thursday 23 October 2025 at 6.30pm

HARP Update

Approved Planning 1 paper

AI summaryRibble Valley planning committee approves a temporary part-time Assistant Planning Officer post for two years to handle the Haweswater Aqueduct project, funded by Section 106 payments, and refers it to Personnel Committee.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAssistant Planning Officer, temporary 2 years, subject to review
Money£27,694 to £35,412 per annumSalary scales 4 to 6, depending on qualifications, funded by Section 106
What happens nextReferral to Personnel CommitteeTo add the post temporarily to the establishment
Who it affectsPlanning development management serviceSpecifically delivery of the Haweswater Aqueduct Resilience Programme in Ribble Valley

What was decided

Committee approved the creation of a part-time Assistant Planning Officer for a temporary two-year period, subject to review. Report P24

Committee agreed to refer the matter to Personnel Committee so the post can be included temporarily within the council's establishment. Report P24, 3.3

Why

Two planning applications for the Haweswater Aqueduct Resilience Programme in Ribble Valley were approved in January 2024 and a contractor has now been appointed, requiring officer resource to manage condition discharges and ongoing work. Report 2.4, P9, 3.3

Five Section 106 payments have been secured to fund the post, and a temporary two-year basis is proposed so the role can be reviewed in light of potential Local Government Reorganisation. Report 3.4

What happens next

The post is to be referred to Personnel Committee for inclusion in the establishment on a temporary basis. Report P24

The post will then be advertised, and the role is scheduled for review at the end of the two-year period. Report 3.4, P26

The money

  • £27,694 to £29,064 per annum Scale 4 (scp 10-13) salary for postholders with relevant A levels or similar Report P28, P41
  • £30,518 to £32,061 per annum Scale 5 (scp 16-19) salary for postholders with a relevant degree Report P28, P41
  • £33,143 to £35,412 per annum Scale 6 (scp 21-24) salary for postholders eligible for RTPI professional membership Report P28, P41

Options considered

  • Chosen: Create the part-time Assistant Planning Officer post on a temporary two-year basis, subject to review. Five Section 106 payments are secured and a temporary basis allows review given possible Local Government Reorganisation Report 3.3, 3.4, P24

Implications

  • Financial: Section 106 funding has been secured for the post; legal agreements and assurances are in place for administering the scheme. Report P23
  • Legal: Legal have been consulted and their comments are incorporated into the report. Report P23
  • Risk: Political, reputation and equality and diversity risks are recorded as not applicable. Report P23

Who and where

  • The council's planning development management team, which will gain a part-time officer to handle HARP work Report P30, P32
  • United Utilities and Cascade Infrastructure (Strabag, Equitix and GLIL Infrastructure) as the HARP delivery partners Report 2.6
  • Residents in the Bowland and Marl Hill sections of the Ribble Valley, where the pipeline replacement will take place Report P11

Timeline

  • 16 March 2023: Planning and Development Committee resolved to approve both HARP planning applications in Ribble Valley Report 2.2
  • 19 July 2023: Secretary of State decided not to call in the applications Report 2.3
  • 19 January 2024: Both Section 106 legal agreements completed and planning applications approved Report 2.4
  • From October 2025: Further Ground Investigation works expected to start in Ribble Valley Report P11
  • Late 2026 to mid 2028: Highways works expected, dependent on detailed design Report P11
  • Early to mid 2027: Enabling works indicatively scheduled Report P11
  • 2028: Main construction currently expected to start on the Bowland Section Report P11
  • Mid 2028: Main construction currently expected to start on the Marl Hill Section Report P11
  • Two years after appointment: The temporary Assistant Planning Officer post is to be reviewed Report 3.4, P26

Plain English for the jargon

  • HARP: Haweswater Aqueduct Resilience Programme, replacing six tunnel sections of a 110km pipeline from the Lake District through Lancashire to Greater Manchester
  • DPC: Direct Procurement for Customers, an Ofwat model introduced around 2019 under which a water company competitively tenders a third party to design, build, finance, operate and/or maintain new infrastructure
  • CAP: Competitively Appointed Provider, the third party appointed through the DPC process
  • TBM: Tunnel Boring Machine, used for more than one section of the pipeline replacement
  • Section 106: Planning obligation under Section 106 of the Town and Country Planning Act used to secure contributions from developers
  • RTPI: Royal Town Planning Institute, the professional body for planners; eligibility for membership indicates Scale 6 pay
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item376

Resolved

RESOLVED THAT COMMITTEE: Approve the creation of a part-time Assistant Planning Officer for a temporary 2-year period (subject to review) and refer the matter to Personal Committee to include the post temporarily within the establishment.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Planning and Development

DECISION

RIBBLE VALLEY BOROUGH COUNCIL REPORT TO PLANNING AND DEVELOPMENT COMMITTEE meeting date: THURSDAY, 23rd OCTOBER 2025 title: HAWESWATER AQUEDUCT RESILIENCE PROGRAMME submitted by: DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING principal author: NICOLA HOPKINS – DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING

1 PURPOSE

1.1To update Committee on the Haweswater Aqueduct Resilience Programme (HARP) project and to seek approval to appoint a part time Assistant Planning Officer.

2 BACKGROUND 2.1 The Haweswater Aqueduct Resilience Programme (HARP) is a scheme to replace sections of the Haweswater Pipeline. The Aqueduct is a 110km pipeline which runs from the Lake District, through Lancashire and into Greater Manchester. Completed in the 1950’s, the pipeline needs essential maintenance to ensure it can continue to supply customers. The proposed plans include the replacement of six tunnel sections along the pipeline route and nine planning applications have been submitted across seven local planning authorities for approval to carry out the work.

2.2Two sections of the replacement pipelines are within the Ribble Valley and the development has been subject to two planning applications to the Local Planning Authority. Both applications were considered by Planning and Development Committee on 16 March 2023. Committee resolved to approve both applications subject to confirmation from the Secretary of State that the applications would not be called in and subject to the satisfactory completion of a Legal Agreement.

2.3On 19 July 2023 the Secretary of State decided not to call in the applications, content that they should be determined by the Local Planning Authority.

2.4On the 19 January 2024 both legal agreements were completed, and the planning applications were approved.

UPDATE 2.5 Since the planning decisions were issued United Utilities have formally tendered for a contractor to undertake the works. The contract has now been agreed. Strabag, Equitix, and GLIL Infrastructure, known as Cascade Infrastructure, have been appointed to design, construct, maintain, and finance the replacement of six tunnel sections of the existing aqueduct. They are responsible for the full design and construction scope of the project, with Strabag UK leading the design and construction.

2.6For Committees information HARP has been procured by United Utilities Water and is the first to be delivered under the Direct Procurement for Customers (DPC) model introduced by Ofwat around 2019. DPC is a process through which a water company competitively tenders for a third-party (a competitively appointed provider or CAP) to design, build, finance, operate and/or maintain new infrastructure. A special licence granted by Ofwat (called the Allowed Revenue Direction) means the costs of the project are recovered directly from customers over the life of the contract. It is the first time this approach has been used in the UK Water Industry. 2.7 In respect of the work programme, following the completion of the contract, this is as follows:

•In Ribble Valley initial surveys (topo, GPR and utilities) are now underway to inform the design. Some further Ground Investigation works will be required starting October 2025 •Detailed design is currently being undertaken •Period of discharge of planning conditions and obtaining outstanding consents •Highways works, dependant on detailed design, currently expected to be sometime late- 2026 to mid-2028 •Enabling works, indicative dates from early to mid-2027 •Main construction currently expected to start from 2028 on the Bowland Section and mid- 2028 on Marl Hill Section •The tunnel boring machines (TBM) will be used for more than one section, the TBM from the Bowland Section will go to another section afterwards and the TBM for Marl Hill will come from a different tunnel section.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HARP UpdateReport 314 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 21 attended
SB
Councillor Susan BibbyCommittee Member, present
A(
Councillor Anthony (Tony) AustinCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPVice-Chair, apologies
MF
Councillor Mark FrenchCommittee Member, present
MG
Councillor Michael GravestonCommittee Member, present
MH
Councillor Mark HindleCommittee Member, apologies
GH
Councillor Gaynor HibbertCommittee Member, present
JH
Councillor Jonathan HillCommittee Member, present
KH
Councillor Kevin Horkin MBECommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
J(
Councillor James (Jim) RogersonCommittee Member, present

All 21 on the meeting page

On this subject at Ribble Valley

Search all
  1. HARP UpdateThis decision
  2. Applications - 3/2021/0660 and 3/2021/0661 - HARPApproved

More from Ribble Valley Planning and Development

All decisions
MeetingDecisionOutcome
27 Aug 2026 3/2025/0801 - Land to east of Salesbury View WilpshireRESOLVED THAT COMMITTEE: REFUSE PLANNING PERMISSION for the following reasons: 1. The proposed development would be o... Refused Open
27 Aug 2026 3/2022/0317 - Land at Higher Standen Farm and Part Littlemoor Farm ClitheroeRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): 1. Unless explicitly requir... Approved Open
27 Aug 2026 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): The development hereby perm... Approved Open
27 Aug 2026 3/2025/0997 - Land off Henthorn Road Clitheroe BB7 3BYRESOLVED THAT COMMITTEE: Application deferred to enable an alternative access directly off Henthorn Road to serve the... Deferred Open
27 Aug 2026 3/2026/0230 - Land to the south of Ribblesdale Primary School west and north of Higher Standen DriveRESOLVED THAT COMMITTEE: DEFER AND DELEGATE to the Director of Economic Development and Planning for approval subject... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies