Policy and Finance, Tuesday 11 November 2025 at 6.30pm

Ribble Valley Shared Prosperity and Jubilee Fund

Approved Finance 1 paper

AI summaryRibble Valley Policy and Finance Committee approves five Shared Prosperity and Jubilee Fund projects, lifts Dunsop Bridge grant to £100,000, and invites four more to apply.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDunsop Bridge grant increased to £100,000
Money£1,650,810 total fund£1,339,722 still unallocated before new approvals
What happens nextReopen EOI process with new criteriaNew EOI deadline 5 January 2026
Who it affectsCommunity groups and parish projectsAcross Ribble Valley borough

What was decided

The Committee confirmed an increase in the grant to Dunsop Bridge Jubilee Play Area Charitable Trust from £50,000 to £100,000, and approved the five full applications in section 3 of the report (West Bradford Village Hall, Ribchester Playing Field Trust, Dunsop Bridge, Thornley Community Space, and Primrose Community Nature Trust). Report 2.8, 2.9, 3.5, 3.9, 3.13, 3.18, 3.22

The Committee instructed the Director of Economic Development and Planning to invite four further projects to full application: Martholme Greenway Group, Whalley in Bloom, Longridge Environment Group flood resilience, and Longridge Men's Shed dust extraction, using up to £63,000. Report 4.3, P46

The Committee approved revised grant criteria and instructed that the Expression of Interest process be reopened, with all projects listed at Appendix 4 to be closed (except Ribchester Roman Museum) and applicants invited to submit a new EOI if they meet the new criteria. Report 5.3, 5.4, P50

Why

Dunsop Bridge Jubilee Play Area Charitable Trust requested additional funding to deliver the full £200,000 refurbishment in a single phase, citing value for money, reduced inflation risk, and earlier community benefits; the Working Group supported the increase to £100,000 on 29 September 2025. Report 2.8, 2.9, P10

The five section 3 projects were previously agreed in principle at the 16 September 2025 Committee and have now submitted full applications for final approval. Report 2.6, 2.7, P7

The new EOI criteria focus on community energy, community gardens and green spaces, heritage assets, community building energy upgrades, and play equipment, to ensure funded projects leave a lasting legacy across the borough. Report 5.3, P62

What happens next

Approved section 3 applicants will be issued offer letters; West Bradford Village Hall aims to complete by February 2026, Ribchester Playing Field Trust plans a September 2026 start, and Dunsop Bridge could begin installation in early 2026 and finish within 8 to 10 weeks. Report 3.5, 3.9, P10, 3.13

The Director will invite the four projects at paragraph 4.2 to submit full applications, and reopen the EOI process in November 2025 with a deadline of 5 January 2026 for new applications. Report 4.3, P46, P68

Recommendations on the new EOIs will be considered by the Shared Prosperity and Jubilee Fund Working Group and reported to the Policy and Finance Committee on 20 January 2026. Report P59

The money

  • £1,650,810 Total funding for the Shared Prosperity and Jubilee Fund grant scheme Report 2.3
  • £1,339,722 Funding not yet allocated to projects before new approvals Report 5.2
  • £100,000 Increased grant to Dunsop Bridge Jubilee Play Area Charitable Trust Report 2.9
  • £50,000 Original approved grant to Dunsop Bridge Jubilee Play Area Charitable Trust Report 2.6, P7
  • £10,000 Grant to West Bradford Village Hall (project cost £20,000) Report 3.2, 3.4, P17
  • £100,000 Grant to Ribchester Playing Field Trust (project cost £150,000) Report 3.6, 3.8, P23
  • £200,000 Total project cost of Dunsop Bridge refurbishment Report 3.12, P28
  • £56,088 Grant to Thornley Community Space Charity (100% of £56,088 project cost) Report 3.14, P33
  • £95,000 Grant to Primrose Community Nature Trust Limited (100% of £95,000 project cost) Report 3.19, 3.21, P40
  • up to £63,000 Total cost of the four new projects invited to full application Report 4.3, P46
  • £610,000 RVBC Shared Prosperity Fund Equivalent Scheme allocation 2025/26 Report 2.1
  • £1,000,000 Jubilee Scheme allocation 2025/26 Report 2.1
  • £40,810 Voluntary Organisation Grants 2025/26 added to the fund Report 2.3

Options considered

  • Chosen: Increase Dunsop Bridge grant to £100,000 for single-phase delivery. Working Group on 29 September supported the increase to deliver the full scheme in one phase, improving value for money and reducing inflation risk. Report 2.9, P10
  • Chosen: Approve West Bradford Village Hall, Ribchester Playing Field Trust, Dunsop Bridge, Thornley Community Space, and Primrose Community Nature Trust full applications. Five full applications submitted following September in-principle support; detailed in section 3. Report 3.5, 3.9, 3.13, 3.18, 3.22
  • Chosen: Invite Martholme Greenway Group, Whalley in Bloom, Longridge Environment Group, and Longridge Men's Shed to full application. Working Group recommendations of 23 October; total cost up to £63,000. Report 4.3, P46
  • Chosen: Reopen EOI process with revised grant criteria and close existing applications at Appendix 4 (except Ribchester Roman Museum). To ensure remaining £1,339,722 funds legacy projects such as community energy, green spaces, heritage, energy efficiency, and play equipment across the borough. Report 5.2, 5.3, 5.4, P50
  • Rejected: Support Longridge CLCGB minibus purchase (£25,000). Working Group did not recommend supporting this request. Report P44
  • Rejected: Support St. James Church kitchen refurbishment (£20,000). Working Group did not recommend supporting this grant request. Report P44
  • Rejected: Support St. Mary's Centre Community Hall refurbishment (£100,000). Working Group did not recommend supporting this request. Report P44
  • Rejected: Support Longridge Town Council Royal British Legion Club community hub (£200,000). Working Group had concerns about the risks associated with the project and did not recommend supporting it. Report P44
  • Rejected: Support Pendleton Parish Council bus stops and crossings scheme (£20,000). Pending Lancashire County Council position; not recommended at this stage. Report P44

Implications

  • Financial: The total grant scheme budget is £1,650,810, of which £1,339,722 remained unallocated before these approvals; grants are normally paid retrospectively, with upfront payment possible where certain criteria are met. Report 2.3, 5.2, P52
  • Legal: Legal have been consulted and their comments are incorporated; suitable agreements and assurances will be put in place for administering the scheme, and capital grants are subject to UK subsidy control legislation. Report P53, P66, P67
  • Equalities: Work on the report supports the council's aim of delivering a sustainable local economy to the benefit of all its community; applications are assessed for non-discrimination in decision-making. Report P54, P65
  • Climate: Thornley Community Space project will reduce the building's carbon footprint through solar PV, battery storage, a new heating system and replacement windows; new grant criteria prioritise community energy, heat pumps, solar, and reduced energy consumption. Report 3.15, 3.17, 5.3, P62
  • Risk: Resource risk: organisations may need upfront payment if they lack cash flow. The Working Group also flagged risks associated with the Longridge Royal British Legion community hub project, which was not supported. Report P52, P44
  • Other: The scheme fits the Council's Corporate Strategy (2019 to 2023) Ambitions 2 and 3: a strong and prosperous Ribble Valley and helping make people's lives safer and healthier. Report P52

Who and where

  • Dunsop Bridge Jubilee Play Area Charitable Trust Report 2.8, 2.9, 3.10, P10
  • West Bradford Village Hall Report 3.2, 3.4, P17
  • Ribchester Playing Field Trust Report 3.6, 3.8, P23
  • Thornley Community Space Charity Report 3.14, P33
  • Primrose Community Nature Trust Limited Report 3.19, 3.21, P40
  • Martholme Greenway Group Report 4.3
  • Whalley in Bloom Report 4.3
  • Longridge Environment Group Report 4.3
  • Longridge Men's Shed Report 4.3

Timeline

  • 4 March 2025: Full Council approved the 5-year Capital Programme including £610,000 Shared Prosperity Fund and £1,000,000 Jubilee Scheme for 2025/26 Report 2.1
  • April 2025: Grant scheme went live Report 2.4
  • 1st April 2025: Policy and Finance Committee agreed to merge the two schemes into the Ribble Valley Shared Prosperity Fund and add £40,810 from the Voluntary Organisation Grants budget, totalling £1,650,810 Report 2.2, 2.3, 2.4
  • 30th May 2025: Deadline for Expressions of Interest Report 2.5
  • 16th September 2025: Committee agreed in principle to support five schemes including £50,000 for Dunsop Bridge Report 2.6, P7
  • 29th September 2025: Working Group confirmed support for increasing Dunsop Bridge funding to £100,000 Report 2.9
  • 23rd October 2025: Working Group considered further schemes and made recommendations on additional projects Report P43, P44
  • November 2025: New Expression of Interest process to reopen Report P68
  • 11th November 2025: Policy and Finance Committee meeting deciding on full applications and revised criteria
  • 5th January 2026: Deadline for new Expressions of Interest Report P59
  • 20th January 2026: Next Policy and Finance Committee to consider Working Group recommendations on new EOIs Report P59
  • February 2026: West Bradford Village Hall project to complete subject to funding Report 3.5
  • Early 2026: Dunsop Bridge installation could commence and complete within 8 to 10 weeks, before end March 2026 Report P10
  • September 2026: Ribchester Playing Field Trust project start date to allow time to raise additional £38,000 Report 3.9

Plain English for the jargon

  • EOI: Expression of Interest, an initial application step before a full grant application
  • UKSPF: UK Shared Prosperity Fund, a separate government-backed funding stream reported elsewhere on the agenda
  • REPF: Rural England Prosperity Fund, a separate government funding stream
  • Capital grant: Grant for buildings, infrastructure or equipment with a life expectancy of at least two years and a purchase value of at least £1,000
  • Match funding: The applicant's own capital or funds from another source to cover the total project cost
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item429

Resolved

RESOLVED THAT COMMITTEE: 1. Confirmed an increase in the grant to Dunsop Bridge Jubilee Play Area Charitable Trust to £100,000. 2. Approved the projects set out within section 3 of the report. 3. Instructed the Director of Economic Development and Planning to invite the following projects to ... view the full minutes text for item 429.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Policy and Finance

Background

2.1Full Council, on 4 March 2025, approved the Council’s 5-year Capital Programme from 2025/26 to 2029/30. This included the following amounts in 2025/26 •RVBC ‘Shared Prosperity Fund’ Equivalent Scheme- £610,000 •Jubilee Scheme- £1,000,000

2.2The Budget Working Group recommended that these two schemes should be merged to develop a RVBC Shared Prosperity Fund with funding of £1,610,000 available.

2.3At Policy and Finance Committee on 1st April 2025 it was agreed that the remaining Voluntary Organisation Grants 2025/26 budget, of £40,810, should be allocated to the Ribble Valley Shared Prosperity Fund/ Jubilee Fund. As such the total funding for this grant scheme is £1,650,810.

2.4The criteria for this grant scheme was also agreed at Committee on 1st April and the grant scheme went live in April 2025 (Ribble Valley Shared Prosperity and Jubilee Fund (2025/26) – Ribble Valley Borough Council)

2.5Expressions of Interest into the fund were invited until 30th May 2025.

2.6Committee, on 16th September 2025, agreed to support the following schemes via the Shared Prosperity and Jubilee Fund Scheme Grant Amount

Thornley Community Space 56,088 Upgrade heating to a sustainable energy eco friendly system. West Bradford Village Hall 10,000 Enhancement of playground and exercise equipment Primrose Community Nature Trust Ltd 95,000 The creation of a third footpath access point close to the centre of Clitheroe. Ribchester Playing Field Trust 100,000 To replace tired and/or broken play equipment and safety matting on Ribchester Recreation Ground. Dunsop Bridge Jubilee Play Area Charitable Trust 50,000* Purchase and installation of new play equipment as part of the Dunsop Bridge Jubilee Play Area refurbishment project. Total project cost for the refurbishment of phase 1 is £140k TOTAL 311,088 *see further update below

2.7These schemes have now been invited submit full applications.

2.8In respect of the approved scheme at Dunsop Bridge following Committees resolution to support this project the applicant contacted the Director of Economic Development and Planning requesting additional funding for the following reasons:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ribble Valley Shared Prosperity and Jubilee FundReport 456 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 32 attended
SH
Councillor Simon HoreChair, present
SA
Councillor Stephen AtkinsonCommittee Member, apologies
SB
Councillor Susan BibbyVice-Chair, present
SC
Councillor Sophie CowmanCommittee Member, present
MG
Councillor Michael GravestonCommittee Member, present
JH
Councillor Jonathan HillCommittee Member, expected
MH
Councillor Mark HindleCommittee Member, present
SH
Councillor Stuart HirstCommittee Member, present
KH
Councillor Kevin Horkin MBECommittee Member, present
LJ
Councillor Lee JamesonCommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
RR
Councillor Rachael RayCommittee Member, present

All 32 on the meeting page

On this subject at Ribble Valley

Search all
  1. Ribble Valley Shared Prosperity and Jubilee FundThis decision
  2. Ribble Valley in BloomDecided
  3. Ribble Valley Shared Prosperity and Jubilee FundApproved
  4. Ribble Valley Shared Prosperity and Jubilee Fund (2025/26)Decided
  5. Ribble Valley in BloomDecided
  6. Jubilee Fund and Ribble Valley SPFApproved

More from Ribble Valley Policy and Finance

All decisions
MeetingDecisionOutcome
16 Jun 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: 1. Approved slippage of £1,756,430 on the main Policy and Finance Committee capital schemes ... Approved Open
16 Jun 2026 Returning Officers’ Scale of Fees 2026/27 – Borough and Parish ElectionsRESOLVED THAT COMMITTEE: Agreed the Returning Officers’ Scale of Fees for any Borough or Parish By Election in 2026/2... Agreed Open
16 Jun 2026 Government Consultation - High Value Council Tax SurchargeRESOLVED THAT COMMITTEE: 1. Approved the consultation response attached at Annex 1 subject to minor amendments as dis... Approved Open
16 Jun 2026 Town and Parish Council Traffic Management Plan Grant Scheme 2026-27RESOLVED THAT COMMITTEE: 1. Approved the grant scheme criteria and conditions as set out at paragraph 3.1 with the co... Approved Open
16 Jun 2026 Appointment to Working GroupsRESOLVED THAT COMMITTEE: 1. Approved the continuance of the following working groups under the remit of this committe... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies