3/2025/0775 - Clitheroe Castle Keep Castle Gate Clitheroe BB7 1BA

Deferred Planning 1 paper

AI summaryRibble Valley councillors defer Listed Building Consent for 12 LED lights on Clitheroe Castle Keep wall, pending Historic England's response. Approval delegated to the Director of Economic Development and Planning with four conditions covering bat boxes and lighting brightness.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredSubject to Historic England response and conditions
MoneyNot stated
What happens next21-day Historic England consultationNo objection or no response required
Who it affectsClitheroe Castle Keep and Conservation AreaGrade I listed, Scheduled Monument

What was decided

The application was deferred and delegated to the Director of Economic Development and Planning for approval, subject to confirmation that Historic England have no issues or no response within the 21-day consultation period. Report P113

Four conditions were imposed covering the three-year commencement period, plans compliance, bat box provision, and detailed light fixing and brightness specifications.

Why

The Castle is a Grade I Designated Heritage Asset and a Scheduled Monument within the Clitheroe Conservation Area, requiring special regard to preserving or enhancing its significance and setting under Section 16 of the Planning (Listed Buildings and Conservation Areas) Act 1990 and NPPF paragraphs 212 to 221. Report 1.1, P45, P61, P62, P63

Officers found no significant measurable harm to the heritage assets, conservation area, or residential amenity, noting the proposed downlighting would complement existing evening illumination of the castle.

A bat survey found no bats emerging from the building, with low to moderate roost potential; a compensatory bat box is proposed as biodiversity enhancement. Report P107, P108, P109

What happens next

Historic England's consultation response is awaited and must be received or the 21-day period must expire without objection before the Director of Economic Development and Planning can grant approval. Report P11, P113

Before work starts, details of the proposed bat box and its location must be submitted to and agreed in writing by the Local Planning Authority.

Before work starts, details of the light fixings and level of brightness must be submitted to and agreed in writing by the Local Planning Authority.

Options considered

  • Chosen: Defer and delegate to Director of Economic Development and Planning for approval subject to Historic England consultation and conditions. No significant measurable harm to heritage assets, conservation area, or residential amenity identified; bat survey showed no emerging bats Report P113, P107
  • Rejected: Refuse Listed Building Consent. Officers concluded the proposal does not warrant refusal, as it preserves and enhances the significance of the heritage assets subject to conditions Report 6.1, P111

Implications

  • Legal: Listed Building Consent granted under the Planning (Listed Buildings and Conservation Areas) Act 1990 (as amended by s.58B of the Levelling-up and Regeneration Act 2023) imposes a statutory duty to preserve or enhance the special character of the Grade I heritage asset. Report P44, P45, P81, P82
  • Equalities: Clitheroe Town Council raised no objection and no public representations were received on the application. Report P9, P13
  • Environment and climate: The scheme includes a compensatory bat box (one Greenwood Eco Habitats two crevice box) to be installed before works commence as biodiversity enhancement. Report P109
  • Risk: Final approval depends on Historic England's response during the 21-day consultation period; any objection from Historic England could prevent delegated approval. Report P11, P113

Who and where

  • Ribble Valley Borough Council (the applicant and occupier of premises within the castle grounds) Report 2.2, P36
  • Clitheroe Town Council (consultee, raised no objection) Report P9
  • Historic England (consultee, response awaited) Report P10, P11
  • Visitors to Clitheroe Castle Keep and Clitheroe Conservation Area Report 1.1, P75

Timeline

  • 28th August 2022: Preliminary bat roost assessment survey carried out on the Keep Report P107
  • 28th August and 10th September 2022: Two emergence bat surveys conducted; no bats recorded emerging Report P107
  • 4th June 2025: Follow-up emergence bat survey using thermal cameras; no bats recorded emerging Report P107
  • 27 November 2025: Application considered by Planning and Development Committee and deferred and delegated for approval Report P3

Plain English for the jargon

  • Listed Building Consent: Permission required from the local planning authority to carry out works that affect the special character of a listed building
  • Scheduled Monument: A site of national importance protected under the Ancient Monuments and Archaeological Areas Act, in this case the Clitheroe Castle Medieval Enclosure
  • Grade I Designated Heritage Asset: A building of exceptional interest, the highest listing grade; only about 2.5% of listed buildings are Grade I
  • Defer and delegate: Committee defers the decision and gives authority to an officer to grant approval once specified requirements (such as consultee responses) are satisfied
  • Bat box: An artificial roost structure installed to provide habitat for bats, used here as compensatory biodiversity enhancement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item491b

Resolved

RESOLVED THAT COMMITTEE: That the application be DEFERRED AND DELEGATED to the Director of Economic Development and Planning for approval following confirmation that Historic England have no issues with the scheme or no response being received by them within the 21-day consultation period, subject to the imposition of the following condition(s): 1. The development must be begun not later than the expiration of three years beginning with the date of this permission. REASON: Required to be imposed pursuant to Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990. 2. Unless explicitly required by condition within this consent, the development hereby permitted shall be carried out in complete accordance with the proposals as detailed on drawings: Location Plan Castle Keep Lighting: Sheet 1 (Lighting Sections) Castle Keep Lighting: Sheet 1 (Lighting Layout Drawing) REASON: For the avoidance of doubt and to clarify which plans are relevant to the Listed Building Consent hereby approved. 3. Prior to the commencement of development, details of the proposed ‘bat box’ provisions and their precise locations shall have been submitted to and agreed in writing by the Local Planning Authority. For the avoidance of doubt the agreed provisions shall be installed and made available prior to the commencement of works and be retained thereafter. REASON: To ensure the proposal contributes towards ecological and biodiversity enhancement. 4. Prior to the commencement of development, details of the light fixings and the level of brightness shall have been submitted to and agreed in writing by the Local Planning Authority. The development shall be installed in accordance with the approved lighting scheme. REASON: To ensure the proposal protects and enhances the designated heritage assets.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Planning and Development

RECOMMENDATION FOR PLANNING AND DEVELOPMENT COMMITTEE

DEF

DATE: 27 NOVEMBER 2025 REF: SK CHECKED BY: LH

APPLICATION REF: 3/2025/0775

GRID REF: SD 374217 441639

DEVELOPMENT DESCRIPTION:

LISTED BUILDING CONSENT FOR THE PROPOSED INSTALLATION OF 12 LED LIGHTS FIXED ON BRACKETS ATTACHED TO THE EXISTING FENCE POSTS OF THE PERIMETER OF THE CURTAIN WALL OF CLITHEROE CASTLE KEEP. CLITHEROE CASTLE KEEP, CASTLE GATE, CLITHEROE BB7 1BA CONSULTEE RESPONSES/ REPRESENTATIONS MADE:

PARISH COUNCIL:

Clitheroe Town Council have raised no objection to the proposal.

HISTORIC ENGLAND:

Response Awaited

ADDITIONAL REPRESENTATIONS:

No representations received in respect of the application.

1. Site Description and Surrounding Area

1.1The application relates to the Clitheroe Castle Keep wall located on Castle Gate Clitheroe. The Castle is a Grade I Designated Heritage Asset, with the Clitheroe Castle; Medieval Enclosure also being a Scheduled Monument. The application site lies within the defined settlement of Clitheroe, also being located within the designated Clitheroe Conservation Area.

2. Proposed Development for which consent is sought

2.1The application seeks consent for the installation of 12 LED lights to be mounted around the perimeter of the Castle Keep perimeter wall. It is proposed that the lights will be fixed to the existing handrail fence post bases that are situated around the perimeter of the walkway area atop the existing Keep Wall. As such the fixings will not benefit from any direct interface with the existing historic fabric of the Keep Wall.

2.2The light fixtures will be clamped to the existing balustrade bases and project outwards providing a down lighting effect to the existing Castle keep walling. This application is brought before Planning and Development Committee as the applicant is Ribble Valley Borough Council.

3. Relevant Planning History

3/2023/0681: Listed Building Consent for removal of existing roof and replacement with new prefabricated trussed rafters and Welsh blue slates. New cast iron rainwater goods and new electrical wiring and fittings. (Approved)

3/2023/0680: Planning permission for removal of existing roof and replacement with new prefabricated trussed rafters and Welsh blue slates. New cast iron rainwater goods and new electrical wiring and fittings. (Approved)

3/2023/0068:Listed Building Consent to install a plaque in the rose garden within the grounds of Clitheroe Castle. (Withdrawn)

3/2021/1290:Replace existing traditional mortar ridge system with a dry venticated ridge system to the existing slate pitched roof areas. (Approved) 3/2021/0699:Dismantle parapet to level of copper/lead tray. Make adjustments/replace lead/copper trays and rebuild parapet using the retained stone and matching mortar. (Approved)

3/2020/0873:Erection of two sets of galvanised and powder coated railings to match existing railings adjacent to dawn redwood tree. (Approved)

4. Relevant Policies

Ribble Valley Core Strategy

Key Statement DS1: Development Strategy Key Statement DS2: Sustainable Development Key Statement EN4: Biodiversity and Geodiversity Key Statement EN5: Heritage Assets

Policy DMG1: General Considerations Policy DME1: Protecting Trees & Woodland Policy DME2: Landscape & Townscape Protection Policy DME3: Site and Species Protection and Conservation Policy DME4: Protecting Heritage Assets

Planning (Listed Buildings and Conservation Areas) Act National Planning Policy Framework (NPPF)

5. Assessment of Proposed Development

5.1Impact upon Listed Building(s) and Setting:

5.1.1 The application relates to the Clitheroe Castle Keep wall located on Castle Gate Clitheroe. The Castle is a Grade I Designated Heritage Asset, with the Clitheroe Castle; Medieval Enclosure also being a Scheduled Monument, with the respective listing reading as follows:

5.1.2 Clitheroe Castle (List Entry: 1071553)

CASTLE GATE 1. 5295 (South-West Side) Clitheroe Castle SD 7441 1/2 19.5.50. GV

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3/2025/0775: Clitheroe Castle Keep Castle Gate Clitheroe BB7 1BAReport 408 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 22 attended
A(
Councillor Anthony (Tony) AustinCommittee Member, present
SB
Councillor Susan BibbyCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPVice-Chair, present
MF
Councillor Mark FrenchCommittee Member, present
MG
Councillor Michael GravestonCommittee Member, present
MH
Councillor Mark HindleCommittee Member, apologies
GH
Councillor Gaynor HibbertCommittee Member, present
JH
Councillor Jonathan HillCommittee Member, present
KH
Councillor Kevin Horkin MBECommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
J(
Councillor James (Jim) RogersonCommittee Member, present

All 22 on the meeting page

On this subject at Ribble Valley

Search all
  1. 3/2025/0775 - Clitheroe Castle Keep Castle Gate Clitheroe BB7 1BAThis decision
  2. 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZApproved
  3. Clitheroe Castle BandstandAgreed
  4. Clitheroe Castle Grounds Improvement ProgrammeApproved
  5. 3/2024/0318 - 29 Castle View Clitheroe BB7 2DTRefused
  6. 3/2023/0680 - Parks Store Clitheroe Castle Castle Gate Clitheroe BB7 1AZApproved

More from Ribble Valley Planning and Development

All decisions
MeetingDecisionOutcome
27 Aug 2026 3/2025/0801 - Land to east of Salesbury View WilpshireRESOLVED THAT COMMITTEE: REFUSE PLANNING PERMISSION for the following reasons: 1. The proposed development would be o... Refused Open
27 Aug 2026 3/2022/0317 - Land at Higher Standen Farm and Part Littlemoor Farm ClitheroeRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): 1. Unless explicitly requir... Approved Open
27 Aug 2026 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): The development hereby perm... Approved Open
27 Aug 2026 3/2025/0997 - Land off Henthorn Road Clitheroe BB7 3BYRESOLVED THAT COMMITTEE: Application deferred to enable an alternative access directly off Henthorn Road to serve the... Deferred Open
27 Aug 2026 3/2026/0230 - Land to the south of Ribblesdale Primary School west and north of Higher Standen DriveRESOLVED THAT COMMITTEE: DEFER AND DELEGATE to the Director of Economic Development and Planning for approval subject... Deferred Open