Ribble Valley Borough Council
Planning and Development, Thursday 27 November 2025 at 6.30pm

Longridge Loop

Decided Planning 1 paper

AI summaryRibble Valley Planning and Development Committee authorised a £23,375 payment to Longridge Town Council for the Longridge Loop project, to be released within 28 days of works being completed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPassed to Longridge Town Council for Longridge Loop items
Money£23,375Section 106 contribution from Preston Road development
What happens nextPay within 28 days of completionTown Council must complete the specified works first
Who it affectsLongridge Town Council and loop usersFunds benches, planters, tables, finger posts, interpretation boards

What was decided

The Committee authorised payment of £23,375 to Longridge Town Council for the items set out in paragraph 3.2, within 28 days of completion of the works. Report 5.1

Why

Section 106 contributions have been collected for the Longridge Loop and Longridge Town Council has confirmed how it intends to spend the money on specific items. Report 2.1, 2.2, 3.1, 3.2

The remaining Preston Road contribution must be committed by 18th March 2026, making timely authorisation necessary. Report 3.1

What happens next

Longridge Town Council will deliver the works identified in the plan and the Council will release £23,375 within 28 days of completion. Report 5.1, 3.2

As contracting authority, the Town Council must ensure its procurement rules are followed. Report P10

The money

  • £15,000 S106 contribution from Land East of Chipping Lane (3/2014/0764) Report P3
  • £14,577 Already spent from Chipping Lane contribution on Longridge Loop Report P3
  • £423 Remainder of Chipping Lane contribution Report P3
  • £30,000 S106 contribution from Land West of Preston Road (3/2016/0974) Report P3
  • £6,604 Already spent from Preston Road contribution on Longridge Loop Report P3
  • £23,396 Remainder of Preston Road contribution to spend on Longridge Loop Report P3, 3.1
  • £3,000 S106 contribution from Spout Farm, Longridge (3/2020/0309), none spent Report P3
  • £48,000 Total Longridge Loop S106 contributions secured Report P3
  • £21,181 Total amount already spent on Longridge Loop Report P3
  • £26,819 Total remaining Longridge Loop monies Report P3
  • £23,375 Payment authorised to Longridge Town Council for items in paragraph 3.2 Report 5.1

Options considered

  • Chosen: Authorise payment of £23,375 to Longridge Town Council for the listed items. Town Council confirmed intended use and S106 deadline of 18th March 2026 applies Report 3.1, 3.2, 5.1

Implications

  • Financial: Commuted sums have already been received by the Council and are available to fund the works. Report P10
  • Legal: The project accords with the stipulations of the S106 legal agreements. Report P11
  • Other: Provision of the Longridge Loop is a benefit to the town and reflects the purpose of contributions secured from new residential developments. Report P13
  • Risk: The Town Council, as contracting authority, must follow its own procurement rules when delivering the works. Report P10

Who and where

  • Longridge Town Council (recipient of the funding and contracting authority for the works) Report 3.1, P10
  • Residents and visitors who use the Longridge Loop route Report P13
  • Occupants of the three contributing developments (Land East of Chipping Lane, Land West of Preston Road, Spout Farm) Report P3

Timeline

  • 18th March 2026: Deadline by which the remaining Preston Road contribution must be committed Report 3.1
  • Within 28 days of completion of the works: Payment of £23,375 to be released to Longridge Town Council Report 5.1

Plain English for the jargon

  • Section 106 Agreement: A planning obligation attached to a planning permission under which a developer contributes money or works
  • Commuted sum: Money paid by a developer in lieu of carrying out works directly
  • Passport funding: Passing collected S106 money to a town or parish council to deliver agreed projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item494

Resolved

RESOLVED THAT COMMITTEE: Authorise payment of £23,375 to Longridge Town Council, for the items set out within paragraph 3.2 of the report, within 28 days of the completion of the works. Councillor J Rogerson returned to the meeting.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Planning and Development

Background

2.1There are various Section 106 Agreements which have secured planning obligations to Longridge Loop. Committee may recall that authority have been sought previously to passport some of this funding to Longridge Town Council.

2.2The current position in terms of contributions is as follows:

Application Address of Longridge Spent Remainder to No. Site Loop S106 Longridge Spend on Total Loop Monies Longridge Contribution Loop 3/2014/0764 Land East of £15,000 £14,577 £423 Chipping Lane 3/2016/0974 Land West of £30,000 £6,604 £23,396 Preston Road 3/2020/0309 Spout Farm, £3,000 None £3,000 Longridge TOTAL £48,000 £21,181 £26,819

3. PROPOSAL

3.1The Town Council have been contacted in respect of these contributions to establish how they intend to use the contributions for the Longridge Loop project. The remaining £23,396 secured from the Preston Road development needs to be committed by 18th March 2026.

3.2The Town Council have confirmed that they intend to use the contributions for the following items detailed on the attached plan

• 10 x Baxenden Bench 1.5m • 6 x Planter • 2 x 8-Seater Picnic Table one side • 6 x Seated planters • 33 finger posts • 7x Mendip Outdoor Freestanding Angled Interpretation Board

1 4. RISK ASSESSMENT

4.1The approval of this report may have the following implications:

• Resources – The commuted sums have been received by the Council and are available to facilitate the works proposed. As the contracting Authority the Town Council will need to ensure they accord with their procurement rules.

• Technical, Environmental and Legal - The project would accord with the stipulations of the legal agreements

• Political - N/A

• Reputation - The provision of Longridge Loop is a benefit to the Town and accords with the purpose of securing such contributions as part of new residential developments.

• Equality and Diversity - N/A

5. RECOMMENDED THAT Committee

5.1Authorise payment of £23,375 to Longridge Town Council, for the items set out within paragraph 3.2, within 28 days of the completion of the works.

NICOLA HOPKINS DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING

2 3

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Longridge LoopReport 350 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 22 attended
A(
Councillor Anthony (Tony) AustinCommittee Member, present
SB
Councillor Susan BibbyCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPVice-Chair, present
MF
Councillor Mark FrenchCommittee Member, present
MG
Councillor Michael GravestonCommittee Member, present
MH
Councillor Mark HindleCommittee Member, apologies
GH
Councillor Gaynor HibbertCommittee Member, present
JH
Councillor Jonathan HillCommittee Member, present
KH
Councillor Kevin Horkin MBECommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
J(
Councillor James (Jim) RogersonCommittee Member, present

All 22 on the meeting page

On this subject at Ribble Valley

Search all
  1. Longridge LoopThis decision
  2. Longridge LoopDecided
  3. Longridge LoopApproved
  4. Longridge LoopDecided

More from Ribble Valley Planning and Development

All decisions
MeetingDecisionOutcome
27 Aug 2026 3/2025/0801 - Land to east of Salesbury View WilpshireRESOLVED THAT COMMITTEE: REFUSE PLANNING PERMISSION for the following reasons: 1. The proposed development would be o... Refused Open
27 Aug 2026 3/2022/0317 - Land at Higher Standen Farm and Part Littlemoor Farm ClitheroeRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): 1. Unless explicitly requir... Approved Open
27 Aug 2026 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): The development hereby perm... Approved Open
27 Aug 2026 3/2025/0997 - Land off Henthorn Road Clitheroe BB7 3BYRESOLVED THAT COMMITTEE: Application deferred to enable an alternative access directly off Henthorn Road to serve the... Deferred Open
27 Aug 2026 3/2026/0230 - Land to the south of Ribblesdale Primary School west and north of Higher Standen DriveRESOLVED THAT COMMITTEE: DEFER AND DELEGATE to the Director of Economic Development and Planning for approval subject... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies