Resolved
RESOLVED THAT COMMITTEE: Recommended to Council the Capital Programme for 2026/27 to 2029/30 as set out in the Annex to the report.
AI summaryRibblesdale Pool refurbishment, a Clitheroe cemetery extension, and Joiners Arms renovation are included in a £16,961,680 capital programme for 2026/27 to 2029/30, recommended to full council on 3 March 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED THAT COMMITTEE: Recommended to Council the Capital Programme for 2026/27 to 2029/30 as set out in the Annex to the report.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO SPECIAL POLICY AND FINANCE COMMITTEE
meeting date: 10 FEBRUARY 2026 title: FOUR-YEAR CAPITAL PROGRAMME 2026/27 – 2029/30 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: LAWSON ODDIE
UPDATED FOLLOWING BUDGET WORKING GROUP MEETING 10 FEBRUARY 2026 1 PURPOSE 1.1 To seek approval from members for the proposed four-year capital programme covering the period 2026/27 to 2029/30. 1.2 Should committee agree with the proposals in this report, members are asked to recommend a capital programme to Full Council on 3 March 2026. 2 STARTING POINT 2.1 At the September meeting of Policy and Finance Committee, service committees were advised that: • no bids should be invited for year 5 of a new capital programme. • the existing programme should be reviewed for any schemes that could be reprofiled to a later year. 2.2 The summary below shows the starting point for the review that has taken place of the remaining four years in the existing capital programme. The table shows the existing capital programme for the period, as approved last year. 2026/27 2027/28 2028/29 2029/30 TOTAL £ £ £ £ £ Schemes:
Community Services 1,592,150 715,000 1,210,300 519,730 4,037,180
Economic Development 0 0 0 0 0
Health and Housing 443,000 443,000 493,000 443,000 1,822,000 Planning and 0 0 0 0 0 Development Policy and Finance 43,600 69,760 0 277,200 390,560
Total Schemes 2,078,750 1,227,760 1,703,300 1,239,930 6,249,740
Financing
Grants and Contributions -393,000 -393,000 -429,000 -393,000 -1,608,000
Earmarked Reserves -1,300,470 -312,860 -1,274,300 -846,930 -3,734,560
Capital Receipts -385,280 -521,900 0 0 -907,180 Total Approved -2,078,750 -1,227,760 -1,703,300 -1,239,930 -6,249,740 Resources Excess Schemes or 0 0 0 0 0 Shortfall in Resources Four-Year Capital Programme (003) 1 of 13 2.3 As can be seen from the table at 2.2, the existing schemes in the remaining four years of the capital programme are fully financed. 2.4 The stages that have been considered to arrive at the final proposed four-year capital programme are: • Adjusting for amendments that have been approved during 2025/26 • Review of the existing capital programme by Heads of Service • Impact of proposals from the Overall Revised Capital Programme 2025/26 report 3 ADJUSTMENTS THAT HAVE BEEN APPROVED DURING 2025/26 3.1 During this year, an amendment was agreed to the refuse collection vehicle purchase scheme in 2026/27 following a recent procurement exercise that included this particular vehicle. It was agreed that this budget be increased by £8,970 based on the tendered price. 3.2 There have also been a number of other movements during the current financial year due to schemes being moved forward to the 2025/26 financial year. 3.3 The impact of the additional budget and the movement of two scheme to 2025/26 is shown in the table below: 2026/27 2027/28 2028/29 2029/30 TOTAL £ £ £ £ £ Total Approved 2,078,750 1,227,760 1,703,300 1,239,930 6,249,740 Schemes Schemes brought forward to 2025/26 Chatburn Public Conveniences Refurbishment -11,000 -11,000 (Community Services Committee) Replacement of Council Offices Fire Alarm System -69,760 -69,760 (Policy and Finance Committee) Increased Scheme Cost following Procurement Replacement Refuse Collection Vehicle 8,970 8,970 (Community Services Committee) Total Latest Position 2,076,720 1,158,000 1,703,300 1,239,930 6,177,950
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Four Year Capital Programme 2026/27 to 2029/30Report | 431 KB | DownloadRead as text |
Follow Policy and Finance at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: 1. Approved slippage of £1,756,430 on the main Policy and Finance Committee capital schemes ... | Approved | Open |
| 16 Jun 2026 | Returning Officers’ Scale of Fees 2026/27 – Borough and Parish ElectionsRESOLVED THAT COMMITTEE: Agreed the Returning Officers’ Scale of Fees for any Borough or Parish By Election in 2026/2... | Agreed | Open |
| 16 Jun 2026 | Government Consultation - High Value Council Tax SurchargeRESOLVED THAT COMMITTEE: 1. Approved the consultation response attached at Annex 1 subject to minor amendments as dis... | Approved | Open |
| 16 Jun 2026 | Town and Parish Council Traffic Management Plan Grant Scheme 2026-27RESOLVED THAT COMMITTEE: 1. Approved the grant scheme criteria and conditions as set out at paragraph 3.1 with the co... | Approved | Open |
| 16 Jun 2026 | Appointment to Working GroupsRESOLVED THAT COMMITTEE: 1. Approved the continuance of the following working groups under the remit of this committe... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.