Resolved
RESOLVED That the report be noted.
Corporate Overview and Scrutiny Committee noted this item on Monday 19 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted.
1.1To inform Cabinet and Corporate Overview and Scrutiny Committee of the Council’s proposed Capital Programme for 2019/20 to 2021/22.
1.2The proposed Capital Programme 2019/20 to 2021/22 contains details of schemes for the following years:
2019/20 budget of £80.940m 2020/21 budget of £54.745m 2021/22 budget of £26.365m
1.3The Capital Programme is funded from a combination of Capital Receipts, Prudential Borrowing, Invest to Save, Government Grants and Contributions, and Revenue Contributions to Capital Outlay.
1.4Some of the assumed external funding included in the programme is still subject to clarification from Government and in some cases may involve bids for funds. It is therefore recommended that all approvals are subject to confirmation of funding allocations.
2.1That the 2019/20 (£80.940m) Capital Programme and provisional programmes for 2020/21 and 2021/22, be approved for the purposes of public consultation.
2.2Cabinet to consider the proposal to delegate approval to spend the £5m Corporate Investment scheme to the Chief Finance Officer in consultation with Leader of the Council. Reason for Recommendation
3.1The provisional 2019/20 to 2021/22 Capital Programme is presented to Cabinet for consultation as part of the budget setting process.
3.2The delegation of spend is the preferred option to allow schemes to progress as early as possible.
Key Points for Consideration
4.1The Capital Programme for 2019/20 to 2021/22 takes into consideration the priorities of the Council and the resources available. The approach for setting the 2019/20 capital budget has followed the steps below:
• Initial budget as provisionally approved at Budget Council on 28th February 2018. • Review of 2018/19 and 2019/20 schemes – Finance Service has worked with services to review 2018/19 and 2019/20 schemes taking into account spend to date and previous re-phasing of budget on the schemes. • Consideration of new schemes • Member Review Session with Leader, Deputy Leader and Assistant Finance Portfolio Holder.
4.2The result of the above steps is the proposed Capital Programme for 2019/20, and provisional Capital Programmes for 2020/21 and 2021/22 for consultation, detailed in Appendices 1 and 2.
4.3When a scheme is approved and the proposed spend is profiled across financial years, the scheme funding will be approved across these financial years and will therefore be considered as a priority in future years. Any reduction in the funding of these schemes will only be considered where contracts have not been entered into.
4.4Schemes totalling £80.9m have been proposed to be included in the 2019/20 Capital Programme. Table A below shows the total proposed Capital expenditure by service for 2019/20 to 2021/22, and how the expenditure is proposed to be funded.
4.5The Capital budget has been created in line with the Council’s priorities: Place Plan – aligning capital investment to support the borough’s economic growth potential and continue to regenerate our town centres. Corporate Plan – ensuring the borough maintains its high standard of quality building and public space. Asset Strategy – aiming to hold fewer but more efficient assets, realising maximum value from the estate whilst safeguarding its staff, customers and other building users. Table A – Summary of Capital programme
2019/20 2020/21 2021/22 Directorate £'000 £'000 £'000 Adult Care 2,440 2,440 2,440 Children's Services 12,508 20,526 7,516 Corporate 5,000 0 0 Economy 39,970 18,714 7,970 Neighbourhoods 21,022 12,389 8,439 Public Health 0 676 0 Total requirement 80,940 54,745 26,365
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2019/20 TO 2021/22Report | 330 KB | DownloadRead as text |
Follow Corporate Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | People Strategy Progress 2026Resolved – 1. That progress made against the People Strategy 2024-2026 be noted. 2. That the implementation of the re... | Noted | Open |
| 7 Sep 2026 | Finance Update 2026/27 Quarter 1Resolved – 1. That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June... | Noted | Open |
| 7 Sep 2026 | Children’s Services Q1, 2026/27 Revenue Monitoring UpdateResolved – 1. That the Children’s Services forecasted financial position for 2026/27 at Quarter 1 and related service... | Noted | Open |
| 7 Sep 2026 | Notice of Key Decisions and Private ItemsResolved - That the Notice of Key Decisions and Private Items be noted | Noted | Open |
| 7 Sep 2026 | Work Programme 2026-27 and Action Tracker 2026-27It was agreed that a report on Digital, Data and Technology be submitted to the Committee meeting scheduled for 19 Oc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.