That the future capital allocations as detailed below be noted: · Basic Need (New School Places 2019/20) -£9,987,191 (the above allocation was first reported to Cabinet in March 2018); · Basic Need (New School Places 2020/21) - £18,005,738 (pending DfE notification of final allocation); · School Condition Allocation (indicative figure for 2019/20) - £1,830,000; · Additional 2018-19 Devolved Formula Capital (DFC) - £913,548 · Devolved Formula Capital (DFC) - £480,000 (indicative figure for 2019/20); 2. That the capital receipts as detailed below be noted: · Land receipt from the sale of the former Balderstone HS - £1,268,000; · Building Schools for the Future underspend - £764,000.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
2. Members are asked to consider the report and to:
Note the future capital allocations as follows: Basic Need (New School Places 2019/20) £9,987,191 (the above allocation was first reported to Cabinet in March 2018) Basic Need (New School Places 2020/21) £18,005,738 (pending DfE notification of final allocation) School Condition Allocation (indicative figure for 2019/20) £1,830,000 Additional 2018-19 Devolved Formula Capital (DFC) £913,548 Devolved Formula Capital (DFC) £480,000 (indicative figure for 2019/20) The following capital receipts: Land receipt from the sale of the former Balderstone HS £1,268,000 Building Schools for the Future underspend £764,000
And to
ii) Approve expenditure on the proposed final programmes detailed within this report (Appendix A), for invitations to tender to be issued and accepted and for the supporting contracts, PFI deeds of variation (where necessary) and any incidental and ancillary documentation, to be signed in order to deliver the development schemes outlined in the appendices, in accordance with Financial Regulations: Basic Need Programme of £30,237,000 as set out in Appendix A
Capital Programme of £2,066,000 as set out in Appendix A Reason for Recommendation
3. Background 3.1 The Authority has received confirmation of allocations for Basic Need for a further year (2019/20), and for other school capital allocations this will be for one year only. Demand on, and proposals for, extra school places previously reported to Cabinet and most recently updated on 26th February 2019, will be followed by further phases as identified. Repairs to the school estate have considered all commitments and urgent demands before making recommendations to address the most significant issues, in conjunction with continued DFC allocations to schools.
3.2As well as on-going support for the current phases of capital works already committed, we are proposing a new programme of works to address major condition needs based on Asset Management information, recently commissioned and prioritised full building condition survey information and priority place planning demands in order to ensure that we satisfy the LA’s statutory obligations for the provision of school places and continued education. Our full recommendations for inclusion in this year’s capital programme are outlined in Appendix A, including costs estimated by the Council’s Property Services Team.
3.3It is proposed that the Buildings Maintenance revenue budget will be used, as in previous years, to support programme development costs, emergency/unplanned repairs and ongoing obligations related to the inspection of the schools building stock.
3.4It is further proposed that the sums received from the sale of the former Balderstone High School site and the unspent Building Schools for the Future funding will be used to support the provision of additional school places and capital projects at those schools which have already provided them, respectively. The original intention for the use of these funds was to support redevelopment of the secondary school estate and was agreed as part of the overall BSF strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.