That the following future capital allocations be noted: · School Condition Allocations £1,808,000 - (indicative figure for receipt in each of years 2021/22 and 2022/23); · Devolved Formula Capital (DFC) £480,000 - (indicative figure for receipt in each of years 2021/22 and 2022/23); · Basic Need Allocations £4,749,871 - ( DfE confirmed figure for 2020/21); 2. That approval be given to the expenditure on the proposed final programmes as detailed within the report (Appendix A), for invitations to tender to be issued and accepted and for the supporting contracts, PFI deeds of variation (where necessary) and any incidental and ancillary documentation, to be signed in order to deliver the development schemes outlined in the appendices, in accordance with Financial Regulations: · Basic Need Programme of £22,941,817 as set out in Appendix A; · Capital Programme of £3,527,500 as set out in Appendix A; 3. That the Director of Children’s Services be authorised to invite and evaluate tenders for the projects described in the report and enter into the appropriate contracts and incidental and ancillary documentation in consultation with the relevant Portfolio Holder and Assistant Director Legal Governance & Workforce, as per the Council Constitution; 4. That the Council’s Section 151 officer be authorised to allocate and vire funding to Children’s Services to support the programme when it is received.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1. The report seeks approval for proposed expenditure on various schemes in accordance with the Council’s Financial Regulations. These regulations provide that Cabinet approval should be obtained before new expenditure can be incurred. This report requests approval and tender acceptance, where necessary, for the outlined and reserve schemes proposed, contingency and other specified budgets.
Recommendation
2. Members are asked to consider the report and to:
Note the future capital allocations as follows: School Condition Allocations £1,808,000 (indicative figure for receipt in each of years 2021/22 and 2022/23) Devolved Formula Capital (DFC) £480,000 (indicative figure for receipt in each of years 2021/22 and 2022/23) Basic Need Allocations £4,749,871 (DfE confirmed figure for 2020/21)
And to
ii) Approve expenditure on the proposed final programmes detailed within this report (Appendix A), for invitations to tender to be issued and accepted and for the supporting contracts, PFI deeds of variation (where necessary) and any incidental and ancillary documentation, to be signed in order to deliver the development schemes outlined in the appendices, in accordance with Financial Regulations:
Basic Need Programme of £22,941,817 as set out in Appendix A
Capital Programme of £3,527,500 as set out in Appendix A
iii) Authorises, subject to the approval of recommendation 1, the Director for Children’s Services to invite and evaluate tenders for the projects described in this report and enter into the appropriate contracts and incidental and ancillary documentation in consultation with the Portfolio Holder and Assistant Director Legal Governance & Workforce, as per the Council’s Constitution.
iv) Authorises the Council’s Section 151 officer to allocate and vire funding to Children’s Services to support the programme when it is received.
Reason for recommendation
3. Background 3.1 The Authority has received confirmation of allocations for Basic Need for 2020/21, this is less than in previous years to reflect the DFE’s provision of the new Secondary Free Schools, rather than the LA. Demand on, and proposals for, extra school places previously reported to Cabinet on 29th September 2020, will be followed by further phases as identified. Repairs to the school estate have considered all commitments and urgent demands before making recommendations to address the most significant issues, in conjunction with continued DFC allocations to schools.
3.2As well as on-going support for the current phases of capital works already committed, we are proposing a new programme of works to address major condition needs based on Asset Management information, recently commissioned and prioritised full building condition survey information and priority place planning demands in order to ensure that we satisfy the LA’s statutory obligations for the provision of school places and continued education. Our full recommendations for inclusion in this year’s capital programme are outlined in Appendix A, including costs estimated by the Council’s Property Services Team.
3.3It is proposed that the Buildings Maintenance revenue budget will be used, as in previous years, to support programme development costs, emergency/unplanned repairs and ongoing obligations related to the inspection of the schools building stock.
School Capital Programme 3.4 The School Condition Allocation grant covers both primary and secondary schools and has been historically weighted by the Department for Education (DfE) in favour of those schools which have not received new build/refurbishment investment. It is necessary that the allocation is targeted largely at primary schools given the investment in the remaining LA maintained secondary schools through the Building Schools for the Future programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.