Resolved 1. That the future capital allocations as follows be noted: School Condition Allocations £1,800,000 ( indicative figure for receipt in each of years 2023/24 and 2024/25) Additional DfE School Condition Allocation for 2022/23 £920,435 Devolved Formula Capital (DFC) £480,000 (indicative figure for receipt in each of years 2023/24 and 2024/25) 2. To approve the expenditure on the proposed programmes detailed within Appendix A of the report, for invitations to tender to be issued and accepted and for the supporting contracts, PFI deeds of variation (where necessary) and any incidental and ancillary documentation, to be signed in order to deliver the development schemes outlined in the appendices, in accordance with Financial Regulations: · Basic Need Programme of £25,056,008 as set out in Appendix A of the report. · Capital Programme of £3,450,435 as set out in Appendix A of the report. · Including in-principle approval for the expansion of the Special school estate, by both supporting the delivery of two new (potential) DfE delivery schools (SEMH and AP), and the expansion of Brownhill Learning Community to meet need, with particular focus on relocation/redesign of Saxon Hall to meet future demand. 3. To authorise the Director for Children’s Services to invite and evaluate tenders for the projects described in the report and to enter into the appropriate contracts and incidental and ancillary documentation in consultation with the Portfolio Holder and Assistant Director Legal and Governance. 4. To authorise the Council’s Section 151 Officer to allocate and vire funding to Children’s Services to support the programme when it was received. Reasons for the Decision Cabinet approval was required for the proposed expenditure on the various schemes set out in the report in accordance with the Council’s Financial Regulations.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1. The report seeks approval for proposed expenditure on various schemes in accordance with the Council’s Financial Regulations. These regulations provide that Cabinet approval should be obtained before new expenditure can be incurred. This report requests approval and tender acceptance, where necessary, for the outlined and reserve schemes proposed, contingency and other specified budgets.
Recommendation
2. Members are asked to consider the report and to:
Note the future capital allocations as follows: School Condition Allocations £1,800,000 (indicative figure for receipt in each of years 2023/24 and 2024/25) Additional DfE School Condition Allocation for 2022/23 £920,435 Devolved Formula Capital (DFC) £480,000 (indicative figure for receipt in each of years 2023/24 and 2024/25)
And to
ii) Approve expenditure on the proposed programmes detailed within this report (Appendix A), for invitations to tender to be issued and accepted and for the supporting contracts, PFI deeds of variation (where necessary) and any incidental and ancillary documentation, to be signed in order to deliver the development schemes outlined in the appendices, in accordance with Financial Regulations:
Basic Need Programme of £25,056,008 as set out in Appendix A
Capital Programme of £3,450,435 as set out in Appendix A
Including in-principle approval for the expansion of the Special school estate, by both supporting the delivery of two new (potential) DfE delivery schools (SEMH and AP), and the expansion of Brownhill Learning Community to meet need, with particular focus on relocation/redesign of Saxon Hall to meet future demand.
iii) Authorise, subject to the approval of recommendation 1, the Director for Children’s Services to invite and evaluate tenders for the projects described in this report and enter into the appropriate contracts and incidental and ancillary documentation in consultation with the Portfolio Holder and Assistant Director Legal & Governance, as per the Council’s Constitution.
iv) Authorise the Council’s Section 151 officer to allocate and vire funding to Children’s Services to support the programme when it is received.
Reason for recommendation
3. Background 3.1 The Authority expects to receive no further of allocations for Basic Need for 2023/24, this reflects the DfE’s provision of the proposed new Secondary and SEN Free Schools, rather than the LA. Demand on, and proposals relating to school places were previously reported to Cabinet on 22nd November 2022, this will be folllowed by further reports as need is identified. Repairs to the LA maintained school estate have considered all commitments and urgent demands before making recommendations to address the most significant issues, in conjunction with continued DFC allocations to schools.
3.2As well as on-going support for the current phases of capital works already committed, we are proposing a new programme of works to address major condition needs based on Asset Management information, recently commissioned and prioritised full building condition survey information and priority place planning demands in order to ensure that we satisfy the LA’s statutory obligations for the provision of school places and continued education. Our full recommendations for inclusion in this year’s capital programme are outlined in Appendix A, including costs estimated by the Council’s Property Services Team.
3.3It is proposed that the Buildings Maintenance revenue budget will be used, as in previous years, to support programme development costs, emergency/unplanned repairs and ongoing obligations related to the inspection of the schools building stock.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.