The Three Year (2026/27 to 2028/29) Local Transport Plan (LTP) Highways Programme of Works
ApprovedCommittee1 paper
AI summaryHeywood Township Committee has approved Rochdale's three-year Local Transport Plan highways programme covering 2026/27 to 2028/29, based on a £3.058m annual Department for Transport allocation for 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCarriageway and bridges works for 2026/27 to 2028/29
Money£3.058m annual LTP allocationUsed as a guide for 2027/28 and 2028/29, subject to DfT confirmation
What happens nextProgrammes delivered in 2026/27 to 2028/29Each scheme subject to its own due diligence and governance
Who it affectsResidents across five Rochdale townshipsHeywood 14%, Middleton 22%, Pennine 20%, Rochdale North 19%, Rochdale South 25%
What was decided
The Committee approved the proposed three-year Local Transport Plan Highways Programme of Works to be delivered in 2026/27, 2027/28 and 2028/29 as set out in the report. Report P2, P4
Schemes were selected using asset management principles drawing on network condition data, engineer inspections, life cycle planning and cost efficiency. Report P4, P5
The programme keeps the council aligned with Department for Transport guidance on preventative maintenance and secures the full DfT incentive fund allocation. Report P5
Why
Asset management based scheme selection meets the Department for Transport's strategic aim of prioritising preventative maintenance. Report P4, P5
Following DfT guidance enables Rochdale to continue receiving the full incentive fund allocation and to align with other Greater Manchester authorities. Report P5
What happens next
The 2027/28 and 2028/29 allocations will be confirmed when the Department for Transport publishes annual allocations. Report P5
Any project underspends will be spent in conjunction with the township where the underspend occurred. Report P6
Each individual scheme within the programme will be subject to its own due diligence, governance and decision making. Report P7
The money
£3.058m Total LTP allocation for highways in 2026/27, used as a guide for later years Report P5
Options considered
Rejected: Not to agree the Programme of Works. Could reduce the amount of funding Rochdale Borough Council receives from the Department for Transport Report P5
Chosen: Approve the proposed three-year LTP Highways Programme of Works. Aligns with DfT guidance, supports preventative maintenance and protects incentive fund allocation Report P4, P5
Implications
Financial: Approval preserves the council's full DfT incentive fund allocation; 18% of budget is ringfenced for bridges and structures, the remainder split by township population. Report P5
Legal: No immediate legal implications; each scheme will be subject to its own due diligence and governance. Report P7
Who and where
Residents and road users in the Heywood township (14% share of funding) Report P5, P9
Residents and road users in the Middleton township (22% share of funding) Report P5, P9
Residents and road users in the Pennine township (20% share of funding) Report P5, P9
Residents and road users in the Rochdale North township (19% share of funding) Report P5, P9
Residents and road users in the Rochdale South township (25% share of funding) Report P5, P9
Timeline
3rd November 2025: Heywood Township Committee approved the three-year LTP Highways Programme of Works Report P1
2026/27: First year of LTP carriageway and bridges/structures programme delivery, funded by £3.058m allocation Report P2, P4, P5
2027/28: Second year of LTP programme delivery, subject to DfT allocation confirmation Report P2, P4, P5
2028/29: Third year of LTP programme delivery, subject to DfT allocation confirmation Report P2, P4, P5
Plain English for the jargon
LTP: Local Transport Plan, the funding stream from the Department for Transport used for the programme.
DfT: Department for Transport, the government department providing the funding allocation and incentive fund.
CW: Carriageway, the road surface works category used in the programme list.
Steady State programme: A separate 2026/27 programme of works containing schemes not identified in the LTP programme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28
Resolved
Resolved - That the proposed three-year Local Transport Plan Highways Programme of Works to be delivered in 2026/27, 2027/28 and 2028/29, as set out in the report be approved. Reasons for the decision The schemes had been selected and developed based on the principles of asset management, which utilised network condition data, engineer inspections, life cycle planning and cost efficiency to produce the most efficient highway improvement over the course of the programmes. Using asset management techniques for scheme selection ensured the Council was in line with recommendations from the Department for Transport to meet the strategic aim of investing in preventative maintenance techniques as a priority. This enabled the Council to continue to receive full funding allocation from the Department for Transport incentive fund scheme. Alternatives considered Not to agree the Programme of Works – this option was not recommended as it could potentially cause a reduction in the amount of funding Rochdale Borough Council received from the Department of Transport. The Programme had been developed according to Department for Transport guidance, and in line with other Greater Manchester local authorities. It was noted there was a Steady State 2026-27 Programme of Works that included schemes not identified in the proposed Local Transport Plan Programme.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report title: The Three Year (2026/27 to 2028/29) Local Transport Plan (LTP) Highways Programme of Works Report to: Heywood Township Committee Date of meeting: 3rd November 2025 Cabinet Portfolio Holder: Portfolio Holder for Highways and Facilities Management Report of: Director of Economy and Place Public or private: Public Key Decision: No Published on the Forward Plan: N/A
1. Report summary 1.1 The purpose of this report is for Members to note and approve the attached highways work programmes which are proposed to take place during the 2026/27, 2027/28 and 2028/29 financial years.
The attached programme includes the following – • 3 year local transport plan (LTP) funded carriageway capital programme. • 3 year Bridges and Highway Structures local transport plan (LTP) funded capital programme.
2. Recommendations 2.1 That the Committee note and approve the proposed work programmes to be delivered in 2026/27, 2027/28 and 2028/29. 3. Reason for recommendation 3.1 The schemes that have been selected have been prepared based on the principles of asset management which use network condition data, engineer inspections, life cycle planning and cost efficiency to produce the most efficient highway improvement over the course of the programmes.
Using Asset Management techniques for scheme selection ensures that we are in line with recommendations from the Department for Transport (DfT) meeting their strategic aims to invest in preventative maintenance techniques as a priority and enables us to continue to receive the full funding allocation from the DfT incentive fund scheme 4. Alternatives considered 4.1 No alternatives have been considered. The programme has been developed according to DfT guidance and in line with other GM Authorities. However, members should note that in addition to the LTP programme there is the Steady State 2026-27 programme of works which includes schemes not identified in this proposed programme. 5. Key information 5.1 The recommended programme has been put together to achieve the highest level of improvement available with the allocated budget. Not agreeing this programme could potentially cause a reduction in the amount of funding Rochdale Borough Council receive from the DfT 6. Finance 6.1 The total LTP allocation for highways is £3.058m for 2026/27. For the purpose of this report the figure of £3.058m has been used as a guide for the 2027/28 and 2028/29 programmes and will be subject to confirmation when the annual allocations are published by the Department For Transport The budgets with the exception of bridges and structures (18%) have been split into each Township according to population size. The budget splits are as follows – Township % Allocation Heywood 14 Middleton 22 Pennine 20 Rochdale North 19 Rochdale South 25
Any project underspends will be spent in conjunction with the Township where the underspend occurred
7. Legal 7.1 There are no immediate legal implications arising from this report. Each programme of works will be subject to its own due diligence, governance and decision making as required. Human resource 8.1 N/A 8. Sustainability impact 8.1 N/A 9. Other considerations (corporate priorities, risks) 9.1 N/A Background Papers: Contact: Andy Collins - [email protected]
Treatment Approx. Township Road Type/Work Budget Source From / To Type
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.