The Three Year (2026/27 to 2028/29) Local Transport Plan (LTP) Highways Programme of Works
ApprovedCommittee1 paper
AI summaryRochdale South Township Committee approved the three-year Local Transport Plan Highways Programme for 2026/27 to 2028/29. The total LTP highways allocation is £3.058m for 2026/27, with 25% allocated to Rochdale South.
Money£3.058m for 2026/27Total LTP highways allocation, used as guide for later years
What happens nextAnnual DfT allocations to confirmFuture years subject to confirmation from Department for Transport
Who it affectsRochdale South residents and roads25% of township share; plus bridges and structures 18%
What was decided
The Committee approved the proposed three-year Local Transport Plan Highways Programme of Works for 2026/27, 2027/28 and 2028/29. Report P2, P4
The carriageway and bridges and structures capital programmes were noted as part of the approved package. Report P3
The Committee accepted that scheme selection followed asset management principles using network condition data, engineer inspections, life cycle planning and cost efficiency. Report P4
Why
Asset management techniques align with Department for Transport recommendations on preventative maintenance and secure the Council's full share of the DfT incentive fund. Report P5
Not approving the programme could reduce the amount of DfT funding Rochdale Borough Council receives. Report P5
The programme was developed according to Department for Transport guidance and in line with other Greater Manchester authorities. Report P5
What happens next
Each programme of works will be subject to its own due diligence, governance and decision making as required. Report P7
Budgets for 2027/28 and 2028/29 are subject to confirmation when annual DfT allocations are published. Report P5
Any project underspends will be spent in conjunction with the township where the underspend occurred. Report P6
The money
£3.058m Total LTP allocation for highways for 2026/27, used as a guide for 2027/28 and 2028/29 Report P5
Options considered
Chosen: Approve the proposed three-year LTP Highways Programme of Works. Aligns with DfT preventative maintenance priorities and preserves full DfT incentive fund allocation Report P4, P5
Rejected: Do not agree the Programme of Works. Could potentially cause a reduction in the amount of DfT funding Rochdale Borough Council receives Report P5
Implications
Financial: Full DfT incentive fund allocation is at risk if the programme is not approved, and a separate Steady State 2026-27 programme covers additional schemes not on this list. Report P5
Legal: No immediate legal implications; each works programme will go through its own due diligence and governance. Report P7
Other: Budgets are split by township population (Heywood 14%, Middleton 22%, Pennine 20%, Rochdale North 19%, Rochdale South 25%), except for bridges and structures which receive 18%. Report P5
Who and where
Rochdale South township, with 25% of the carriageway allocation and a long list of named road treatments Report P5, P9
Heywood, Middleton, Pennine and Rochdale North townships, each receiving a population-based share of carriageway funding Report P5
Bridges and structures programme, ring-fenced at 18% of the LTP allocation Report P5
Timeline
2026/27: First year of the LTP Highways Programme of Works to be delivered Report P2
2027/28: Second year of the programme; budget subject to DfT annual allocation confirmation Report P2, P5
2028/29: Third year of the programme; budget subject to DfT annual allocation confirmation Report P2, P5
2025-11-06: Decision taken at Rochdale South Township Committee meeting Report P1
Plain English for the jargon
LTP: Local Transport Plan, the Department for Transport funding stream for local highway maintenance
DfT: Department for Transport
CW: Carriageway, used as a prefix on the scheme list to indicate road surface treatments
Steady State 2026-27 Programme: A separate programme of works covering schemes not identified in the LTP programme
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43
Resolved
Resolved : That the proposed three-year Local Transport Plan Highways Programme of Works to be delivered in 2026/27, 2027/28 and 2028/29, as set out in the report be approved. Reasons for the decision: The schemes had been selected and developed based on the principles of asset management, which utilised network condition data, engineer inspections, life cycle planning and cost efficiency to produce the most efficient highway improvement over the course of the programmes. Using asset management techniques for scheme selection ensured the Council was in line with recommendations from the Department for Transport to meet the strategic aim of investing in preventative maintenance techniques as a priority. This enabled the Council to continue to receive full funding allocation from the Department for Transport incentive fund scheme. Alternatives considered: Not to agree the Programme of Works – this option was not recommended as it could potentially cause a reduction in the amount of funding Rochdale Borough Council received from the Department of Transport. The Programme had been developed according to Department for Transport guidance, and in line with other Greater Manchester local authorities. It was noted there was a Steady State 2026-27 Programme of Works that included schemes not identified in the proposed Local Transport Plan Programme.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report title: The Three Year (2026/27 to 2028/29) Local Transport Plan (LTP) Highways Programme of Works Report to: Rochdale South Township Committee Date of meeting: 6 November 2025 Cabinet Portfolio Holder: Portfolio Holder for Highways and Facilities Management Report of: Director of Economy and Place Public or private: Public Key Decision: No Published on the Forward Plan: N/A
1. Report summary 1.1 The purpose of this report is for Members to note and approve the attached highways work programmes which are proposed to take place during the 2026/27, 2027/28 and 2028/29 financial years.
The attached programme includes the following – • 3 year local transport plan (LTP) funded carriageway capital programme. • 3 year Bridges and Highway Structures local transport plan (LTP) funded capital programme.
2. Recommendations 2.1 That the Committee note and approve the proposed work programmes to be delivered in 2026/27, 2027/28 and 2028/29. 3. Reason for recommendation 3.1 The schemes that have been selected have been prepared based on the principles of asset management which use network condition data, engineer inspections, life cycle planning and cost efficiency to produce the most efficient highway improvement over the course of the programmes.
Using Asset Management techniques for scheme selection ensures that we are in line with recommendations from the Department for Transport (DfT) meeting their strategic aims to invest in preventative maintenance techniques as a priority and enables us to continue to receive the full funding allocation from the DfT incentive fund scheme 4. Alternatives considered 4.1 No alternatives have been considered. The programme has been developed according to DfT guidance and in line with other GM Authorities. However, members should note that in addition to the LTP programme there is the Steady State 2026-27 programme of works which includes schemes not identified in this proposed programme. 5. Key information 5.1 The recommended programme has been put together to achieve the highest level of improvement available with the allocated budget. Not agreeing this programme could potentially cause a reduction in the amount of funding Rochdale Borough Council receive from the DfT 6. Finance 6.1 The total LTP allocation for highways is £3.058m for 2026/27. For the purpose of this report the figure of £3.058m has been used as a guide for the 2027/28 and 2028/29 programmes and will be subject to confirmation when the annual allocations are published by the Department For Transport The budgets with the exception of bridges and structures (18%) have been split into each Township according to population size. The budget splits are as follows – Township % Allocation Heywood 14 Middleton 22 Pennine 20 Rochdale North 19 Rochdale South 25
Any project underspends will be spent in conjunction with the Township where the underspend occurred
7. Legal 7.1 There are no immediate legal implications arising from this report. Each programme of works will be subject to its own due diligence, governance and decision making as required. Human resource 8.1 N/A 8. Sustainability impact 8.1 N/A 9. Other considerations (corporate priorities, risks) 9.1 N/A Background Papers: Contact: Andy Collins - [email protected]
Treatment Approx. Township Road Type/Work Budget Source From / To Type
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointments to the Norman Barnes FundThat Councillor Aasim Rashid, Councillor A. Smith and Billy Sheerin be appointed as Trustees to the Norman Barnes Fun...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.