Resolved :- (1) That the report be received and the additional £2 million utilising Prudential Borrowing over a payback period of 60 years be approved. (2) That the pressure this additional borrowing would create in the Council’s capital financing budget be approved. (3) That the Eldon Road allotment site for the proposed location of the new Central Primary School be approved. (4) That negotiations for the purchase of the Donfield Tavern and associated land be approved.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
There is an unprecedented increase in the numbers of pupils needing to access schools places within the authority. As a consequence of the increasing pressure on school places, it is necessary to increase the number of school places in the authority.
There is particular pressure for school places within the central catchment areas of Rotherham that is Eastwood and St Ann’s.
In response to this pressure a bid was submitted by the Council to the Department for Education (DfE) through their Targeted Basic Need Programme to fund a 1.5 form new central primary school (ages 3 to 11) to be located within the central catchment area of the authority.
The Council was successful with their bid and has secured a grant of £3,216,065 plus £150,000 for project support funding. The estimated cost of the new school would be c£5.2m. The additional £2m will need to be funded by the Council.
The times scales for the development are a two year programme of design and construction with an anticipated opening at the start of the 2015/2016 school year.
This report requests the Cabinet approve the recommendations as detailed in Section 6 of this report.
Recommendations
• That the report is received and approval given for the Council to fund the additional £2m utilising Prudential Borrowing over a payback period of 60 years. • Approval is given to reflect the pressure this additional borrowing will create in the Council’s capital financing budget. • Approval is given to the Eldon Road allotment site for the proposed location of the new Central Primary School. • Approval is given for the Council to negotiate the purchase of the Donfield Tavern and associated land. 7. Background
There is an unprecedented increase in the numbers of pupils needing to access schools places within the authority. As a consequence of the increasing pressure on school places, it is necessary to increase the number of school places in the authority.
There is particular pressure for school places within the central catchment areas of Rotherham that is Eastwood and St Ann’s. A “snapshot” count taken on the 19th August 2013 showed there to be 62 children without a school place in the authority of which 25 were within the Eastwood and St Ann’s catchment area.
Additionally Eastwood and St Ann’s is an area of deprivation and with a high proportion of EU migrants. A study of the census data shows that the population of the area has grown by 7.8% compared to the Rotherham average of 3.7% from 2001 to 2011. The census data confirms that the BME population is greater in this area than the rest of Rotherham, 34.2% compared to 8.1%. The 0 to 4 age population percentage of the Eastwood area is also greater than the Rotherham average, 11.8% compared to 6.1%. Birth projections also show an increase which substantiates the census data and in addition the total admission number is regularly below the births in the area.
Further places are currently being created at Herringthorpe Infant and Junior Schools, which is able to be expanded by 20 pupils per year group. This will increase the published admission number in the area to 514, which is still below the number of births which is 527 in 2013/14 rising to 585 in 2014/15.
In response to this pressure the Council submitted a bid to the DfE Targeted Basic Need Programme to fund a new 1.5 form entry Primary school (ages 3 to 11) to provide a long term solution to pupils needing to access school places within the central catchment areas of the authority. The estimated cost of providing this provision was c£5.2m.
On the 18th July 2013 the Council was informed that the bid had been successful.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.