CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Cabinet (Pre-Intervention, Wednesday 2 June 2004

Corporate Risk Register

Noted Executive 1 paper

Cabinet (Pre-Intervention noted this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.

Item215

Resolved

Resolved :- (1) That the updated corporate risk register summary attached at Appendix A be noted. (2) That any further risks that Cabinet feels should be added to the risk register be indicated.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Cabinet (Pre-Intervention, 24 pages

Summary

Attached to this report is the current corporate risk register summary. The summary shows the risks associated with the Council’s most significant priorities and projects, and actions being taken to mitigate these risks.

Included in the significant changes this period is a new risk relating to the integration of 2010 Rotherham Ltd services back into Council management. New risks have also been added relating to highways road conditions, schools collaboration (relating to procurement of services) and the establishment of Free Schools.

There are 2 red residual risks, relating to Use of Resources for Children’s Services and Social Care Commissioning. This has reduced from 4 residual red risks in the previous quarter’s report, as the achievement of the Cultural Quarter risk is not immediately at risk and the delivery of the Children & Young People’s Plan is no longer a statutory requirement. Both have therefore been moved from the Corporate Risk Register to the EDS and CYPS Directorate Risk Registers respectively.

Recommendations

Cabinet is asked to:

• note the updated corporate risk register summary attached at Appendix A

• indicate any further risks that Cabinet feels should be added to the risk register. 7 Proposals and Details

7.1Format This report contains the latest position on the Corporate Risk Register. The report has two key parts:

• An ‘at a glance’ picture showing the pattern of risk assessments for corporate priorities or projects both before and after risk management actions – see 7.3 below.

• A more detailed summary of the risk register that reflects the current risk assessments for each corporate priority or project. This is attached at Appendix A.

There are 3 overall categories of risk (RED, AMBER, GREEN) representing varying degrees of exposure. Each category contains a range of risk scores, so there are varying degrees of risk within each category. Appendix A shows specific current risk scores and after mitigating actions, as well as the general risk category for each priority or project included in the register.

7.2Changes since previous SLT report. The risk relating to the ALMO Decent Homes Programme has been removed from the corporate risk register following the completion of the programme. Other significant changes in this period include:

• A new risk has been created relating to the integration of 2010 Rotherham Ltd services back into Council management (Appendix A reference SLT0014). This replaces the previous risk relating to 2010 Rotherham Ltd service and financial performance.

• The risk formerly titled ‘Response to DFE Notice to Improve’ (SLT0021) has been renamed ‘Sustaining improvement post intervention’ to reflect the official confirmation of the removal of the notice to improve, which was received on 13 January 2011.

• A new risk has been added to reflect the position regarding Highway Maintenance in light of deteriorating road conditions and finite budgets for road maintenance. (SLT0029).

• Two new CYPS risks have been added entitled ‘Schools Collaboration’ (SLT0030) and ‘Free Schools and Other School Arrangements’ (SLT0031) in recognition of the potential negative impact on both schools commissioning and wider Local Authority services.

• The risk relating to the Cultural Quarter has been removed from the Corporate Risk Register as this does not constitute an immediate risk.

• The former risk relating to the delivery of the Children & Young People’s Plan (SLT0007) is no longer a statutory requirement and has therefore been moved to the CYPS Directorate Risk Register.

• The mitigations relating to former risk Academy Schools (SLT0028) are now at 90% complete level and / or are being managed operationally; therefore the risk has been moved to the CYPS Directorate Risk Register. 7.3 Corporate Risks at a Glance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk RegisterReport 24 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Corporate Risk RegisterThis decision
  2. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateDecided
  3. Corporate Strategic Risk Register UpdateNoted
  4. Corporate Strategic Risk Register UpdateNoted
  5. Risk Management Annual Summary 2022-2023 and Corporate Strategic Risk Register UpdateNoted
  6. Corporate Strategic Risk RegisterNoted

More from Rotherham Cabinet (Pre-Intervention

All decisions
MeetingDecisionOutcome
2 Jun 2004 IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... Approved Open
2 Jun 2004 Questions from Members of the Public.It was agreed to provide a detailed answer in writing. Agreed Open
2 Jun 2004 Awards- That Members and staff involved be congratulated on these achievements. Decided Open
2 Jun 2004 John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . Decided Open
2 Jun 2004 Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies