Rotherham Metropolitan Borough Council
Audit Committee, Tuesday 28 July 2026

Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register Update

Decided Finance 1 paper

AI summaryRotherham Audit Committee noted the 2025-26 risk management summary and Corporate Strategic Risk Register updates, with 16 risks on the register and four rated red.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee asked to consider and note both items
MoneyNot stated
What happens nextM2 training restarts August 2026Refreshed risk guide to go to November Audit Committee
Who it affectsRotherham Council and partnersRisk register covers all directorates, services and partners

What was decided

The Audit Committee considered and noted the annual summary of risk management activity for 2025-2026. Report P1

The Audit Committee considered and noted the updates to the Corporate Strategic Risk Register, with 16 strategic risks now on it and four rated red. Report P2, 6.1

Why

The report summarises the principal risk management activity over the past financial year and updates members on the key movements in strategic risks, supporting the Council's ongoing risk and assurance aims. Report 1.1, 1.2, 2.1

Internal Audit's most recent review of Corporate Risk Management, completed in March 2024, gave a 'substantial assurance' rating that the controls were operating effectively. Report 4.6, 4.7

The strategic risk profile rose over 2025-26, with three new red-rated risks added and one existing risk escalated to red, including Equal Pay litigation, Highways Structures inspection, ICB funding, and the Carbon Reduction Plan. Report 5.4, 6.2

What happens next

The M2 manager risk management course, paused in Autumn 2025, will be refreshed and restart in August 2026 under the new Policy, Improvement and Risk Manager. Report 3.2, 7.1

The Corporate Risk Management Guide will be refreshed in the latter part of 2026, with the revised version presented to the Audit Committee for approval at its November meeting. Report 7.2

A new annual cycle has been set under which the Audit Committee will review all directorate risk registers at least once and the CSRR twice in the next 12 months. Report 4.4

Options considered

  • Chosen: Consider and note the annual summary and CSRR updates. Recommendations set out in paragraphs P1 and P2; the report states no alternative options were considered. Report P1, P2, 8.1

Implications

  • Financial: Any additional costs of managing risks will be contained within overall budgets or reported through monthly financial monitoring and to Cabinet if appropriate. Report 11.1
  • Legal: No direct legal implications arise from the risk register; any actions taken in response will consider specific legal implications. Report 12.1
  • Equalities: Proposals for addressing individual risks within the register incorporate equalities and human rights considerations where appropriate. Report 15.1
  • Other: The Strategic Risk Register incorporates Children's and Young People's Services risks that are significant at a corporate or strategic level. Report 14.1
  • Staffing: There are no direct Human Resources implications associated with the proposals. Report 13.1
  • Risk: Strategic risks rose over the year: three new red risks (Equal Pay litigation at 20, Highway Structures inspection at 15, ICB funding at 20) plus the Carbon Reduction Plan escalated to 16; regeneration delivery rose to 15. Report 6.2

Who and where

  • Rotherham Council directorates, with Risk Champions in place for Children's Services, Regeneration and Environment, Corporate Services, Housing, Adult Care, Public Health, HR, and Policy, Strategy and Engagement Report 2.4, 2.5
  • Council staff required to undertake mandatory online risk training; 86% had completed it by end of June 2026 Report 3.1, 3.5
  • Council managers at M2 grade and above required to undertake the two-hour risk course (383 completed since January 2022) Report 3.1, 3.2
  • Risk Champions and deputies required to complete the two-day IRM accredited course (around 60 managers accredited since 2022) Report 3.1, 3.3
  • Elected members, with a course recording available on the member training portal and a further course planned Report 3.4
  • Council partners and suppliers, whose financial or business affairs are referenced in the exempt Appendix 1 Report P12, 16.1

Timeline

  • January 2022: M2 manager course relaunched after Covid pause Report 3.2
  • 22 February 2022: Elected members risk training course delivered, attended by fifteen members Report 3.4
  • March 2024: Internal Audit's last review of Corporate Risk Management completed, giving 'substantial assurance' Report 4.6, 4.7
  • 29 July 2025: Previous annual risk management summary report to Audit Committee Report P5
  • Autumn 2025: M2 manager course paused following retirement of previous Policy, Improvement and Risk Manager Report 3.2
  • 13 January 2026: Previous Corporate Strategic Risk Register update report to Audit Committee Report P6
  • March 2026: Two-day IRM accredited course run; ten staff accredited Report 3.3
  • End of June 2026: 86% of all staff had completed the online risk management course Report 3.5
  • 12 June 2026: Date of the full Corporate Strategic Risk Register in Appendix 1 Report P4, 6.1
  • 28 July 2026: Audit Committee meeting at which this report was considered
  • August 2026: M2 manager risk course to restart with refreshed content Report 7.1
  • November 2026: Refreshed Corporate Risk Management Guide to be presented to Audit Committee for approval Report 7.2
  • Early 2027: Next two-day IRM accredited course currently intended to run Report 3.3

Plain English for the jargon

  • CSRR: Corporate Strategic Risk Register, the Council's record of its most significant strategic risks
  • IRM: Institute of Risk Management, the body that accredits the two-day risk management course
  • SLT: Strategic Leadership Team, which formally reviews the CSRR quarterly
  • DLT: Directorate Leadership Team, which reviews directorate risk registers
  • SMT: Service Management Team, which reviews service-level risk registers
  • M2: A management grade at the Council; M2 managers and above must complete the two-hour risk course
  • ICB: Integrated Care Board, the NHS body whose funding reductions affect adult social care commissioning
  • CYPS: Children and Young People's Services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

- That the annual summary of risk management ... view the full minutes text for item 28.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Audit Committee

Recommendations

1. The Audit Committee is asked to consider and note the annual summary of risk management activity

2. The Audit Committee is asked to consider and note the updates to the Corporate Strategic Risk Register and make any comments as necessary.

List of Appendices Included

Appendix 1 Full Corporate Strategic Risk Register at 12 June 2026. Background Papers

Report to Audit Committee; 29 July 2025 (Annual Risk Management Summary 2024- 2025)

Report to Audit Committee; 13 January 2026 (Corporate Strategic Risk Register update)

Consideration by any other Council Committee, Scrutiny or Advisory Panel

This paper is not intended to be circulated to other Committees or Panels and is produced solely for the Audit Committee.

Council Approval Required No

Exempt from the Press and Public

Yes.

An exemption is sought for Appendix 1 under Paragraph 3 (Information relating to the financial or business affairs of any particular person (including the authority holding that information)) of Part I of Schedule 12A of the Local Government Act 1972 is requested, as this report contains information that refers to the affairs of third parties.

It is considered that the public interest in maintaining the exemption would outweigh the public interest in disclosing the information because failure to do so may result in disclosure of information about the financial or business affairs of Council suppliers and partners. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register Update

Background

1.1The Council’s ongoing risk and assurance aims are to:

• Provide Members and Senior Officers with an understanding of the key risks facing the Council and its communities, and to show how these risks are being effectively mitigated • Implement and maintain a fluid process for business-as-usual management of risks relevant to our objectives, outcomes, services and assets • Align reporting mechanisms for finance, risk, audit and performance providing members and senior officers triangulated risk and assurance profiles.

1.2This report aims to summarise the principal risk management activity that has been carried out within the Council throughout the past financial year. It also summarises the key movements in Strategic Risks that have occurred over the period and updates the Committee on the current risks on the Corporate Strategic Risk Register (CSRR).

2. Risk Management Responsibilities

2.1The Council’s Risk Management Policy and the separate Risk Management Guide both state that risk management is the responsibility of all Council officers. This is further set out in section 4.9 of the Policy where the specific responsibilities of all members and officers are detailed. In this section, all employees are required to:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateReport 239 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
JB
Councillor Jamie BaggaleyChair, present
JB
Councillor John BlackhamMember, present
RE
Councillor Rob ElliottMember, present
RI
Councillor Rukhsana IsmailMember, present
GM
Councillor Gina MonkMember, present
AH
Alison HutchinsonGuest, apologies
MO
Michael Olugbenga-BabalolaGuest, present
KS
Katie SteadCouncil Staff, expected

On this subject at Rotherham

Search all
  1. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateThis decision
  2. Risk Management Directorate Presentation - Finance and Customer ServicesNoted
  3. Risk Management Guide Refresh 2025Noted
  4. Risk Management Directorate Presentation - Regeneration and EnvironmentNoted
  5. Risk Management Directorate Presentation - Adult Care, Housing and Public HealthNoted
  6. Risk Management Directorate Presentation - Children and Young People's ServicesNoted

More from Rotherham Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... Decided Open
24 Sep 2026 Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. Approved Open
24 Sep 2026 External Audit Progress Report and Sector Update- That the progress and sector updates be noted. Noted Open
24 Sep 2026 Code of Corporate Governance- That the refreshed version of the be received and noted. Noted Open
24 Sep 2026 Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies