Resolved
Resolved :- (1) That permission be refused for the following reason:- It is considered that the development would have a materially detrimental effect on the residential amenities of adjoining residents by way of the generation of extraneous traffic and associated nuisance, along with noise dust and vibration from the process, and would thereby be in conflict with Policy HG 1 Housing and ENV 3.7 Control of Pollution of the adopted Unitary Development Plan. (2) That enforcement action for cessation of the use of the buildings and land for the manufacture and supply of fencing be authorised with a compliance period of three months.