Resolved
- (1) That the work that has already taken place in developing submissions to the Regional Transport Board (RTB) be endorsed. (2) That the decisions of the RTB to support the Bus Rapid Transit Scheme - both Northern and Southern Route routes be noted. (3) That the outline routes for both the BRT Scheme Northern and Southern, as shown on the drawing accompanying the report at Appendix A (Bus Rapid Transit – Northern and Southern Route Proposals Version 1.0) be agreed. (4) That the further development of Major Scheme Business Cases for both the BRT Scheme Northern and Southern Routes be noted. (5) That the report be referred for information to the Cabinet and the Regeneration Scrutiny Panel. (6) That further progress reports be submitted to future meetings of the Cabinet Member as appropriate.
Word for word from the decision Rotherham published for this meeting.
Source: moderngov.rotherham.gov.uk