CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
The Former Regeneration Scrutiny Panel, Wednesday 20 October 2010

Principal Road Programme

Noted Scrutiny 3 papers

The Former Regeneration Scrutiny Panel noted this item on Wednesday 20 October 2010. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

Resolved :- That the progress report be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to The Former Regeneration Scrutiny Panel, 4 pages

Recommendations

a) That the progress report be noted. 7. Proposals and Details

Principal Roads Capital Programme In July 2008 Council agreed a project for £5,000,000 of Major Strategic Capital Investment for the improvement of Principal Roads across Rotherham to be delivered over a three year period 2008-11. The first schemes within this programme commenced on site in October 2008 and the full programme of works is now nearing completion.

A schedule of schemes delivered or remaining to be completed this year as part of this programme together with other schemes on the Principal Road Network funded from other sources is attached to the report as Appendix A.

The national performance indicator for Principal Road condition, NI168, was one of the indicators selected for inclusion in the Local Area Agreement. The value of the indicator represents the percentage of the network in need of major repair and where maintenance should be planned soon. Improvement targets for this indicator set for the three year period were:

2008/09 5% 2009/10 4% 2010/11 3%

The target for both 2008/9 and 2009/10 were met. The final target of 3% by March 2011 was very challenging and has been made more so by the severe winter damage suffered early in 2010. We are currently on target to meet this figure. The latest national figures available are for 2008/9 when the top quartile figure was 3% with a median figure of 5%.

Various treatments have been used as part of the programme from large patch repairs and surface treatments through to the resurfacing / reconstruction of substantial lengths of road. In each instance the most appropriate option was selected for the nature and scale of the failure evident on the roads.

Due to the nature of the roads forming the Principal network, and the level of traffic that they carry, all works undertaken have restrictions placed on the timing of the works. All are programmed for off-peak working and a number are undertaken at night or on Sundays. These restrictions do have a significant impact on the resulting costs of the work. The needs of public transport also have to be taken into account.

Close liaison was required with Transportation Service in programming works in order to coordinate with their proposals for local safety and traffic management schemes. Maintenance works on Wellgate in Rotherham Town Centre were deferred pending the delivery of traffic management proposals.

A630 Centenary Way – Major Maintenance Scheme On 3 April 2009 the Department for Transport finally confirmed that a sum of £4,300,000 vired from the Regional Funding Allocation had been allocated to Rotherham to fund the reconstruction of Centenary Way at Canklow. Streetpride worked closely with our strategic partner, Ringway Infrastructure Services in preparing the final scheme and following detailed design the works commenced on site on 13 July 2009.

The works were extensive, involving the excavation and disposal of all the expansive material. This involved excavation to a depth of 1.2m on average over the full width of the dual-carriageway. As part of the works a new safety barrier was also installed within the reconstructed central reserve. All the excavated materials were taken for reprocessing and all unbound replacement materials used on the site were re-cycled aggregates.

During construction one lane of traffic in each direction was maintained at all times except at Ickles roundabout where reconstruction required some weekend closures. The junction with Canklow Road also had to be closed for some weeks and during this period of time the scheme funded the provision of a free shuttle bus between Canklow Road and the Transport Interchange.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 2: Appendix A oct 10 prn update programmesAppendix 14 pages Download
PDF
Item 2- Appendix B: Cent Way Comp ReportAppendix 2 pages Download
PDF
Principal Road ProgrammeReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Principal Road ProgrammeThis decision
  2. Principal Road Programme 2008-2011Noted
  3. Principal Road Programme 2008-11Decided

More from Rotherham The Former Regeneration Scrutiny Panel

All decisions
MeetingDecisionOutcome
23 Mar 2011 Minutes of the previous meeting of the Regeneration Scrutiny Panel held on 23rd February, 2011Resolved :- That the minutes be approved as a correct record. Approved Open
23 Mar 2011 Pedestrian Crossing Assessment Method and Costs- (1) That a scrutiny review take place on this subject and that a scoping meeting take place as soon as possible. (2... Noted Open
23 Mar 2011 Road Safety Education, Training and Publicity updateResolved :- (1) That the Senior Engineer be congratulated for his informative report and concise presentation. (2) Th... Noted Open
23 Mar 2011 Environment & Development Services Performance Report 3rd Quarter 2010 - 2011- That the content of the report be noted. Noted Open
23 Mar 2011 Minutes of the Performance and Scrutiny Overview Committee- That the content of the minutes be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies