Rotherham Metropolitan Borough Council

Corporate Risk Register

Noted Scrutiny 1 paper

The Former Performance and Scrutiny Overview Committee noted this item on Wednesday 27 April 2011. Below is the council's own wording, with the papers it was decided on.

Item165

Resolved

Resolved :- That the updated summary, attached at Appendix A to the report, be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to The Former Performance and Scrutiny Overview Committee, 24 pages

Summary

Attached to this report is the current corporate risk register summary. The summary shows the risks associated with the Council’s most significant priorities and projects, and actions being taken to mitigate these risks.

Included in the significant changes this period is a new risk relating to the integration of 2010 Rotherham Ltd services back into Council management. New risks have also been added relating to highways road conditions, schools collaboration (relating to procurement of services) and the establishment of Free Schools.

There are 2 red residual risks, relating to Use of Resources for Children’s Services and Social Care Commissioning. This has reduced from 4 residual red risks in the previous quarter’s report, as the achievement of the Cultural Quarter risk is not immediately at risk and the delivery of the Children & Young People’s Plan is no longer a statutory requirement. Both have therefore been moved from the Corporate Risk Register to the EDS and CYPS Directorate Risk Registers respectively.

Recommendations

Performance, Scrutiny and Overview Committee is asked to:

• note the updated corporate risk register summary attached at Appendix A

• indicate any further risks that the Committee feels should be added to the risk register. 7 Proposals and Details

7.1Format This report contains the latest position on the Corporate Risk Register. The report has two key parts:

• An ‘at a glance’ picture showing the pattern of risk assessments for corporate priorities or projects both before and after risk management actions – see 7.3 below.

• A more detailed summary of the risk register that reflects the current risk assessments for each corporate priority or project. This is attached at Appendix A.

There are 3 overall categories of risk (RED, AMBER, GREEN) representing varying degrees of exposure. Each category contains a range of risk scores, so there are varying degrees of risk within each category. Appendix A shows specific current risk scores and after mitigating actions, as well as the general risk category for each priority or project included in the register.

7.2Changes since previous SLT report. The risk relating to the ALMO Decent Homes Programme has been removed from the corporate risk register following the completion of the programme. Other significant changes in this period include:

• A new risk has been created relating to the integration of 2010 Rotherham Ltd services back into Council management (Appendix A reference SLT0014). This replaces the previous risk relating to 2010 Rotherham Ltd service and financial performance.

• The risk formerly titled ‘Response to DFE Notice to Improve’ (SLT0021) has been renamed ‘Sustaining improvement post intervention’ to reflect the official confirmation of the removal of the notice to improve, which was received on 13 January 2011.

• A new risk has been added to reflect the position regarding Highway Maintenance in light of deteriorating road conditions and finite budgets for road maintenance. (SLT0029).

• Two new CYPS risks have been added entitled ‘Schools Collaboration’ (SLT0030) and ‘Free Schools and Other School Arrangements’ (SLT0031) in recognition of the potential negative impact on both schools commissioning and wider Local Authority services.

• The risk relating to the Cultural Quarter has been removed from the Corporate Risk Register as this does not constitute an immediate risk.

• The former risk relating to the delivery of the Children & Young People’s Plan (SLT0007) is no longer a statutory requirement and has therefore been moved to the CYPS Directorate Risk Register.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk RegisterReport 24 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Corporate Risk RegisterThis decision
  2. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateDecided
  3. Corporate Strategic Risk Register UpdateNoted
  4. Corporate Strategic Risk Register UpdateNoted
  5. Risk Management Annual Summary 2022-2023 and Corporate Strategic Risk Register UpdateNoted
  6. Corporate Strategic Risk RegisterNoted

More from Rotherham The Former Performance and Scrutiny Overview Committee

All decisions
MeetingDecisionOutcome
27 Apr 2011 Review of Overview and Scrutiny- That the information be noted. Noted Open
27 Apr 2011 Rewriting the Script : Preparing Overview and Scrutiny for the" New Localism"Resolved :- That the information be noted. Noted Open
27 Apr 2011 Councillor Jane AustenResolved :- That Councillor Austen be thanked for her services to the Council and scrutiny in particular and she be w... Decided Open
8 Apr 2011 Date of Next MeetingResolved :- That the next meeting scheduled for 29th April be rearranged to Wednesday, 27th April, 2011 commencing at... Decided Open
25 Mar 2011 The Role and Functions of Overview and Scrutiny in Rotherham - Future Arrangements- (1) That, as far as this Committee is concerned, approval be given to the proposal to establish an Overview and Scr... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies