Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 6 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the report be noted.
The report sets out the final outturn position for the Housing Investment Programme (HIP) and Non HIP Capital Schemes for 2010/11. The HIP shows a year end underspend of £3.664m (7.27%) against budget.
THAT CABINET MEMBER RECEIVES AND NOTES THE REPORT. 7. Proposals and Details
7.1A revised Housing Investment Programme (HIP) totalling £50.379m was approved by the Cabinet Member on 13th December 2010 against resources of £50.962m. The outturn position for each of the schemes within the HIP are included in Appendix 1.
7.2The final outturn position is £46.715m which represents an underspend of £3.664m against the Programme. Within this overall underspend, it is worth noting that schemes managed by 2010 Rotherham Ltd (£26.545m) overspent by £1.090m (4.1%), whilst there was a £4.753m underspend (19.94%) on the £23.833m schemes managed by the Council. The following paragraphs provide the Cabinet Member with explanations for the main variances from the approved Programme.
2010 Ltd Managed Schemes
7.3For the schemes managed by 2010 Rotherham Ltd, £27.635m has been spent which equates to an overspend of £1.090m against the approved Programme (£26.545m).
Decent Homes – Phase 2
7.4The Refurbishment budget of £11.335m outturned at £13.577m, an overspend of £2.242m. On 4th October 2010 Cabinet Member was first informed of a potential £1.5m overspend following the need to amend the specification of Decent Homes work in East Herringthorpe and the confirmation of the Connaught settlement figure. To address these issues a virement of £400k from the Environmental works budget was approved together with the temporary use of £1.2m HRA balance in 2010/11 which will be replenished in 2011/12.
Since the above approvals, the final accounts for the other contractors have been received and in order to bring some of the properties to the Rotherham Decent Homes Standard extra structural and improvement works over and above the target costs agreed with the contractors have been incurred. This has led to Bramall Construction being overspent by £1.086m and Boots by £1.077m contributing to the overall Refurbishment overspend of £2.242m.
7.5There was an underspend on the Windows Replacement Programme of £639k which arose due to reduced installation requirements on the planned windows programme. This became apparent following on site survey works to establish real demand on a property by property basis. Also, some communal areas scheduled for work in 2010/11 were deemed fit for purpose and re-allocated into future programmed schemes. Other Capital Projects
7.6The Disability Discrimination Act Works had a budget allocation of £100k and no final expenditure. This programme was to be focussed on works to the neighbourhood centres but as the review into them has still to be concluded there were no outcomes to act upon. The review should be completed in 2011/12 to enable the Council to ensure the centres will serve a wider customer base, offer an increased range of activities and still remain accessible to the public. Once this has been completed a programme will be set to fit the timescale for completion. The saving achieved in 2010/11 has partially offset the refurbishment overspends described above.
7.7One-Off Properties – The original budget of £400k was revised during the review by 2010 Rotherham to assist with management of the Refurbishment budget pressures previously mentioned. Certain activities were slowed down, including the conversion of the Elizabeth Finch neighbourhood centre, and expenditure was capped at £240k. Actual expenditure was £228k due to a delay with an element of the work commissioned at Dawson Croft. This will now be completed in 2011/12.
RMBC Managed Schemes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIP OUTTURN 2010-11 Appendix 1xlsAppendix | 1 pages | Download |
PDF |
HIP OUTTURN 2010-11 Appendix 2Appendix | 1 pages | Download |
PDF |
Housing Investment Programme (HIP) 2010/11 and Other Capital SchemesReport | 7 pages | DownloadRead as text |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.