Resolved
Resolved :- That the proposed works be approved and the funding arrangements noted.
Regeneration and Environment (to approved this item on Tuesday 21 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the proposed works be approved and the funding arrangements noted.
To report on proposals for environmental improvement works throughout the Laughton Common/Monksbridge corridors, including Monksbridge Roundabout.
(i) To provide enhanced landscaping works along Station Road and Outgang Lane, Laughton Common between the railway bridge at the north-west end of Laughton Common and Monksbridge Roundabout at the south-east end.
(ii) To provide enhanced landscaping works to Monksbridge Roundabout incorporating two mounds which acknowledge Dinningtons Neolithic past; the town is believed to take its name from a local long barrow or burial mound.
(iii) Similarly to provide high quality enhanced works along Monksbridge Road, Dinnington between Monksbridge Roundabout at the north-east end of the corridor and the junction of Monksbridge Road with Rotherham Road at the south-west end.
Cabinet Member approves the proposed works and notes the funding arrangements. 7. Proposals and Details
The Laughton Common/Monksbridge Road highway corridor was identified as a potential Gateway Improvement scheme within the wider Gateway Improvement Plan (approved 22 June 2005) and was included in the 2010/11 Regional Housing Programme.
The Cabinet Member will be aware of ‘Gateway’ style street name signs already installed throughout this corridor; a further phase of works is now proposed as follows.
Introduction of pedestrian footways at the junction of Monksbridge Road with Rotherham Road and at Station Road with ‘The Sycamores’.
Introduction of wildflower and bulb planting throughout the area, together with limited tree and shrub planting.
Landscaping improvements to Monksbridge Roundabout comprising two raised barrows, mature tree planting, wildflower and bulb planting. It should be noted that the existing commemorative ‘Pit Wheel’ feature will be retained.
Please refer to the plans in Appendix A (extent of coverage of the works), B (Footway Improvements at junction of Monksbridge Road and Rotherham Road) and C (Footway improvements at the junction of Station Road and The Sycamores) for details as to the extent of the works. More detailed copies of these plans have also been on display in the Members Room for the past week.
The Gateway project team within RIDO have ensured that extensive consultation has been carried out with the local community, including residents within the immediate vicinity of the works, the ‘Friends of Laughton Common’, New Laughton Tenants and Residents Association and Thurcroft Parish Council. Local Members have been involved with the project through the Dinnington Area Development Framework Steering Group.
Subject to Member approval, works will be carried out during the period January to March 2011.
8. Finance
These works will be funded from the 2010/11 Regional Housing Board programme, with Monksbridge Gateway having been allocated a budget of £180,000. It can be seen therefore that the proposed works fall well within the budget limit.
Total estimated costs:
(i). Outgang Lane Corridor
Cultivation and seeding £ 2,630.55 Maintenance of seeded areas £ 539.60 Wildflower planting £ 352.42 Spray off areas £ 1,667.60 Cultivate for shrubs £ 88.00 Shrub planting £ 2,240.00 Shrub maintenance £ 640.00 Beat up of shrubs £ 224.00 Tree planting £ 800.00 Bulb planting £ 3,117.60 Additional topsoil £ 500.00 Street lighting columns £ 7,500.00 Footway Improvements £ 9,243.89
Total £ 29,543.66
(ii). Monksbridge Road Corridor
Cultivation and seeding £ 2,636.40 Maintenance of seeded areas £ 540.80 Wildflower planting £ 554.64 Spray off areas £ 1,707.20 Cutting back existing vegetation £ 1,360.00 Tree planting £ 320.00 Bulb planting £ 1,620.00 Footway Improvements £ 19,276.70 Traffic Management Costs £ 800.00
Total £ 28,815.74
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Monksbridge Road and Station Road, DinningtonAppendix B | 1 pages | Download |
PDF |
Monksbridge Rod and Station Road, DinningtonAppendix C | 1 pages | Download |
PDF |
Footway Improvements at Monksbridge road and Station road, DinningtonReport | 5 pages | DownloadRead as text |
Follow Regeneration and Environment (to at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jun 2011 | Duke of Norfolk estate - Proposed No Waiting At Any Time RestrictionsResolved :- (1) That the proposal as currently advertised be implemented and then monitored for 2 months. (2) That th... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Local Development Framework Members' Steering Group held on 15th April, 2011Resolved :- That the content of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Opening of offers and e-tenders- That the action of the Cabinet Member on 31 st May, 2011 in opening offers and e-tenders for the following be recor... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Transport Liaison Group held on 16th March, 2011Resolved :- That the contents of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Petition requesting re-surfacing of carriageway on Chapel Walk, RawmarshResolved :- That the lead petitioner be informed that resurfacing of Chapel Walk, Rawmarsh , will be assessed for pri... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.