CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Town Centres (to, Wednesday 22 June 2011

Rotherham Economic Regeneration Fund (RERF) - Church Street Design Feasibility

Approved Committee 1 paper

Town Centres (to approved this item on Wednesday 22 June 2011. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

Resolved :- (1) That £5,000 of RERF revenue be approved to fund the provision of the design feasibility for public realm works on Church Street. (2) That a further report on the proposed design be submitted to a future meeting of the Cabinet Member for Town Centres.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Town Centres (to, 4 pages

ROTHERHAM BOROUGH COUNCIL – REPORT TO MEMBERS

1. Meeting: Cabinet Member for Town Centres

2. Date: 29th November 2010

3. Title: RERF - Church Street Design Feasibility

4. Programme Area: Environment and Development Services

5. Summary This report seeks approval of allocation of £5,000 RERF revenue funding to preparatory work on designing a public realm scheme for Church Street in Rotherham town centre.

6. Recommendations That £5,000 of RERF revenue is approved to fund the provision of the design feasibility for public realm works on Church Street. 7. Proposals and Details

After the demolition of the former All Saints Buildings the Council committed to providing a high quality public realm scheme, which not only covered the footprint of the demolished building but addressed the surrounding roads.

With the demise of the Regional Development Agency the original funding for the scheme was withdrawn. Officers have now secured funding through LAA Reward Grant, WNF and LABGI to create a new public open space on the site of the former building. This scheme is to be known as “Minster Gardens”. Works are due to commence in January 2011 with completion scheduled for August 2011. The budget available has been significantly reduced and the new scheme designed to incorporate a larger amount of soft landscape with the aim of reducing costs without reducing quality.

Also ongoing at this time is the redevelopment of Minster Yard. This scheme includes the restoration of footpaths, new seating, lighting of the Minster and the creation of a new stepped access from Church Street and is due for completion December 2010.

Between these two new pieces of public realm and immediately adjacent the recently refurbished Imperial Buildings is a piece of important space which has suffered from lack of investment and maintenance. The space includes two trees and three hexagonal seats probably dating from the 1970’s. The space is predominantly York stone paving with York stone setts and kerbs. Some areas are in good condition; however, several areas have been severely damaged by vehicular traffic during the restoration schemes as part of the wider Rotherham Renaissance.

The site is within the Town Centre Conservation Area and directly adjacent to two listed buildings. It is, therefore, vitally important that this space is improved to reflect the quality of the other two spaces and to ensure the connectivity with High Street.

The whole area would be a pedestrian only zone and free of vehicular traffic. Initial thoughts for the usage of the space includes, external event space for the Artists / Occupiers of Imperial Buildings and a dedicated café seating area with views over Minster Yard and Minster Gardens.

Officers from RiDO and Streetpride have been proactive in finding an affordable solution for this area. Currently the Council Highways Depot is relocating from Greasbrough Road to Hellaby. This move together with limited storage space at the new depot has resulted in a significant amount of paving materials which would be ideally suited to the Conservation Area becoming available.

The materials are generally left over from similar funded schemes, second hand products and other surplus to requirements including natural stone paving, setts and kerbs, steel bollards etc. Officers have earmarked all suitable materials for the project and these will be available “free issue”, provided that the physical work on site is carried out by the Streetpride Team.

The next step is to compile a detailed inventory of all materials, to include sizes, finish quantity etc. Also carry out a survey of the existing area and identify the quantity of reusable materials.

Once these tasks are complete, the Landscape Design Team will produce a draft scheme utilizing the new and existing materials. This design will then identify any shortfall of materials which may be required to complete the scheme. Detailed estimates can then also be produced and the scheme fully evaluated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rotherham Economic Regeneration Fund (RERF): Church Street Design FeasibilityReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Rotherham Economic Regeneration Fund (RERF) - Church Street Design FeasibilityThis decision
  2. Rotherham Economic Regeneration Fund - Allocation of FundingNoted
  3. Rotherham Economic Regeneration Fund - Rotherham Growth FundNoted
  4. Rotherham Economic Regeneration Fund (RERF) - Public Realm - High Street, RotherhamNoted
  5. Rotherham Economic Regeneration Fund - Centenary Markets - Redevelopment FeasibilityNoted
  6. Rotherham Economic Regeneration Fund - Work and Skills - Employer Portfolio and Business BriefingNoted

More from Rotherham Town Centres (to

All decisions
MeetingDecisionOutcome
22 Jun 2011 Exclusion of the press and public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... Decided Open
22 Jun 2011 Exclusion of the press and publicResolved :- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the m... Decided Open
22 Jun 2011 Minutes of a meeting of the Townscape Heritage Initiative Partnership held on 1st November, 2010Resolved :- That the contents of the minutes be noted. Noted Open
22 Jun 2011 Minutes of a meeting of the Health, Welfare and Safety Panel held on 9th July, 2010Agreed :- That Councillor R. S. Russell be re-appointed Chairman of the Health, Welfare and Safety Panel for the 2010... Agreed Open
22 Jun 2011 Proposals for the introduction of cashless parking in Rotherham Town Centre- (1) That approval be given for the system to be introduced for an initial trial period in selected locations with a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies