Rotherham Economic Regeneration Fund (RERF) - Public Realm - High Street, Rotherham

Noted Committee 1 paper

Regeneration and Development noted this item on Monday 2 December 2013. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

Resolved :- (1) That the report be received and its contents noted. (2) That a revenue contribution of £22,000 be allocated from the Rotherham Economic Regeneration Fund towards the cost of the public realm works on High Street, Rotherham.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Regeneration and Development, 3 pages

ROTHERHAM BOROUGH COUNCIL – REPORT TO MEMBERS

1. Meeting: Cabinet Member and Advisers for Regeneration and Development 2. Date: Monday 2nd December 2013

3. Title: RERF - High Street public realm

4. Programme Area: Environment and Development Services

5. Summary This report seeks approval of an allocation of £22,000 RERF revenue towards funding of public realm works on High Street as part of the Townscape Heritage Initiative (THI) programme.

6. Recommendations That £22,000 of RERF revenue is approved towards public realm works on High Street 7. Proposals and Details

The Rotherham Townscape Heritage Initiative (THI) scheme was established to help improve the historic buildings on High Street in the town centre. The scheme included complimentary proposals to carry out public realm improvements to both Minster Yard and High Street.

The aim of the initiative is to contribute to the wider regeneration of the town centre by returning this once bustling shopping street back to its former glory. This is being achieved by restoring the architectural features of the buildings, carrying out essential building repairs and reinstating traditional shop frontages to the properties.

The THI programme was funded by Heritage Lottery Fund (£1.145m), Yorkshire Forward (£1.5m) and Rotherham Borough Council (£1m) with a further £800k being invested by those property owners assisted by the programme.

Public Realm works in Minster Yard funded through Yorkshire Forward and THI have been completed, dramatically improving the setting of the Minster

The works to the High Street properties helping to bring vacant floor space back into use and so transforming this part of the town centre into a vibrant area attracting increased footfall.

The original THI programme had an allocation of £580,000 to develop and improve the public realm on High Street thus reinforcing the regeneration of the location and improving the setting of the retail units. Shop owners were encouraged to invest in their properties as part of a complete package of regeneration works, which included works to the public realm. However, these works were to be wholly funded through the Yorkshire Forward (YF) money and when YF were disbanded these funds were withdrawn leaving a gap in the budget for the public realm works

Officers continued to work up a scheme for the public realm which dramatically improves the quality of High Street but recognises the funding pressures which the Council has to deal with.

The Public Realm scheme has now been costed at £417,500 including professional fees

Funding has been identified from the following sources

1) SEEDS £40,000 2) RMBC capital programme £305,500 3) Local Transport Fund £25,000 4) Highways Maintenance £25,000

This leaves a £22,000 funding shortfall, which is being sought from RERF to specifically contribute towards ongoing professional fees. If the RERF funding is secured officers will immediately order materials to secure a discount from the supplier with a view to commencing works in April 2014. The works will take 20 weeks to complete. 8. Finance Status of funding. Approved/ Total Awaiting Funding Approval 2013/2014 2014/2015 2015/2016 RERF Capital - Revenue Awaiting 22,000 22,000 TOTAL RERF 22,000 - - 22,000

Other Funding Sources RMBC 50,000 255,500 305,500 SEEDS 20,000 20,000 40,000 LTF 25,000 25,000 Highways Maintenance 25,000 25,000 - TOTAL OTHER FUNDING 70,000 70,000 - 395,500 Grand Total 92,000 325,500 - 417,500

There is currently £50,000 of revenue money available under the RERF programme. This is sufficient to fund this project and leave £28,000 for the remainder of 2013/14

9. Risks and Uncertainties HLF still have to agree that the works can be carried out by RMBC, although as their quote is considerably lower than the only private sector company that tendered then this is not expected to be a problem

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rotherham Economic Regeneration Fund (RERF): Public Realm: High Street, RotherhamReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Rotherham Economic Regeneration Fund (RERF) - Public Realm - High Street, RotherhamThis decision
  2. Rotherham Economic Regeneration Fund - Allocation of FundingNoted
  3. Rotherham Economic Regeneration Fund - Rotherham Growth FundNoted
  4. Rotherham Economic Regeneration Fund - Centenary Markets - Redevelopment FeasibilityNoted
  5. Rotherham Economic Regeneration Fund - Work and Skills - Employer Portfolio and Business BriefingNoted
  6. Rotherham Economic Regeneration Fund - Rotherham Development ProjectsNoted

More from Rotherham Regeneration and Development

All decisions
MeetingDecisionOutcome
2 Jun 2014 Minutes of the previous meetings held on 6th May 2014 and on 8th May 2014Resolved :- That the minutes of the meetings of the Cabinet Member and Advisers for Regeneration and Development, hel... Approved Open
2 Jun 2014 A633 Rotherham to Parkgate - Bus Priority MeasuresResolved :- (1) That the report be received and its contents noted. (2) That the principle of a bus and cycle only la... Noted Open
2 Jun 2014 Objections to Proposed Waiting Restrictions - Areas of Wellgate and Moorgate, RotherhamResolved :- (1) That the report be received and its contents noted. (2) That, after due consideration by Elected Memb... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Temple Crescent, BramleyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open
2 Jun 2014 Petition - Condition of the Carriageway - Cook Avenue, MaltbyResolved :- (1) That the petition and report be received and their contents noted. (2) That the lead petitioner be in... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies