Resolved
Resolved :- (1) That the contents of the report be noted. (2) That the relevant Ward Councillors be kept informed of progress with regard to the Fitzwilliam Estate District Heating Scheme.
Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 19 September 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the contents of the report be noted. (2) That the relevant Ward Councillors be kept informed of progress with regard to the Fitzwilliam Estate District Heating Scheme.
This report presents progress to the end of Month 04 on the 2011/12 Capital Programme, together with a forecast to the end of the financial year.
Details include schemes within the Housing Investment Programme (HIP), together with other Non HIP schemes for 2011/12.
At this stage in the financial year the HIP Programme is forecasting to outturn on budget.
That Cabinet Member receives and notes the content of this report. 7. Proposals and Details
7.1The 2011/12 HIP was approved by Cabinet on the 23rd February 2011 with a total programmed spend of £21,166,243. This total has now been uplifted to £21,305,243 to reflect additional resources now available for aids and adaptations.
7.2The 2011/12 Programme was drawn up in the anticipation that the 2010/11 Programme would be delivered on budget and that resource available in that year would be fully utilised, and prudential borrowing in excess of £5m would be drawn down as part of the resources used.
7.3However, spending within the 2010/11 was below Programme, primarily within the HCA New Build and Private Sector Regeneration. This led to a substantial under spend of £3.663m in 2010/11, as shown in the table below. The under spend was as a result of slippage in programmed works due primarily to adverse weather conditions during November to January, and a consequence of this is that additional spend will now fall into 2011/12.
7.4The slippage identified above is now resulting in a forecast over spend of £2.185m on the original Programme level for 2011/12 as shown in the table below.
7.5However, the resources not drawn down in 2010/11 are, in the main, still available to be carried forward into 2011/12. This will result in a revised Programme level of £23.490m which would be fully resourced.
Outturn Original Forecast at Revised Estimates P4 Estimates 2010/11 2011/12 2011/12 2011/12 £000’s £000’s £000’s £000’s Approved Programme 50,378 21,166 21,305 23,490 Actual / Forecast Spend 46,715 21,305 23,490 23,490 Actual / Forecast Under / Over spend -3,663 +139 +2,185 0
7.6Details
7.6.1 The following paragraphs provide an overview of progress to date on the main spending heads within the HIP Programme:
7.6.2 Refurbishment and Improvements to Housing Revenue Account (HRA) Dwellings
It can be seen from Appendix A that a total of £9.648m is scheduled to be spent across public sector properties during 2011/12. The scheduled work is further analysed as follows:- Refurbishments
A total spend of £4.786m has been budgeted in 2011/12 to undertake refurbishment to properties and based upon activity to date the forecast outturn is £4.853m, a forecast overspend of £66k. This forecast overspend is off-set by a forecast saving of the same amount on other capital works, and is as a result of refining of scheme budgets.
Actual work scheduled includes:
• Window replacements • Roof replacements to 29 units in Maltby • External works to approx 268 units in Swinton • Internal works to approx 316 units - various areas across North Herringthorpe, Thrybergh and North Anston • Internal refurbs to approx 250 units - various areas across North Herringthorpe, Thrybergh and North Anston
This work has been allocated to Morrison and Willmott Dixon as part of the Repair and Maintenance Contract.
Delays were experienced in getting the earlier phases of some of the work to site due to
• The need to re-survey planned works due to inaccurate stock condition information as APEX, the stock condition database, was not updated to reflect work carried out during the earlier years of the Decent Homes Programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Investment Programme (HIP) 2011/12 and Other Capital SchemesReport | 10 pages | DownloadRead as text |
PDF |
MG: APPENDIX A: FINAL: P3: HIPAppendix | 1 pages | Download |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.